Ninian Southern topsides and upper jacket decommissioning programmes
The Ninian Southern Topsides, Upper Jacket and Associated Riser Sections Decommissioning Programmes were approved in February 2026. The operator, CNR International (U.K.) Limited, plans to remove the 27,522 tonne topsides and the 12,052 tonne upper jacket of the Ninian Southern Platform in the UK Northern North Sea. The topsides are planned to come off between 2027 and 2029, and the upper jacket by 2030. The lower jacket and footings stay for a later programme.
Key facts
| Programmes | Ninian Southern Topsides, Upper Jacket and Associated Riser Sections Decommissioning Programmes (five programmes in one document) |
|---|---|
| Operator | CNR International (U.K.) Limited (100%) |
| Approved | February 2026 |
| Location | UK Northern North Sea, Block 3/8a, approx. 120 km east of Shetland |
| Water depth | 140 m |
| Platform installed | June 1977 |
| First production | December 1978 |
| Cessation of production | 30 June 2025 |
| What is removed | Topsides 27,522 tonnes in 28 modules; upper jacket 12,052 tonnes; riser sections 170.3 tonnes |
| What stays for now | Lower jacket, footings, drill cuttings pile and seabed pipelines, for later programmes |
| Wells | 42 platform wells |
| Planned removal | Topsides 2027 to 2029; upper jacket by 2030 |
| Recycling target | At least 95% reused or recycled |
What is being removed?
The programmes cover the topsides, the upper jacket, and the riser and umbilical sections inside the upper jacket. In total, 39,574 tonnes of installations come off. The topsides weigh 27,522 tonnes, in 28 modules over two levels on a module support frame. The modules include:
- wellhead, separation and main oil line pump modules
- power generation, gas compression, water injection and water treatment modules
- drilling modules and a derrick
- accommodation modules and a heliport
- two cranes and two flare booms
The upper jacket weighs 12,052 tonnes, of which 1,629 tonnes is marine growth. 15 riser and umbilical sections, from 2 inch to 24 inch, are removed with the upper jacket, weighing 170.3 tonnes.
What stays in place?
The platform stands on a four-leg welded steel jacket, 155 m high, on 32 grouted piles (8 per leg). The jacket is planned to be cut between 77 m and 87 m below Lowest Astronomical Tide, which is 53 m to 63 m above the seabed. A range is used so the cut can move if a cutting tool gets stuck.
The lower jacket, the footings, the drill cuttings pile and the seabed pipelines stay for later programmes.
How will the work be done?
- Topsides: modular lift by a heavy lift vessel, single lift by a single lift vessel, or piece small
- Upper jacket: heavy lift vessel or single lift vessel
- Only dynamic positioning vessels will be used, with no anchors
The choice of method is made through a tender. The programme notes that the upper jacket is too wide for a single lift by Pioneering Spirit, the only single lift vessel available.
When will the work happen?
- June 1977: platform installed
- December 1978: first production
- 30 June 2025: cessation of production
- 2027 to 2029: topsides removal
- By 2030: upper jacket removal
What happens to the materials?
The aim is to reuse or recycle at least 95% of the material, which comes ashore between 2027 and 2030. The disposal yard has not been chosen and could be in or outside the UK.
Link to the official government decommissioning programme
CNR International (U.K.) Limited, approved February 2026. This page summarises pages 10 to 64.
Key terms
- Topsides
- The decks and equipment that sit above the sea on an offshore platform. See topside preparation and removal.
- Jacket
- The steel frame that holds a platform's topsides up from the seabed. See substructure removal.
- Marine growth
- Sea life, such as mussels and seaweed, that builds up on structures under water and adds to their weight.
- Lowest Astronomical Tide (LAT)
- The lowest sea level that can be predicted. Heights and depths on offshore installations are often measured from LAT.
- Cessation of production (CoP)
- The date a field permanently stops producing.
Other programmes approved in 2026
Learn more about decommissioning
Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including topside preparation and removal.
Explore the trainingSource. Ninian Southern Topsides, Upper Jacket and Associated Riser Sections Decommissioning Programmes, CNR International (U.K.) Limited, approved February 2026: programme document (PDF, GOV.UK), pages 10 to 64.
List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).
Contains public sector information licensed under the Open Government Licence v3.0.
Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.