Alba Northern Platform topsides decommissioning programme

Approved January 2026 · Information accurate as of 4 November 2026 · Source: programme document on GOV.UK

The Alba Northern Platform Topsides Decommissioning Programme was approved in January 2026. The operator, Ithaca Oil and Gas Limited, plans to remove the 17,543 tonne topsides of the Alba Northern Platform in the UK Central North Sea between mid-2028 and the end of 2032. The eight-leg steel jacket stays in place for a later programme.

Key facts

ProgrammeAlba Northern Platform Topsides Decommissioning Programme
OperatorIthaca Oil and Gas Limited (36.67% equity)
ApprovedJanuary 2026
LocationUK Central North Sea, Block 16/26a, approx. 210 km north-east of Aberdeen
Water depthApprox. 138 m
Platform installed1993
First oilJanuary 1994
Cessation of productionQ3 2026 (agreed)
What is removedTopsides: 17,543 tonnes, one integrated deck
What stays for nowEight-leg steel jacket, for a later programme
Wells31 platform wells: 25 oil production and 6 water injection
Planned removalMid-2028 to the end of 2032
Recycling targetMore than 95% recycled

What is being removed?

TOPSIDESremovedcutJACKETstays for now138 mNot to scale
Simple drawing, not to scale. The topsides (blue) are removed. The jacket (grey) stays for a later programme.

The programme covers the topsides of the Alba Northern Platform: one integrated deck with deck extensions, weighing 17,543 tonnes. The topsides include:

  • drilling modules, and a drilling derrick on skid rails over the well bay
  • an accommodation module for up to 144 people, with the central control room, helideck and lifeboats
  • a flare boom at the north end
  • process plant for separation, gas compression, water injection, produced water treatment and power generation

By weight, the topsides are 92.5% steel, 4.75% non-ferrous metal, 2.5% plastic and rubber, and 0.25% hazardous material. The cut between the topsides and the jacket is planned between elevation +13 m and +22 m.

What stays in place?

The eight-leg steel jacket stays in place for a later programme, together with the caissons, risers and umbilicals fixed to the jacket. Diesel tanks inside the jacket legs will be drained. The top of the jacket stays above sea level, and the 500 m safety zone and navigation aids are kept. The pipelines, the floating storage unit and the subsea equipment are covered by other programmes.

How will the topsides be removed?

The programme lists four removal options. The final method will follow a front-end engineering design (FEED) study and a tender.

  • Single lift by a single lift vessel or semi-submersible crane vessel
  • Modular lift, in sections
  • Piece small, cutting the topsides into small pieces offshore
  • A combination of these methods

When will the work happen?

  1. 1984: field discovered
  2. 1993: platform installed
  3. January 1994: first oil
  4. Q3 2026: cessation of production
  5. Mid-2028 to end of 2032: topsides removal window

What happens to the materials?

All 17,543 tonnes are planned to come ashore. The target is more than 95% recycled, less than 5% reused and less than 5% disposed of. The disposal yard has not been named, and a yard outside the UK is possible.

Link to the official government decommissioning programme

Alba Northern Platform Topsides Decommissioning Programme (PDF, GOV.UK)

Ithaca Oil and Gas Limited, final version 14 November 2025, approved January 2026. This page summarises pages 7 to 30.

Key terms

Topsides
The decks and equipment that sit above the sea on an offshore platform. See topside preparation and removal.
Jacket
The steel frame that holds a platform's topsides up from the seabed. See substructure removal.
Cessation of production (CoP)
The date a field permanently stops producing.
Decommissioning programme
The document an operator submits to the regulator, setting out how offshore installations and pipelines will be decommissioned. See decommissioning programme.

Other programmes approved in 2026

Learn more about decommissioning

Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including topside preparation and removal.

Explore the training

Source. Alba Northern Platform Topsides Decommissioning Programme, Ithaca Oil and Gas Limited, final version 14 November 2025, approved January 2026: programme document (PDF, GOV.UK), pages 7 to 30.

List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).

Contains public sector information licensed under the Open Government Licence v3.0.

Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.

Scroll to Top
Secret Link