Leman Southwest well and pipeline sections decommissioning programmes

Approved July 2026 · Information accurate as of 4 November 2026 · Source: programme document on GOV.UK

The Leman Southwest 53/02a-15Y WHPS and PL3731 & PLU3732 Pipeline Sections Decommissioning Programmes were approved in July 2026. The operator, Perenco UK Limited, plans to permanently abandon one subsea gas well in the UK Southern North Sea and remove the Xmas tree, wellhead, wellhead protection structure and short pipeline end sections, 232.68 tonnes in total. The work is planned over four years from the third quarter of 2026.

Key facts

ProgrammesLeman Southwest 53/02a-15Y WHPS and PL3731 & PLU3732 Pipeline Sections Decommissioning Programmes (two programmes)
OperatorsPerenco UK Limited (78.26%) and RockRose UKCS 10 Limited (21.74%)
ApprovedJuly 2026
LocationUK Southern North Sea, Leman South field, Block 53/02a, approx. 60 km north-east of Bacton Gas Terminal
Water depth37.2 m
ProductionFebruary 2015 to August 2021 (gas)
Well1 subsea gas well, 53/02a-15Y
What is removedXmas tree 17.56 tonnes, wellhead 18.8 tonnes, wellhead protection structure 24.11 tonnes, mattresses, and up to 16 m of the 6 inch gas line PL3731 and 10 m of the 4 inch umbilical PLU3732: 232.68 tonnes in total
What staysThe rest of PL3731 and PLU3732, for a later programme. The neighbouring well 53/02a-14A stays in production
Protected areaInside the Southern North Sea SAC
Planned scheduleFour years from Q3 2026

What is being removed?

37.2 mPIPELINEends cut, rest laterXMAS TREEremovedwell pluggedNot to scale
Simple drawing, not to scale. The Xmas tree, wellhead and pipeline ends (blue) are removed and the well plugged. The rest of the pipeline (grey) waits for a later programme.
  • Xmas tree: 17.56 tonnes
  • Wellhead: 18.8 tonnes, including 4.2 tonnes of conductor
  • Wellhead protection structure: 24.11 tonnes
  • Up to 5 fronded mattresses of approx. 10 tonnes each
  • Up to 16 m of the 6 inch gas line PL3731 and up to 10 m of the 4 inch umbilical PLU3732
  • Up to 10 more mattresses of approx. 12 tonnes each, and an umbilical ramp

All 232.68 tonnes are planned to come ashore.

Well

The well 53/02a-15Y produced gas from February 2015 and was shut in in August 2021. The well is permanently abandoned, and the conductor is cut 3 m below the seabed.

What stays in place?

The rest of the gas line PL3731 and the umbilical PLU3732 stay for a later programme. The neighbouring well 53/02a-14A stays in production.

How will the work be done?

Divers close the valves. The lines are cut to leave a gap, and the equipment is lifted to the vessel deck. A danger buoy marks the site for up to one year.

When will the work happen?

  1. 1968: Leman South discovered
  2. February 2015: well starts producing
  3. August 2021: well shut in
  4. Q3 2026: start of the four-year plan

What happens to the materials?

The material is landed in the UK. The subsea control module, instruments and interface plates will be reused.

Link to the official government decommissioning programme

Leman Southwest 53/02a-15Y WHPS and PL3731 & PLU3732 Pipeline Sections Decommissioning Programmes (PDF, GOV.UK)

Perenco UK Limited, final version June 2026, approved July 2026. This page summarises pages 8 to 36.

Key terms

Xmas tree
The assembly of valves on top of a wellhead that controls the flow from a well.
Wellhead
The equipment at the top of a well that supports the well casing and the Xmas tree.
Conductor
The first and widest pipe set into the seabed at the top of a well.
Umbilical
A bundle of hoses and cables that carries power, control signals and chemicals to subsea equipment.
Plug and abandonment (P&A)
Sealing a well permanently with barriers, usually cement, so that the well can no longer flow. See well plug and abandonment.
Special Area of Conservation (SAC)
A protected area for important habitats or species.

Other programmes approved in 2026

Learn more about decommissioning

Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including well plug and abandonment.

Explore the training

Source. Leman Southwest 53/02a-15Y WHPS and PL3731 & PLU3732 Pipeline Sections Decommissioning Programmes, Perenco UK Limited, final version June 2026, approved July 2026: programme document (PDF, GOV.UK), pages 8 to 36.

List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).

Contains public sector information licensed under the Open Government Licence v3.0.

Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.