Gannet A drilling mast decommissioning programme

Approved February 2026 · Information accurate as of 4 November 2026 · Source: programme document on GOV.UK

The Gannet A Mast Decommissioning Programme was approved in February 2026. The programme covers the removal of the drilling mast, approx. 50 m high and approx. 145 tonnes, from the Gannet A platform in the UK Central North Sea. The mast is unsafe for plugging wells, so a hydraulic workover unit will replace the mast while the platform keeps producing. The programme planned all work to finish by the end of March 2026.

Key facts

ProgrammeGannet A Mast Decommissioning Programme
OperatorUK North Sea Limited (Field Operator from 1 December 2025). Programme prepared by Shell U.K. Limited
ApprovedFebruary 2026
LocationUK Central North Sea, Block 21/25, approx. 187 km east of Aberdeen
Water depth95 m
Jacket installedJune 1991
First productionOctober 1992
Field cessation of productionExpected in 2031
What is removedDrilling mast, approx. 145 tonnes and approx. 50 m high, plus drill floor equipment
What staysThe platform, jacket, wells and pipelines
Planned scheduleWork began November 2024; all work planned to finish by the end of March 2026
RecyclingOver 97% by weight expected to be recycled

What is being removed?

TOPSIDESstay in productionMASTremovedJACKETstays for now95 mNot to scale
Simple drawing, not to scale. The drilling mast (blue) is removed. The topsides and jacket (grey) stay in production.

The mast is a steel structure approx. 50 m high and approx. 145 tonnes, around 1% of the 14,634 tonne topsides. Four legs are pinned to the top of the drilling substructure. The mast tapers from 10 m by 10 m at the base to 3.5 m by 7.3 m at the hinge, approx. 15 m up, and to 2.5 m by 2.85 m at the top. The mast has not been used for drilling since 2005.

Drill floor equipment is removed at the same time:

  • the crown block and sheaves (the crown block weighs approx. 6 tonnes)
  • the doghouse
  • the iron roughneck
  • the draw-works
  • the choke and kill package
  • old winch lines

Why is the mast being removed?

The mast is inoperable and unsafe for well plug and abandonment. A hydraulic workover unit will replace the mast so that the wells can be plugged before cessation of production.

What stays in place?

The rest of the platform, the jacket, the wells, the pipelines and the subsea tie-backs stay for future programmes. The drilling equipment set, a skid base and a three-level substructure, also stays. The hydraulic workover unit will sit on top.

How will the mast be removed?

Piece small, with cold cutting preferred. The tools are the platform crane, a fixed A-frame to lower the crown block, and a floating pole.

When does the work happen?

  1. November 2024: work began
  2. March 2025: work paused
  3. November 2025: offshore work planned to finish
  4. End of March 2026: all work planned to finish
  5. 2031: field cessation of production expected

What happens to the materials?

Over 97% by weight is expected to be recycled. The material goes to a licensed UK dismantling site, with the onshore work done within six months.

Link to the official government decommissioning programme

Gannet A Mast Decommissioning Programme (PDF, GOV.UK)

Prepared by Shell U.K. Limited, final version 10 October 2025, approved February 2026. This page summarises pages 7 to 29.

Key terms

Drilling mast
The tall steel tower over a platform's well bay that carries the lifting equipment used for drilling and well work.
Plug and abandonment (P&A)
Sealing a well permanently with barriers, usually cement, so that the well can no longer flow. See well plug and abandonment.
Piece small
Cutting a structure into small pieces offshore and lifting the pieces with a platform or vessel crane.
Topsides
The decks and equipment that sit above the sea on an offshore platform. See topside preparation and removal.
Cessation of production (CoP)
The date a field permanently stops producing.

Other programmes approved in 2026

Learn more about decommissioning

Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including topside preparation and removal.

Explore the training

Source. Gannet A Mast Decommissioning Programme, prepared by Shell U.K. Limited, final version 10 October 2025, approved February 2026: programme document (PDF, GOV.UK), pages 7 to 29.

List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).

Contains public sector information licensed under the Open Government Licence v3.0.

Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.

Scroll to Top
Secret Link