Leman 49/27J jacket and pipeline decommissioning programmes

Approved March 2026 · Information accurate as of 4 November 2026 · Source: programme document on GOV.UK

The Leman 49/27J Jacket and Pipeline PL207 Decommissioning Programmes were approved in March 2026. The operator, Perenco UK Limited, plans to remove the 1,124 tonne four-leg steel jacket of the Leman 27J platform and a short section of the 16 inch gas pipeline PL207, in the UK Southern North Sea, with jacket removal planned by the first quarter of 2028. The topsides were removed in November 2024 under an earlier programme.

Key facts

ProgrammesLeman 49/27J Jacket and Pipeline PL207 Decommissioning Programmes (two programmes)
OperatorsPerenco UK Limited (78.26%) and RockRose UKCS 10 Limited (21.74%)
ApprovedMarch 2026
LocationUK Southern North Sea, Block 49/27, approx. 53 km north-east of Bacton Gas Terminal
Water depth41.8 m
First productionJuly 1984
Cessation of productionApproved 15 December 2021
TopsidesRemoved in November 2024 under an earlier programme
What is removedFour-leg steel jacket, 1,124 tonnes including piles and marine growth; pipeline PL207, 89.7 m including the riser, 20 tonnes
What stays281 tonnes of piles, cut at least 3 m below the seabed
Wells5 platform gas wells
Planned removalJacket by Q1 2028 at the latest; PL207 by Q3 2028 at the latest
Protected areaInside the North Norfolk Sandbanks and Saturn Reef SAC and the Southern North Sea SAC

What is being removed?

TOPSIDESalready removedJACKETremoved41.8 mNot to scale
Simple drawing, not to scale. The jacket (blue) is removed in one lift. The topsides were removed in 2024.

The programmes cover a four-leg fixed steel jacket for a normally unattended installation, standing on 4 piles. The jacket weighs 1,124 tonnes including the piles and marine growth, and is 97.16% steel. 843 tonnes come ashore.

PL207 is a 16 inch gas pipeline, 89.7 m long including the riser, weighing 20 tonnes. The line rests on 2 grout bags of approx. 1 tonne each.

What stays in place?

The piles are cut at least 3 m below the seabed, and 281 tonnes of pile stays in place. An open tee on the neighbouring pipeline PL206 stays inside a 500 m safety zone until PL206 is removed.

How will the work be done?

  • The jacket is removed in a single lift by a heavy lift vessel
  • The piles are cut by diamond wire, oxyacetylene or abrasive water jet
  • The 5 platform wells are plugged to the final abandonment stage, and a jack-up removes the conductors

When will the work happen?

  1. 1965: Leman field discovered by Shell
  2. 1968: Block 49/27 starts producing
  3. September 1983 to February 1984: 27J wells drilled
  4. July 1984: 27J production starts
  5. 15 December 2021: cessation of production approved
  6. November 2024: topsides removed
  7. Q1 2026: start of the four-year plan
  8. By Q1 2028: jacket removal
  9. By Q3 2028: PL207 removal

What happens to the materials?

Most non-hazardous material is expected to be recycled. The rest goes to energy from waste or landfill. The disposal yard is not named and no recycling percentage is given.

Environment

The jacket stands inside a protected area that supports 17.5% of the UK North Sea harbour porpoise management unit.

Link to the official government decommissioning programme

Leman 49/27J Jacket and Pipeline PL207 Decommissioning Programmes (PDF, GOV.UK)

Perenco UK Limited, final version January 2026, approved March 2026. This page summarises pages 8 to 35.

Key terms

Jacket
The steel frame that holds a platform's topsides up from the seabed. See substructure removal.
Pile
A steel tube driven into the seabed to fix a structure in place.
Single lift
Lifting a whole structure off in one piece with a large crane vessel.
Special Area of Conservation (SAC)
A protected area for important habitats or species.
Plug and abandonment (P&A)
Sealing a well permanently with barriers, usually cement, so that the well can no longer flow. See well plug and abandonment.

Other programmes approved in 2026

Learn more about decommissioning

Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including substructure removal.

Explore the training

Source. Leman 49/27J Jacket and Pipeline PL207 Decommissioning Programmes, Perenco UK Limited, final version January 2026, approved March 2026: programme document (PDF, GOV.UK), pages 8 to 35.

List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).

Contains public sector information licensed under the Open Government Licence v3.0.

Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.

Scroll to Top
Secret Link