North Cormorant upper jacket decommissioning programmes

Approved May 2026 · Information accurate as of 4 November 2026 · Source: programme document on GOV.UK

The North Cormorant Upper Jacket and Associated Riser Sections Decommissioning Programmes were approved in May 2026. The operator, TAQA Bratani Limited, plans to remove the upper section of the 172 m tall North Cormorant jacket in the UK Northern North Sea, approx. 12,500 tonnes including marine growth, with removal planned between 2025 and 2027. The topsides were covered by a 2020 programme, and the footings are left for a later programme.

Key facts

ProgrammesNorth Cormorant Upper Jacket and Associated Riser Sections Decommissioning Programmes (six programmes)
OperatorTAQA Bratani Limited
ApprovedMay 2026
LocationUK Northern North Sea, Block 211/21a, 112 km from the nearest UK coast
Water depth161 m
Installed1981
First productionFebruary 1982
Cessation of productionJune 2024
What is removedUpper jacket, approx. 12,500 tonnes including approx. 700 tonnes of marine growth; upper sections of 4 rigid risers, 3 risers in J-tubes, 3 umbilicals and 9 cables
What stays for nowThe footings below approx. 116 m below LAT, and the drill cuttings pile
Whole jacketEight legs, 172 m tall, 20,052 tonnes without marine growth, piles or grout
Planned removal2025 to 2027; disposal 2026 to 2028
Recycling targetAround 95% recycled

What is being removed?

TOPSIDESalready removedcutUPPER JACKETremovedFOOTINGSstay for now161 mNot to scale
Simple drawing, not to scale. The upper jacket (blue) is removed. The footings (grey) stay for a later programme. The topsides were covered by an earlier programme.

The upper jacket runs from approx. 11 m above Lowest Astronomical Tide down to approx. 116 m below, which is approx. 45 m above the seabed. The section weighs approx. 12,500 tonnes: approx. 11,090 tonnes of steel, approx. 700 tonnes of marine growth and 15 tonnes of hazardous paint.

Two legs were used as diesel tanks, and four legs held drinking water, the larger tanks approx. 500 cubic metres each. Removed with the upper jacket:

  • 4 rigid risers, from 10 inch to 20 inch
  • 3 rigid risers in J-tubes, 8 inch
  • 3 umbilicals
  • 9 cables, including a 33 kV power cable

The whole jacket

North Cormorant stands on an eight-legged steel jacket with K-bracing, 172 m tall in 161 m of water. The jacket weighs 20,052 tonnes, not counting marine growth, piles or grout. 32 foundation piles, 8 at each corner leg, each approx. 2 m in diameter, hold the jacket in place. The corner legs are 6 m in diameter at the base, narrowing to 2 m at the top. The footprint at the seabed is 75 m by 77 m.

What stays in place?

The footings below approx. 116 m below Lowest Astronomical Tide and the drill cuttings pile stay for a later programme. The programmes describe the sub-structure as a candidate for derogation under OSPAR Decision 98/3.

How will the upper jacket be removed?

The programmes list three options. A contractor has been selected, but is not named.

  • A single lift by Pioneering Spirit's jacket lift system
  • A heavy lift vessel, in two sections
  • Two heavy lift vessels working together in a quad lift

When will the work happen?

  1. May 1974: field discovered
  2. 1981: platform installed
  3. February 1982: first production
  4. November 2020: topsides programme approved
  5. June 2024: cessation of production
  6. 2025 to 2027: topsides and upper jacket removal
  7. 2026 to 2028: disposal
  8. 2027 to 2029: survey of what is left

What happens to the materials?

The aim is to recycle around 95%. The yard has not been chosen and may be outside the UK.

Link to the official government decommissioning programme

North Cormorant Upper Jacket and Associated Riser Sections Decommissioning Programmes (PDF, GOV.UK)

TAQA Bratani Limited, final version December 2025, approved May 2026. This page summarises pages 7 to 43.

Key terms

Jacket
The steel frame that holds a platform's topsides up from the seabed. See substructure removal.
Footings
The lowest part of a large steel jacket, at the seabed, where the jacket is fixed to its piles. See substructure removal.
Marine growth
Sea life, such as mussels and seaweed, that builds up on structures under water and adds to their weight.
J-tube
A J-shaped tube fixed to a jacket that guides a riser or cable from the seabed up to the platform.
Derogation
Permission under OSPAR Decision 98/3 to leave part of a large installation, such as the footings of a heavy steel jacket, in place.
Lowest Astronomical Tide (LAT)
The lowest sea level that can be predicted. Heights and depths on offshore installations are often measured from LAT.

Other programmes approved in 2026

Learn more about decommissioning

Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including substructure removal.

Explore the training

Source. North Cormorant Upper Jacket and Associated Riser Sections Decommissioning Programmes, TAQA Bratani Limited, final version December 2025, approved May 2026: programme document (PDF, GOV.UK), pages 7 to 43.

List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).

Contains public sector information licensed under the Open Government Licence v3.0.

Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.