Well Plug and Abandonment: Carbon Capture and Storage (CCS) Considerations

Well decommissioning, commonly known as well plug and abandonment (P&A), permanently seals a well at the end of the well’s life.

Based on the CCS Considerations in Well P&A moduleTaught by Emma Dawson, Equinor
800 m

is the depth below which CO2 storage is generally expected to take place. Below approx. 800 m, CO2 is normally in a dense, liquid or supercritical, state.

IPCC (2005)
50 million tonnes

of CO2 injection capacity a year is the target the EU must reach by 2030 under the Net-Zero Industry Act.

Regulation (EU) 2024/1735
1960s to 1990s

Many legacy wells from this period were probably not abandoned to today’s standards.

Lean Decom training
44

oil and gas companies were named by the European Commission in May 2025 to provide CO2 injection capacity in the EU by 2030.

European Commission
Quick answer

How does CO2 storage (CCS) change well decommissioning?

Where a reservoir may later store carbon dioxide (CO2), oil and gas wells are plugged and abandoned with the future CO2 in mind. The permanent barriers are set below the minimum safe abandonment depth calculated with a CO2 gradient, zones that CO2 injection could repressurise are considered, older wells are assessed, and every plug is recorded for future carbon capture and storage (CCS) developers.

Where this applies: The subsurface principles on this page apply to offshore wells in any region. The phase names, barrier lengths, guidelines and regulations are UK and EU examples. Other countries have their own regulator, rules and terms.

Key points

  • CO2 is normally stored deeper than approx. 800 m, where the CO2 stays in a dense state.
  • The barriers that isolate a zone are set below the minimum safe abandonment depth (MSAD), calculated with a CO2 gradient for a CO2 store.
  • CO2 injection can change which zones need a barrier.
  • In legacy wells from the 1960s to the 1990s, typically only the reservoir was isolated.
  • Record every plug depth and plug thickness on the abandonment schematic.
  • Wells and subsurface teams must check flow zones against plug depths together.
The basics

How does well decommissioning work?

Oil and gas sit in porous reservoir rock, sealed by a cap rock: a fine-grained rock of very low permeability that stops fluids moving up and out of the reservoir. Drilling a well leaves a hole through that cap rock.

Well decommissioning, commonly known as well plug and abandonment (P&A), places permanent barriers inside the well to restore the seal, so that fluids stay in the reservoir and do not flow to the seabed or between rock layers.

The reservoir is not empty when a well is abandoned: often more than 60% of the hydrocarbons are still in the ground. See the well plug and abandonment page for the full process.

A cement plug from well plug and abandonment restores the cap rock seal above a reservoir that may later store CO2
A cement plug restores the seal. The abandonment barrier closes the hole that the well left in the cap rock.From the training: Well-Safe Solutions, Wells and Subsurface Fundamentals
Why CCS changes well decommissioning

A reservoir abandoned today may store CO2 in future, and CO2 injection can change the pressure and the contents of the zones being abandoned now. UK example: when deciding whether to consent to a well abandonment, the North Sea Transition Authority (NSTA) is likely to consider whether the well has a further potential use, such as carbon storage, and, for wells in strata with potential for carbon storage, the materials and techniques to be used to prevent leakage.

Methods

What are the main well decommissioning methods?

For a well in a possible future CO2 store, the training highlights where the barriers must sit, the casing and cementing requirements to check, and what must be recorded.

StepWhat happens
Suspension of the live wellA cement barrier in the production tubing, often called a tailpipe plug, stops the flow. A second barrier is added, such as a weighted fluid column, a mechanical barrier or a downhole safety valve.
AB1 Reservoir isolationThe completion is often removed so that a double barrier can be set above the reservoir, against verified cap rock, and against casing and annular cement judged fit for purpose.
AB2 Intermediate zone isolationIf required, further double barriers isolate other zones with flow potential in the overburden. A shallow environmental barrier may be set where contaminated fluids need to be contained in the well.
AB3 Wellhead removalThe wellhead is cut and recovered with abrasive, explosive or mechanical cutters. In the UK, the cut is often 3 m below the mudline. See wellhead and conductor removal.

Steps as taught in the Lean Decom training. AB1, AB2 and AB3 are well status codes used by the UK regulator, the NSTA. See well abandonment phases for each step in detail.

Materials

Cement and alternatives

A plug is usually cement: well understood, tried and tested, and low in cost. Alternatives include bismuth, resin, some mechanical plugs and shale as an annular barrier.

Technique

Cased hole or through-tubing

Cased hole abandonment is the standard method. Through-tubing abandonment leaves the tubing in place to save time and cost, but verification by logging is less certain.

