UK decommissioning programmes approved in 2026
14 decommissioning programmes for UK offshore installations and pipelines were approved between January and July 2026. Each page below summarises one programme: what is removed, how big the parts are, what stays in place and when the work is planned, with a link to the programme document on GOV.UK.
What is a decommissioning programme?
The document an operator submits to the regulator, setting out how offshore installations and pipelines will be decommissioned. In the UK, programmes are approved by the Offshore Petroleum Regulator for Environment and Decommissioning (OPRED) and published on GOV.UK. See decommissioning programme.
Programmes approved in 2026
| # | Programme | Approved |
|---|---|---|
| 1 | Alba Northern topsides | January 2026 |
| 2 | Ninian Southern topsides and upper jacket | February 2026 |
| 3 | Gannet A drilling mast | February 2026 |
| 4 | Ravenspurn North compression deck | February 2026 |
| 5 | GPIII FPSO sailaway | March 2026 |
| 6 | Leman 27J jacket | March 2026 |
| 7 | Trees: Birch, Larch and Sycamore | April 2026 |
| 8 | Pelican subsea | May 2026 |
| 9 | North Cormorant upper jacket | May 2026 |
| 10 | South Magnus and Magnus Swift wells | June 2026 |
| 11 | Atlantic and Cromarty subsea | June 2026 |
| 12 | Leman Southwest well | July 2026 |
| 13 | Kestrel and Falcon subsea | July 2026 |
| 14 | Hudson subsea | July 2026 |
By type
Topsides and decks
- Alba Northern topsides: 17,543 t topsides
- Ninian Southern topsides and upper jacket: 39,574 t topsides and upper jacket
- Gannet A drilling mast: 145 t drilling mast
- Ravenspurn North compression deck: 3,187 t deck
Jackets
- Leman 27J jacket: 1,124 t jacket
- North Cormorant upper jacket: Approx. 12,500 t upper jacket
Floating production
- GPIII FPSO sailaway: 30,870 t FPSO
Subsea and wells
- Trees: Birch, Larch and Sycamore: 5,300 grout bags
- Pelican subsea: 287 t subsea structures
- South Magnus and Magnus Swift wells: 280 t wellheads and trees
- Atlantic and Cromarty subsea: 203.6 t manifold
- Leman Southwest well: 232.68 t equipment
- Kestrel and Falcon subsea: Approx. 794 t subsea installations
- Hudson subsea: 333.9 t manifold
Programmes under consideration
At the time of checking, GOV.UK also listed 19 draft programmes under consideration. They are not covered here until they are approved.
Learn more about decommissioning
Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey.
Explore the trainingList of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).
Contains public sector information licensed under the Open Government Licence v3.0.
Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.