Trees (Birch, Larch and Sycamore) subsea decommissioning programmes
The Trees Decommissioning Programmes (Birch, Larch and Sycamore) were approved in April 2026. The operator, Spirit Energy North Sea Oil Limited, plans to remove the subsea manifolds, a wellhead and pipeline structures from the Birch, Larch and Sycamore fields in the UK Central North Sea, together with 568 mattresses and 5,300 grout bags. Trenched pipelines stay buried in place.
Key facts
| Programmes | Trees Decommissioning Programmes (Birch, Larch and Sycamore), seven programmes in one document |
|---|---|
| Operator | Spirit Energy North Sea Oil Limited (100%) |
| Approved | April 2026 |
| Location | UK Central North Sea, Block 16/12a, approx. 215 km north-east of Peterhead |
| Water depth | Approx. 125 m |
| Host platform | Subsea tie-backs to Brae Alpha |
| First production | Birch 1995, Larch 1998, Sycamore 2003 |
| Cessation of production | Birch 15 November 2020; Larch 24 January 2023; Sycamore notified as 6 April 2025 |
| What is removed | Birch manifold 109 tonnes; Larch manifold 63 tonnes; Sycamore wellhead and flowbase 10 tonnes; 9 pipeline structures; 3,145 tonnes of pipeline ends and spools; 568 mattresses; 5,300 grout bags; 18 covers |
| What stays | 8,144 tonnes of trenched pipelines, 38,168 tonnes of rock, piles cut 3 m below the seabed, and 2 drill cuttings piles |
| Pipelines and umbilicals | 54 |
| Planned removal | Q3 2024 to Q1 2027, with a window to the end of 2029 |
| Recycling target | More than 95% recycled |
What is being removed?
- Birch manifold: 109 tonnes, 20 m by 16 m by 3.5 m, gravity based
- Larch manifold: 63 tonnes, 12 m by 11.5 m by 3 m, on four piles cut 3 m below the seabed
- Sycamore well SW1 wellhead and flowbase: 10 tonnes
- A crossover bundle at Brae Alpha: 95 tonnes, 37.5 m long
- Larch wye pieces of 71, 24 and 12 tonnes
- Pipeline ends, spools, jumpers and surface-laid lines: 3,145 tonnes
568 concrete mattresses, 5,300 grout bags of 25 kg each and 18 protection covers are also lifted from the seabed.
What stays in place?
Pipelines trenched at least 0.6 m to the top of the pipe stay in place, 8,144 tonnes in all. This was the preferred option in the comparative assessment. The trenches are mostly 1 m to 2 m deep, and no snagging has been reported. 38,168 tonnes of rock stays, along with 2 drill cuttings piles that are below the OSPAR thresholds.
The risers and umbilical at Brae Alpha wait until Brae Alpha is decommissioned.
Pipelines and umbilicals
There are 54 pipelines and umbilicals: 27 at Birch, 10 at Larch and 17 at Sycamore. The Birch main lines are approx. 14 km long: the 10 inch production line (14.26 km), the 12 inch water injection line (13.92 km) and the 4 inch gas lift line (13.91 km).
When will the work happen?
- 1995: Birch production starts
- 1998: Larch production starts
- 2003: Sycamore production starts
- 15 November 2020: Birch cessation of production
- 24 January 2023: Larch cessation of production
- Q3 2024 to Q1 2027: removals, with a window to the end of 2029
What happens to the materials?
The target is more than 95% recycled, less than 5% reused and less than 5% disposed of. No yard is named.
Link to the official government decommissioning programme
Trees Decommissioning Programmes (Birch, Larch and Sycamore) (PDF, GOV.UK)
Spirit Energy North Sea Oil Limited, final version 3 March 2026, approved April 2026. This page summarises pages 8 to 62.
Key terms
- Manifold
- A subsea structure that gathers the flow from several wells into shared pipelines. See subsea infrastructure removal.
- Umbilical
- A bundle of hoses and cables that carries power, control signals and chemicals to subsea equipment.
- Concrete mattress
- A flexible mat of concrete blocks laid over pipelines on the seabed to protect them and hold them in place.
- Grout bag
- A bag filled with grout, a cement mix, used to support or protect pipelines on the seabed.
- Subsea tie-back
- A subsea field connected by pipelines to a platform some distance away, which processes the oil or gas.
- Comparative assessment
- A study that compares the options for decommissioning a pipeline or structure, looking at safety, environmental, technical, societal and economic factors.
Other programmes approved in 2026
Learn more about decommissioning
Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including subsea infrastructure removal.
Explore the trainingSource. Trees Decommissioning Programmes (Birch, Larch and Sycamore), Spirit Energy North Sea Oil Limited, final version 3 March 2026, approved April 2026: programme document (PDF, GOV.UK), pages 8 to 62.
List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).
Contains public sector information licensed under the Open Government Licence v3.0.
Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.