Equipment

Rigs, units and vessels

Platform wells use the platform rig or a hydraulic workover unit. Subsea wells use a drilling rig or a light well intervention vessel.

Guidelines

What do well decommissioning guidelines say? A UK example

The training uses the UK as the example: the regulations set the goal, and the industry guidelines set out good practice. Other countries have their own regulator, rules and guidelines.

UK regulations

The Offshore Installations and Wells (Design and Construction, etc.) Regulations 1996 require that, so far as is reasonably practicable, there can be no unplanned escape of fluids from a well, or from the reservoir the well led to, after abandonment. See OPRED and UK decommissioning regulation.

UK industry guidelines

The training describes the Offshore Energies UK (OEUK) Well Decommissioning Guidelines as largely goal-setting: the aim is long-term containment of fluids, supported by subsurface studies. Operators can therefore apply the ALARP principle (as low as reasonably practicable), weighing risk reduction against technology, time and cost.

OEUK’s supplementary guideline for CO2 storage clarifies, in OEUK’s summary, that barriers must prevent CO2 migrating outside the storage complex, not only to the seabed or surface.

Which zones need a barrier (OEUK workflow)

  • Water-bearing and significantly overpressured: a barrier against flow is needed.
  • Water-bearing and not abnormally pressured: no abandonment plug is required.
  • Hydrocarbon-bearing: a barrier is required if sustained flow potential is proven.

A zone that needs no barrier today may need one if CO2 injection later changes the pressure or the fluid in that zone.

UK requirementAs taught in the training
Double barrierTwo barriers, each 100 ft (approx. 30 m) of good cement, between a zone with sustained flow potential and surface. Usually 500 ft of cement is pumped for each.
Combination barrierOne barrier of 200 ft (approx. 61 m) of good cement. Usually 800 ft of cement is pumped.
VerificationAnnular cement checked by records and logs. Internal plugs tagged and pressure tested, usually to 500 psi (approx. 34 bar) above the fracture strength at that depth.

What CCS adds: the checks

Know the minimum safe abandonment depth, calculated for CO2.
Check the casing and cementing requirements.
Document the abandonment schematic, with every plug depth and plug thickness.
Make sure the wells team speaks to the subsurface team.

The key takeaways from the CCS module of the Lean Decom training.

Carbon capture and storage

What is carbon capture and storage (CCS)?

CCS captures carbon dioxide (CO2) at industrial plants, transports the CO2 and injects the CO2 into deep rock formations for permanent storage.

Diagram of the CCS chain: CO2 capture at an industrial plant, transport by ship, and permanent storage in a reservoir below the seabed
The CCS chain. Capture, transport, then permanent storage in a reservoir, in this Equinor diagram 1,000 to 3,300 m below the seabed.From the training: Equinor, Introduction to CCS

In the Equinor example in the training, CO2 from industrial plants, such as cement works or steelworks, is compressed, moved by ship, received onshore and exported by pipeline to offshore reservoirs. Pipeline, rail and road are other transport options.

CO2 storage is not a new idea

At the Sleipner field in the North Sea, the Equinor example shown in the training, CO2 injection started in 1996.

EU example: oil and gas producers must provide CO2 injection capacity

Under the EU Net-Zero Industry Act (Regulation (EU) 2024/1735), the EU aims for at least 50 million tonnes a year of CO2 injection capacity by 2030. In May 2025, the European Commission named 44 oil and gas companies that must contribute, each in proportion to the company’s share of EU oil and gas production from 2020 to 2023. Depleted oil and gas fields count as storage sites, so a well abandoned today may later sit inside a CO2 store.

Storage depth

Why is CO2 stored deeper than approx. 800 m?

CO2 is injected in the supercritical phase: neither a liquid nor a gas. Supercritical CO2 has a liquid-like density, which makes efficient use of the pore space.

Below approx. 800 m, the pressure and temperature underground normally keep CO2 in a liquid or supercritical state.

Depth matters for well decommissioning in a second way: the barriers in every well that reaches the store must sit deep enough for the rock to hold the pressure of the CO2.

CO2 injected through a well below the cap rock into porous rock for storage
CO2 stored deep underground. The CO2 sits in porous rock below a cap rock. In a depleted field, the cap rock is the seal that held the oil and gas.From the training: Equinor, CCS Considerations in Well P&A
The technical requirement

What is the minimum safe abandonment depth (MSAD) for CO2 storage?

The minimum safe abandonment depth is the depth above which the cap rock is not strong enough to withstand the pressure from the fluids below. For a future CO2 store, those fluids include the injected CO2.

If CO2 is injected into a formation that is too shallow, the pressure could fracture the formation and form a leak path into the overburden (the rocks above), or even up to the seabed.

