UK Well Abandonment Phases: AB1, AB2 and AB3 Explained
Offshore wells are plugged and abandoned in stages: the live well is suspended, the reservoir is isolated, any other zones with flow potential are isolated, and the wellhead is removed.
of cement is usually pumped to place 100 ft of good cement in the well.
Lean Decom trainingabove the fracture strength is a common pressure test for an internal cement plug.
Lean Decom trainingof good cement, or one 200 ft combination barrier: the UK guideline for a double barrier.
NSTA, citing the OEUK guidelines (UK example)below the seabed, at least: the depth to which OPRED requires the well origin to be removed in the UK.
NSTA, UKCS Well Applications and Consents Guidance, January 2026What are the phases of well abandonment?
A well is plugged and abandoned in stages. First, the live well is suspended with a barrier in the production tubing and a second barrier. The reservoir is then isolated with a double barrier against verified cap rock. Any other zones with flow potential are isolated next, if required. Last, the wellhead is cut and recovered, often 3 m below the mudline, and the well is permanently abandoned. In the UK, the last three stages are known as AB1, AB2 and AB3.
Where this applies: The sequence of work applies to offshore wells in any region. The codes AB1, AB2 and AB3 are UK well status codes, and the barrier lengths and case studies are UK North Sea examples. Other countries have their own regulator, rules and terms.
Key points
- Suspension comes first. A suspended well can still be re-entered.
- Reservoir isolation (AB1 in the UK) sets a double barrier above the reservoir.
- Intermediate zone isolation (AB2) is carried out only if required.
- Plugs are tagged and pressure tested, usually to 500 psi above the fracture strength.
- Wellhead removal (AB3) cuts the wellhead, often 3 m below the mudline.
- UK example: a double barrier is two barriers of 100 ft of good cement, or one 200 ft combination barrier.
What is the plug and abandonment process, step by step?
Planning comes first: the subsurface basis of design decides which zones must be isolated, and well engineering turns that plan into operational steps. The work in the well then follows four stages.

Suspend the live well
A barrier in the production tubing stops the flow, and a second barrier backs the first.

Reservoir isolation
The completion is often removed, then a double barrier is set above the reservoir.

Intermediate zones
If required, a further double barrier isolates another zone with flow potential.

Wellhead removal
The wellhead is cut below the mudline and recovered. The well is now permanently abandoned.
Well schematics from the training: Well-Safe Solutions, Stages of Well Abandonment.
AB1, AB2 and AB3 are well status codes used by the North Sea Transition Authority (NSTA), which consents well suspension and abandonment in the UK. AB1: the reservoir has been permanently isolated. AB2: all required permanent isolation barriers, including environmental barriers, have been installed and verified. AB3: the well origin and the conductor have also been removed. In the NSTA guidance, a well at AB1 or AB2 is still classed as a suspended well, not an abandoned well.
Outside the UK, the sequence of work still applies. The codes and the consents differ by country.
How is a live well suspended?
Suspending the live well is the first operation. The aim is to stop hydrocarbons flowing out of the well and up to surface.
Set the tailpipe plug
A barrier, often called a tailpipe plug, is placed inside the production tubing.
Add a second barrier
The second layer of barrier can come from weighting up the fluid column in the well, from other mechanical barriers, or from a downhole safety valve.
Isolate at surface
The production tree, or a blowout preventer at surface, is another means of isolating the flow.


