Atlantic and Cromarty subsea decommissioning programmes (Part 1)

Approved June 2026 · Information accurate as of 4 November 2026 · Source: programme document on GOV.UK

The Atlantic and Cromarty Decommissioning Programmes Part 1 were approved in June 2026. Shell Global LNG Limited and Hess Limited plan to remove the 203.6 tonne Atlantic manifold, the Cromarty piping assembly and surface-laid lines from the Atlantic and Cromarty gas fields in the outer Moray Firth, with subsea removal planned between 2026 and 2029. Buried pipelines stay in place, and the 77.6 km export line is held back to study reuse.

Key facts

ProgrammesAtlantic and Cromarty Decommissioning Programmes Part 1 (four programmes)
OperatorsShell Global LNG Limited (Atlantic and shared facilities) and Hess Limited (Cromarty), with Shell submitting on Hess's behalf
ApprovedJune 2026
LocationOuter Moray Firth, Blocks 14/26a, 20/1 (north) and 13/30a, approx. 67 km north-east of the St Fergus gas terminal
Water depth115 m
Installed2005
Production2006 to 2009 (gas and gas condensate)
Cessation of productionAgreed in 2011
Wells3 (2 Atlantic, 1 Cromarty), plugged and made safe in 2017
What is removedAtlantic manifold 203.6 tonnes; Cromarty piping assembly 8 tonnes; spools, jumpers and part of an umbilical; 199 mattresses; 18 concrete tunnels; 1,245 grout bags. 2,600 tonnes of the 4,517 tonne inventory comes ashore
What stays1,917 tonnes of buried pipeline, approx. 11,500 tonnes of rock, 10 mattresses at crossings and 40 grout bags under rock
Planned removalSubsea removal 2026 to 2029

What is being removed?

115 mPIPELINESburied, stayMANIFOLDremovedNot to scale
Simple drawing, not to scale. The manifold and surface equipment (blue) are removed. Buried pipelines (grey) stay.
  • Atlantic manifold: 17.8 m by 13.7 m by 5.46 m, 203.6 tonnes, on 4 piles, each 27.1 m long, cut 3 m below the seabed
  • Cromarty piping assembly: 7.7 m by 1.5 m by 1.5 m, 8 tonnes
  • Surface-laid spools and jumpers, and part of the control umbilical PLU2033
  • 199 of 209 concrete mattresses, 18 concrete tunnels, 1 deflector block and 1,245 of approx. 1,285 grout bags

In total, 2,600 tonnes of the 4,517 tonne inventory, approx. 58%, comes ashore. The 3 wellhead protection structures were already recovered in 2017.

What stays in place?

1,917 tonnes of buried pipeline stays in place, with approx. 11,500 tonnes of existing rock, 10 mattresses at pipeline crossings and 40 grout bags under rock.

The main length of the 16 inch export line PL2029 (77.6 km in full) and the MEG line PL2031 are kept out of this programme so that reuse can be studied. In 2016 the carbon capture community asked for the export pipeline to be held back for possible CO2 reuse.

Pipelines and umbilicals

Atlantic has 9 lines, 32.1 km in total, the longest being the 31.357 km control umbilical PLU2033. Cromarty has 3 lines, 35.7 km in total: the 12 inch PL2030, the 4 inch PL2032 and the umbilical PLU2034, each approx. 11.9 km. Rock cover, trench and bury, or cut and remove will be chosen through tendering.

When will the work happen?

  1. 2005: facilities installed
  2. 2006: production starts
  3. 2009: production stops
  4. 2011: cessation of production agreed
  5. 2017: wells plugged and made safe
  6. 2026 to 2029: subsea removal and onshore dismantling

What happens to the materials?

The disposal yard will be chosen by commercial tender. No recycling percentage is given.

Link to the official government decommissioning programme

Atlantic and Cromarty Decommissioning Programmes Part 1 (PDF, GOV.UK)

Shell Global LNG Limited and Hess Limited, final version 20 May 2026, approved June 2026. This page summarises pages 8 to 54 (printed page numbers).

Key terms

Manifold
A subsea structure that gathers the flow from several wells into shared pipelines. See subsea infrastructure removal.
Umbilical
A bundle of hoses and cables that carries power, control signals and chemicals to subsea equipment.
Concrete mattress
A flexible mat of concrete blocks laid over pipelines on the seabed to protect them and hold them in place.
Grout bag
A bag filled with grout, a cement mix, used to support or protect pipelines on the seabed.
Rock cover
Rock placed over pipelines or pipeline ends on the seabed to protect them.
Pile
A steel tube driven into the seabed to fix a structure in place.

Other programmes approved in 2026

Learn more about decommissioning

Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including subsea infrastructure removal.

Explore the training

Source. Atlantic and Cromarty Decommissioning Programmes Part 1, Shell Global LNG Limited and Hess Limited, final version 20 May 2026, approved June 2026: programme document (PDF, GOV.UK), pages 8 to 54 (printed page numbers).

List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).

Contains public sector information licensed under the Open Government Licence v3.0.

Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.