Abandonment plugs must therefore be set below the MSAD. The MSAD needs to be calculated for every well being abandoned now, and also considered for the old legacy wells in the field.

How to find the MSAD graphically

Plot pressure against depth

Depth on the vertical axis, pressure on the horizontal axis. The plot shows the overburden pressure and the formation breakdown pressure: the pressure at which the rock fractures.

Start at the maximum reservoir pressure

Mark the maximum reservoir pressure at the depth of the reservoir.

Extend a CO2 gradient upwards

Use a CO2 fluid gradient, because CO2 is the fluid that will be injected.

Read across to the depth axis

Where the CO2 line meets the formation breakdown pressure, read across to the depth. That depth is the MSAD. Plugs below this line are suitable for CO2 injection.

Pressure against depth plot with a CO2 gradient from reservoir pressure meeting the formation breakdown pressure at the MSAD
The MSAD for CO2. The CO2 gradient rises from the reservoir pressure until the gradient meets the formation breakdown pressure.From the training: Equinor, MSAD Calculation
Note

The MSAD depends on the fluid. In the plot shown in the training, the MSAD for the CO2 gradient is deeper than the MSADs for the oil and water gradients, and shallower than the MSAD for the gas gradient. An abandonment designed for oil or water may therefore not be deep enough for CO2.

Want the full method? The minimum safe abandonment depth page explains pore pressure and fracture gradient plots, isolation windows and how the fluid gradient changes the MSAD.

Free information pack

Get your information pack

Course details and free sample lessons, emailed to you.

The risk

Why are legacy wells a risk for CO2 storage?

Older wells in a field may not have every flowing formation above the reservoir isolated. Near a CO2 injection site, such a well is a possible leak path.

Many legacy wells from the 1960s to the 1990s were probably not abandoned to today’s strict standards. Back then, typically only the reservoir was isolated, and the potential flowing units above the reservoir were not considered.

Reservoirs are typically sandstones, but further sandstones may sit higher up the well. In older wells, those higher sandstones may have no plugs across them.

Legacy wells near a future CO2 injection site must therefore be evaluated, and remediated where needed. In the EU, the assessment of a storage site must cover wells that could provide leakage pathways (Directive 2009/31/EC). In the UK, OEUK describes the guideline on legacy wells as covering the wider storage complex and any well that may see a pressure increase, including wells outside the CO2 plume.

Lessons learned

Why do well records matter for future CCS?

Future CCS developers have to find and read the records of wells drilled decades ago. Some old wells have good data. Some have none.

The lesson for wells being abandoned now is to document the zones with flow potential and the abandonment schematic properly, and to make the records available in the public domain. UK example: licensees report well data to the National Data Repository (NDR) held by the North Sea Transition Authority, which may disclose reported information at once or after a specified period.

The training gives two reasons for good records: governments are starting to require the records, and good records reduce the cost of any later CCS project on the same reservoir.

What to record for every abandoned well

The depth and thickness of every plug.
Every zone with flow potential, marked against the plug depths.
A clear abandonment schematic that brings the plugs and zones together.
Records made available in the public domain.

Wells and subsurface teams must work together

Wells teams need to talk to subsurface teams, so that the units with flow potential are highlighted against the planned plug depths. Without that check, details can be missed or misunderstood.

A useful shared tool, taught in the Well-Safe Solutions module, is the plumbing diagram: a simple drawing that puts the simplified geology next to the simplified well design. The plumbing diagram lets both teams see how fluids could move, vertically and sideways.

Plumbing diagram showing eight wells against the rock formations, with the MSAD marked as a red line and a cross flow path between zones
A plumbing diagram. Wells, formations, plugs and the MSAD on one page, so both teams see the same picture.From the training: Well-Safe Solutions, Subsurface Basis of Design
Learn this in the training

CCS considerations in the Lean Decom training

Three modules cover CCS, the subsurface work behind every abandonment and the tools used offshore. The case studies are from the North Sea; the subsurface principles apply in any offshore region.

CCS Considerations in Well P&A module
Wells

CCS Considerations in Well P&A

CO2 storage, the minimum safe abandonment depth, legacy well risks and the lessons learned.

Taught by Emma Dawson, Equinor
Subsurface and Well P&A module
Wells

Subsurface and Well P&A

What needs to be isolated underground, and how abandonment barriers are planned, placed and verified.

Taught by Ruth Thomas, Well-Safe Solutions
Specialised Tooling module
Safety, tools and lessons learned

Specialised Tooling

The tools used in well P&A and removal work, from rigless abandonment to wellhead cutting.