How is the reservoir isolated (AB1)?
Once the decision is taken to abandon the well permanently, the first job is to isolate the reservoir. In the UK, reservoir isolation is commonly known as AB1.
Remove the completion
The completion, and the packers that hold the completion in place, are often removed.
Verify the annular cement
The cement outside the casing must be verified as capable of preventing flow. Any remediation comes before the internal plugs are set.
Set the double barrier
A double barrier is placed above the reservoir, against verified cap rock, casing and annular cement.
Verify each plug
Each internal plug is tagged and pressure tested.
With the reservoir isolated, fluid can no longer flow from the reservoir into other zones or to surface.
When is intermediate zone isolation needed (AB2)?
After the reservoir is isolated, other zones in the overburden may also have flow potential and need isolating. In the UK, intermediate zone isolation is commonly called AB2. The stage is carried out only if required.
- A further zone with flow potential gets another double abandonment barrier in the overburden.
- If two zones need isolating, the second barrier for the reservoir is usually the first barrier for the intermediate zone.
- An environmental barrier can be set very shallow in the well, for example to contain contaminated fluids. The environmental barrier is not always needed.
The subsurface work decides whether an intermediate zone needs isolating. On EnQuest’s Heather platform, where an early bleed campaign brought an annulus down to zero pressure, no abandonment plug had to be set against that formation.

In one UK case, during shallow well operations to remove casing, a large gas bubble behind the casing had not been detected. The gas reached surface before the crew could close the blowout preventers. No one was harmed, but effective planning could have identified the risk and ensured the gas was contained.
From the Lean Decom training: Safety and Risk Management module.

How is the wellhead removed (AB3)?
The final stage of well abandonment is to cut and recover the wellhead, known in the UK as AB3. The cut is often made 3 m below the mudline, using abrasive, explosive or mechanical cutters. In the UK, the Offshore Petroleum Regulator for Environment and Decommissioning (OPRED) requires the well origin to be removed to at least 3 m below the seabed, unless OPRED agrees otherwise.
In a single-trip cut, a water abrasive cutting tool lands on the wellhead and severs all the casings. The vessel crane then pulls the wellhead free.
After the wellhead is removed, the well cannot generally be re-entered and is permanently abandoned. Platform wells also have conductors, which are removed after well abandonment. See wellhead and conductor removal.
What barriers are placed at each stage of P&A?
A plug, usually cement, only counts as a barrier when the plug is well supported and the casing, the annular cement and the formation around the plug are all sound.

| Stage | Barriers placed |
|---|---|
| Suspension | A barrier in the production tubing (the tailpipe plug), plus a weighted fluid column, a mechanical barrier or a downhole safety valve |
| Reservoir isolation (AB1) | A double barrier above the reservoir |
| Intermediate zones (AB2) | A double barrier for each further zone that needs isolating, plus an environmental barrier if needed |
| Wellhead removal (AB3) | No new barrier: the wellhead is cut and recovered |
UK example: a double barrier is two barriers of 100 ft of good cement, or one combination barrier of 200 ft. To place 100 ft of good cement, 500 ft is usually pumped. To place 200 ft, 800 ft is usually pumped.
The barriers that isolate a zone are set deeper than the minimum safe abandonment depth for that zone, where the cap rock can withstand the pressure from the reservoir fluids.


How are abandonment barriers verified?
Each barrier is verified. Verification covers the annular cement outside the casing and the internal plug inside the casing.
Review the cementing records
Check the volumes pumped, the time left for setting and curing, and the testing.
Log the annulus again if needed
A cement bond log (CBL) is often run when the well is drilled. Annular cement can degrade over time, so the cement quite commonly has to be verified again. In very old wells, the CBL may be run again, or a more modern ultrasonic tool used.
Punch and test
Holes are punched in the casing and a pressure difference is applied to measure any leak. Some wells need these extra checks, others do not.
Remediate first
Poor annular cement is remediated before the internal plugs are set, otherwise there is no rock-to-rock barrier.
Tag the plug
The plug is physically bumped to confirm the plug is in the right place and competent.
Pressure test the plug
The usual test is 500 psi above the fracture strength at that interval.


