UK decommissioning programmes approved in 2026

Information accurate as of 4 November 2026 · Source: GOV.UK

14 decommissioning programmes for UK offshore installations and pipelines were approved between January and July 2026. Each page below summarises one programme: what is removed, how big the parts are, what stays in place and when the work is planned, with a link to the programme document on GOV.UK.

What is a decommissioning programme?

The document an operator submits to the regulator, setting out how offshore installations and pipelines will be decommissioned. In the UK, programmes are approved by the Offshore Petroleum Regulator for Environment and Decommissioning (OPRED) and published on GOV.UK. See decommissioning programme.

Programmes approved in 2026

#ProgrammeOperatorAreaApprovedMain figure
1Alba Northern topsidesIthaca Oil and GasCentral North SeaJanuary 202617,543 t topsides
2Ninian Southern topsides and upper jacketCNR InternationalNorthern North SeaFebruary 202639,574 t topsides and upper jacket
3Gannet A drilling mastUK North Sea LimitedCentral North SeaFebruary 2026145 t drilling mast
4Ravenspurn North compression deckPerenco UKSouthern North SeaFebruary 20263,187 t deck
5GPIII FPSO sailawayNEO NEXTCentral North SeaMarch 202630,870 t FPSO
6Leman 27J jacketPerenco UKSouthern North SeaMarch 20261,124 t jacket
7Trees: Birch, Larch and SycamoreSpirit EnergyCentral North SeaApril 20265,300 grout bags
8Pelican subseaTAQANorthern North SeaMay 2026287 t subsea structures
9North Cormorant upper jacketTAQANorthern North SeaMay 2026Approx. 12,500 t upper jacket
10South Magnus and Magnus Swift wellsEnQuestNorthern North SeaJune 2026280 t wellheads and trees
11Atlantic and Cromarty subseaShell and HessOuter Moray FirthJune 2026203.6 t manifold
12Leman Southwest wellPerenco UKSouthern North SeaJuly 2026232.68 t equipment
13Kestrel and Falcon subseaTAQANorthern North SeaJuly 2026Approx. 794 t subsea installations
14Hudson subseaTAQANorthern North SeaJuly 2026333.9 t manifold

By type

Topsides and decks

Jackets

Floating production

Subsea and wells

Programmes under consideration

At the time of checking, GOV.UK also listed 19 draft programmes under consideration. They are not covered here until they are approved.

Learn more about decommissioning

Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey.

Explore the training

List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).

Contains public sector information licensed under the Open Government Licence v3.0.

Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.