Pelican subsea facilities decommissioning programmes
The Pelican Subsea Facilities Decommissioning Programmes were approved in May 2026. The operator, TAQA Bratani Limited, plans to plug and abandon 16 subsea wells and remove 12 subsea structures (287 tonnes), along with 389 mattresses, 5,281 grout bags and 400 sandbags, from the Pelican field in the UK Northern North Sea. Buried pipelines stay in place with the ends cut.
Key facts
| Programmes | Pelican Subsea Facilities Decommissioning Programmes (three programmes) |
|---|---|
| Operator | TAQA Bratani Limited |
| Approved | May 2026 |
| Location | UK Northern North Sea, Block 211/26, approx. 105 km north-east of Shetland |
| Water depth | 154 m |
| Discovered | 1970 |
| First production | 1996 |
| Cessation of production | Q3 2024, with Cormorant Alpha |
| What is removed | 12 subsea structures (287 tonnes); spools, jumpers and surface-laid lines; the riser caisson; 389 mattresses; 5,281 grout bags; 400 sandbags; 4,046 tonnes of pipeline to shore |
| What stays | 2,528 tonnes of buried pipeline, 30,876 tonnes of rock and 2 drill cuttings piles |
| Wells | 16 subsea wells: 12 oil producers and 4 water injectors |
| Planned schedule | Well plugging 2025 to 2030; subsea removal 2026 to 2032 |
What is being removed?
12 subsea structures, 287 tonnes in total, approx. 85% steel:
- manifold: 19.2 m by 7.6 m by 4.2 m, 127.5 tonnes, on 4 steel piles cut 3 m below the seabed
- extension manifold: 22 tonnes, on a suction anchor
- W23 integrated structure: 52.9 tonnes
- subsea valve skid: 32 tonnes
- 2 subsea distribution units and 2 acid skids
- 4 concrete deflectors of 10 tonnes each
389 concrete mattresses (2,620 tonnes), 5,281 grout bags and 400 sandbags are also recovered, together with the spools, jumpers, surface-laid lines and a 0.212 km steel riser caisson at Cormorant Alpha.
Wells
The 16 subsea wells, 12 oil producers and 4 water injectors, are plugged and abandoned. The Xmas trees, wellheads and conductors are removed to at least 3 m below the seabed. The wells are plugged using a drilling rig or a well servicing vessel.
What stays in place?
Buried pipelines stay, with the ends cut and short exposed sections removed. Four main lines of approx. 8.5 km run to Cormorant Alpha. 2,528 tonnes of pipeline and 30,876 tonnes of existing rock stay. Two drill cuttings piles, 20,161 cubic metres in total, are below the OSPAR thresholds and are left to degrade naturally.
When will the work happen?
- 1970: field discovered
- 1996: first production
- Q3 2024: cessation of production
- 2025 to 2030: well plugging
- 2026: upper riser caisson removed
- 2026 to 2032: subsea removal
- 2032 to 2033: survey after removal
What happens to the materials?
4,046 tonnes of pipeline material comes ashore. No recycling percentage is given, and no yard has been chosen yet.
Link to the official government decommissioning programme
Pelican Subsea Facilities Decommissioning Programmes (PDF, GOV.UK)
TAQA Bratani Limited, final version April 2026, approved May 2026. This page summarises pages 8 to 56.
Key terms
- Manifold
- A subsea structure that gathers the flow from several wells into shared pipelines. See subsea infrastructure removal.
- Plug and abandonment (P&A)
- Sealing a well permanently with barriers, usually cement, so that the well can no longer flow. See well plug and abandonment.
- Xmas tree
- The assembly of valves on top of a wellhead that controls the flow from a well.
- Concrete mattress
- A flexible mat of concrete blocks laid over pipelines on the seabed to protect them and hold them in place.
- Grout bag
- A bag filled with grout, a cement mix, used to support or protect pipelines on the seabed.
- Drill cuttings pile
- A pile of crushed rock and drilling fluid on the seabed, left from drilling the wells.
Other programmes approved in 2026
Learn more about decommissioning
Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including subsea infrastructure removal.
Explore the trainingSource. Pelican Subsea Facilities Decommissioning Programmes, TAQA Bratani Limited, final version April 2026, approved May 2026: programme document (PDF, GOV.UK), pages 8 to 56.
List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).
Contains public sector information licensed under the Open Government Licence v3.0.
Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.