Get your information pack
Course details and free sample lessons, emailed to you.
Through-tubing or cased hole P&A: what is the difference?
Cased hole abandonment, with the tubing removed, is the standard method. Through-tubing abandonment leaves the production tubing in place. Through-tubing abandonment is still an emerging method on the UK Continental Shelf, but is expected to offer significant efficiency gains as the method becomes more established.
Through-tubing P&A, step by step
Set and test the tailpipe plug
A tailpipe plug at the bottom of the tubing is pressure tested, to give a good base for the abandonment plug.
Perforate the tubing
The tubing is perforated above the production packers.
Squeeze the cement
A balanced cement plug is squeezed into the base of the tubing and out into the A annulus, so the cement inside and outside the tubing is the same.
Tag and pressure test
The plug is tagged and pressure tested from inside the tubing.
The challenges of through-tubing P&A
- Less confidence in logging verification, for example in highly deviated wells or wells with decentralised casing.
- More difficult to remediate if the plug does not meet the requirements first time.
- Not yet fully established in the North Sea, although significant advances have been made.
| Cased hole P&A | Through-tubing P&A | |
|---|---|---|
| Tubing | Pulled before the plugs are set | Left in place |
| Cement placement | Inside the casing | Inside and outside the tubing |
| Time and cost | Standard | Can deliver major savings |
| Use in the North Sea | Standard method | Emerging |
Rig, rigless or light well intervention vessel: how is the work done?
The equipment depends on where the wells are and how much isolation work the wells need.

Platform rig or hydraulic workover unit
- A working platform rig can re-enter the wells and place the barriers. The rig may need upgrading.
- A hydraulic workover unit, a small-footprint unit, can replace the rig for plugging and abandonment.
- The conductors around the platform wells are removed after well abandonment.

Rig
- Subsea wells are often spread over a wide area and can be tied back to a manifold.
- A rig gives the heavy capability to set plugs in several zones and to cut and recover casing.

Light well intervention vessel
- Used where the isolation requirements allow a rigless approach.
- In the example below, a tool run from a vessel places the cement barriers before the wellhead is cut and recovered.
Rigless abandonment from a vessel: an example
A suspended well abandonment tool, as shown in the Lean Decom training.
Land the tool
The tool, 30 to 40 ft long in the example, is run from the vessel and landed on the wellhead, monitored by a remotely operated vehicle (ROV).
Perforate the casings
Explosive charges perforate the casings at depth. A drop in the pressure held between packers on the tool shows the perforation has worked.
Circulate the well clean
Cleanup fluids are pumped down, and the returns, including oil-based muds, come back up the tool to tanks on the vessel.
Place the cement
Cement pumped down the same tool places plugs in the annulus and environmental barriers in the intermediate casing. The tool is recovered while the cement cures, ready for wellhead removal.
Abandonment brings fluids back to surface: hydrocarbons left in the tubing, and fluids from behind the casing strings. On EnQuest’s Heather platform, the process plant was modified to handle these fluids offshore, so less fluid was shipped to shore. On a vessel, the returns can be stored in tanks and cleaned up on board.
Based on the Specialised Tooling and Decommissioning Overview modules.
How are wells sequenced and bundled in a P&A campaign?
On EnQuest’s Heather platform in the northern North Sea, 41 wells were plugged and abandoned in one continuous campaign of less than four years. The initial wells had been drilled in batches from 1977 to the mid-1980s.
The sequence used on Heather
Wells with structural concerns first
Wells with integrity issues that the structural team felt could affect the jacket were abandoned first.
Simpler wells next
A batch of simpler wells followed, so the rig crews and the asset team could bed in.
Difficult wells bundled
Wells needing the same technology, such as section milling, were packaged together. The equipment was rigged up once, used on several wells, then removed.
Simpler wells last
A final batch of simpler wells reduced the risk of slippage, because engineering down and clean and the last preparations for topsides removal cannot be completed until the wells are complete.
Planning lessons from Heather
- High-cost equipment was brought on board and rigged up once, then used on several wells.
- Bundling saved cost and time in the northern North Sea, where the weather is poor for most of the year.
- The five-yearly rig recertification was brought forward, to avoid a long stop during the campaign.
The well abandonment phases in the Lean Decom training
The training covers each phase with the specialists who plan and deliver the work. Each module is online and video-based, so you can learn at your own pace.

