Pelican subsea facilities decommissioning programmes

Approved May 2026 · Information accurate as of 4 November 2026 · Source: programme document on GOV.UK

The Pelican Subsea Facilities Decommissioning Programmes were approved in May 2026. The operator, TAQA Bratani Limited, plans to plug and abandon 16 subsea wells and remove 12 subsea structures (287 tonnes), along with 389 mattresses, 5,281 grout bags and 400 sandbags, from the Pelican field in the UK Northern North Sea. Buried pipelines stay in place with the ends cut.

Key facts

ProgrammesPelican Subsea Facilities Decommissioning Programmes (three programmes)
OperatorTAQA Bratani Limited
ApprovedMay 2026
LocationUK Northern North Sea, Block 211/26, approx. 105 km north-east of Shetland
Water depth154 m
Discovered1970
First production1996
Cessation of productionQ3 2024, with Cormorant Alpha
What is removed12 subsea structures (287 tonnes); spools, jumpers and surface-laid lines; the riser caisson; 389 mattresses; 5,281 grout bags; 400 sandbags; 4,046 tonnes of pipeline to shore
What stays2,528 tonnes of buried pipeline, 30,876 tonnes of rock and 2 drill cuttings piles
Wells16 subsea wells: 12 oil producers and 4 water injectors
Planned scheduleWell plugging 2025 to 2030; subsea removal 2026 to 2032

What is being removed?

154 mPIPELINESburied, stayMANIFOLDremovedwells pluggedNot to scale
Simple drawing, not to scale. The manifold, Xmas trees and mattresses (blue) are removed and the wells plugged. Buried pipelines (grey) stay.

12 subsea structures, 287 tonnes in total, approx. 85% steel:

  • manifold: 19.2 m by 7.6 m by 4.2 m, 127.5 tonnes, on 4 steel piles cut 3 m below the seabed
  • extension manifold: 22 tonnes, on a suction anchor
  • W23 integrated structure: 52.9 tonnes
  • subsea valve skid: 32 tonnes
  • 2 subsea distribution units and 2 acid skids
  • 4 concrete deflectors of 10 tonnes each

389 concrete mattresses (2,620 tonnes), 5,281 grout bags and 400 sandbags are also recovered, together with the spools, jumpers, surface-laid lines and a 0.212 km steel riser caisson at Cormorant Alpha.

Wells

The 16 subsea wells, 12 oil producers and 4 water injectors, are plugged and abandoned. The Xmas trees, wellheads and conductors are removed to at least 3 m below the seabed. The wells are plugged using a drilling rig or a well servicing vessel.

What stays in place?

Buried pipelines stay, with the ends cut and short exposed sections removed. Four main lines of approx. 8.5 km run to Cormorant Alpha. 2,528 tonnes of pipeline and 30,876 tonnes of existing rock stay. Two drill cuttings piles, 20,161 cubic metres in total, are below the OSPAR thresholds and are left to degrade naturally.

When will the work happen?

  1. 1970: field discovered
  2. 1996: first production
  3. Q3 2024: cessation of production
  4. 2025 to 2030: well plugging
  5. 2026: upper riser caisson removed
  6. 2026 to 2032: subsea removal
  7. 2032 to 2033: survey after removal

What happens to the materials?

4,046 tonnes of pipeline material comes ashore. No recycling percentage is given, and no yard has been chosen yet.

Link to the official government decommissioning programme

Pelican Subsea Facilities Decommissioning Programmes (PDF, GOV.UK)

TAQA Bratani Limited, final version April 2026, approved May 2026. This page summarises pages 8 to 56.

Key terms

Manifold
A subsea structure that gathers the flow from several wells into shared pipelines. See subsea infrastructure removal.
Plug and abandonment (P&A)
Sealing a well permanently with barriers, usually cement, so that the well can no longer flow. See well plug and abandonment.
Xmas tree
The assembly of valves on top of a wellhead that controls the flow from a well.
Concrete mattress
A flexible mat of concrete blocks laid over pipelines on the seabed to protect them and hold them in place.
Grout bag
A bag filled with grout, a cement mix, used to support or protect pipelines on the seabed.
Drill cuttings pile
A pile of crushed rock and drilling fluid on the seabed, left from drilling the wells.

Other programmes approved in 2026

Learn more about decommissioning

Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including subsea infrastructure removal.

Explore the training

Source. Pelican Subsea Facilities Decommissioning Programmes, TAQA Bratani Limited, final version April 2026, approved May 2026: programme document (PDF, GOV.UK), pages 8 to 56.

List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).

Contains public sector information licensed under the Open Government Licence v3.0.

Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.

Scroll to Top
Secret Link