Taught by David Ledingham, Claxton

Explore the training options →

Glossary

CCS and well plug and abandonment terms

Carbon capture and storage (CCS)
Capturing CO2 at industrial plants, transporting the CO2 and injecting the CO2 into deep rock formations for permanent storage.
Well decommissioning
The permanent plugging and abandonment (P&A) of a well, so that subsurface fluids stay contained. In UK usage, the term also covers removal of the wellhead.
Cap rock
A rock of very low permeability above a reservoir that acts as a seal and stops fluids flowing out of the reservoir.
Storage complex
The CO2 storage site and the surrounding geological domain that can affect storage integrity and security (EU Directive 2009/31/EC).
Supercritical CO2
CO2 at a pressure and temperature where the CO2 is neither a liquid nor a gas, and has a liquid-like density.
Minimum safe abandonment depth (MSAD)
The depth above which the cap rock cannot withstand the pressure from the fluids below.
Formation breakdown pressure
The pressure at which a rock formation fractures.
CO2 gradient
The change in pressure with depth in a column of CO2.
Legacy well
An older well in a field. Many legacy wells from the 1960s to the 1990s were probably not abandoned to today’s standards.
Abandonment schematic
A drawing of an abandoned well showing the plugs, with the depth and thickness of each plug.
Sources

Sources and further reading

  1. Lean Decom training: CCS Considerations in Well P&A module, taught by Emma Dawson, Equinor.
  2. Lean Decom training: Subsurface and Well P&A module, taught by Ruth Thomas, Well-Safe Solutions.
  3. UK: The Offshore Installations and Wells (Design and Construction, etc.) Regulations 1996, regulations 13 and 15. legislation.gov.uk
  4. UK: North Sea Transition Authority, UKCS Well Applications and Consents Guidance, January 2026, and UK National Data Repository (NDR).
  5. UK: Offshore Energies UK (OEUK), Well Decommissioning Guidelines, Issue 7 (as described in the training), and Well Decommissioning and Legacy Well Assessment for CO2 Storage, Issue 2 (OEUK’s published summary). oeuk.org.uk
  6. EU: Regulation (EU) 2024/1735 (Net-Zero Industry Act), Articles 20 and 23, and the European Commission news of 22 May 2025 naming the 44 companies.
  7. EU: Directive 2009/31/EC on the geological storage of carbon dioxide, Article 3 and Annex I. eur-lex.europa.eu
  8. Intergovernmental Panel on Climate Change (IPCC), Special Report on Carbon Dioxide Capture and Storage, 2005: Summary for Policymakers and Technical Summary.
FAQ

CCS considerations in well plug and abandonment: common questions

What is well decommissioning?

Well decommissioning is the permanent plugging and abandonment (P&A) of an oil or gas well at the end of the well’s life. Permanent barriers, usually cement, restore the cap rock seal and isolate each zone with flow potential, so that fluids do not flow to the seabed or between rock layers.

What are the main well decommissioning methods?

A live well is first suspended. The reservoir is then isolated, other zones with flow potential are isolated if required, and the wellhead is cut and recovered. In the UK, these three steps are called AB1, AB2 and AB3. Cement is the usual barrier material, and cased hole abandonment is the standard technique.

What guidelines apply to well decommissioning in the UK?

The Offshore Installations and Wells (Design and Construction, etc.) Regulations 1996 require that, so far as is reasonably practicable, there can be no unplanned escape of fluids from a well or from the reservoir the well led to. The training describes the OEUK Well Decommissioning Guidelines as largely goal-setting, with a focus on long-term containment supported by subsurface studies and the ALARP principle.

What does MSAD mean in well abandonment?

MSAD stands for minimum safe abandonment depth: the depth above which the cap rock is not strong enough to withstand the pressure from the fluids below. The barriers that isolate a zone are set below the MSAD for that zone. For a future CO2 store, the MSAD is calculated with a CO2 gradient.

See MSAD explained.

What well data is needed for CCS?

Future CCS developers need the depth and thickness of every plug, and every zone with flow potential marked against the plug depths, on a clear abandonment schematic that is available in the public domain.

Why are legacy wells a risk for CO2 storage?

Many legacy wells from the 1960s to the 1990s were probably not abandoned to today’s standards. Typically only the reservoir was isolated, so flowing zones above the reservoir may have no plugs. Legacy wells near a future CO2 injection site must be evaluated and, where needed, remediated.

Free information pack

Get your information pack

Course details and free sample lessons, emailed to you.

Take the training

Learn well decommissioning and CCS from the people who do the work

Lean Decom is a specialist decommissioning training provider. The training shares lessons from North Sea projects, taught by 18 specialists, for you to apply to your own work.

Online and video-basedECITB-approved course availableFree Preview available
Scroll to Top
Secret Link