Subsurface and Well P&A
The stages of well abandonment, plugs and barriers, and verification.

Decommissioning Overview: Heather and Thistle case study
How a 41-well campaign was planned, sequenced and bundled.

Specialised Tooling
Rigless abandonment from a vessel, and the tools that cut and recover wellheads.
Well abandonment phase terms
- Suspended well
- A well with barriers in place that is not permanently abandoned. Suspending the live well is the first operation, and the well can still be re-entered.
- AB1
- UK well status code: the reservoir has been permanently isolated.
- AB2
- UK well status code: all required permanent isolation barriers have been installed and verified.
- AB3
- UK well status code: the well origin and the conductor have been removed.
- Tailpipe plug
- A barrier placed inside the production tubing to stop flow when a well is suspended.
- Environmental barrier
- A barrier set shallow in the well, for example to contain contaminated fluids.
- Through-tubing abandonment
- A P&A method that leaves the tubing in place and cements inside and outside the tubing.
- Light well intervention vessel
- A vessel used for rigless work on subsea wells, such as cutting and recovering a wellhead.
Sources and further reading
- Lean Decom training: Subsurface and Well P&A module, taught by Ruth Thomas, Well-Safe Solutions.
- Lean Decom training: Decommissioning Overview: Heather and Thistle case study, taught by Will Black and Ean Paul, EnQuest.
- Lean Decom training: Specialised Tooling module, taught by David Ledingham, Claxton.
- Lean Decom training: Safety and Risk Management module, taught by Graham Skinner, OEUK.
- North Sea Transition Authority (NSTA): UKCS Well Applications and Consents Guidance, January 2026. nstauthority.co.uk
- NSTA: Legacy Wells and Carbon Storage: a UK perspective, lessons learned and best practice. Presentation, November 2025. sodir.no
Well abandonment phases: common questions
What are the steps in the plug and abandonment process?
After the subsurface and well engineering planning, the live well is suspended, the reservoir is isolated, any intermediate zones are isolated if required, and the wellhead is cut and recovered. In the UK, the last three steps are known as AB1, AB2 and AB3.
What do AB1, AB2 and AB3 mean?
AB1, AB2 and AB3 are UK well status codes used by the North Sea Transition Authority (NSTA). AB1: the reservoir has been permanently isolated. AB2: all required permanent isolation barriers have been installed and verified. AB3: the well origin and the conductor have also been removed. The NSTA guidance does not define an AB0 code. The step before AB1 is the suspension of the well.
What is AB2 in well abandonment?
AB2 is a UK well status code used by the North Sea Transition Authority (NSTA). AB2 means all required permanent isolation barriers, including environmental barriers, have been installed and verified. No further work inside the well is needed. The well origin and the conductor may still have to be removed.
How are well abandonment barriers verified?
The annular cement is checked against the cementing records and, where needed, by logging or punching and testing. The internal plug is tagged and pressure tested, usually to 500 psi above the fracture strength at that depth.
What is through-tubing plug and abandonment?
Through-tubing P&A leaves the tubing in place and squeezes a balanced cement plug inside and outside the tubing. The method can save time and cost, but logging verification and remediation are harder.
Can wells be plugged and abandoned without a rig?
In some cases, yes. Where the isolation requirements allow, work on subsea wells can be done rigless from a light well intervention vessel. Wells that need plugs in several zones and casing recovery need heavier capability, such as a rig.
Related topics
Get your information pack
Course details and free sample lessons, emailed to you.
Learn each phase of well abandonment from the people who deliver the work
Lean Decom is a specialist decommissioning training provider. The training shares lessons from North Sea projects, taught by 18 specialists, for you to apply to your own work.