Hudson subsea facilities decommissioning programmes

Approved July 2026 · Information accurate as of 4 November 2026 · Source: programme document on GOV.UK

The Tern Area Hudson Subsea Facilities Decommissioning Programmes were approved in July 2026. TAQA plans to plug and abandon nine subsea wells and remove the 333.9 tonne Hudson manifold, nine Xmas trees and other subsea installations from the Hudson field in the UK Northern North Sea, along with 354 mattresses and 24,039 grout bags. Subsea removal is planned between 2025 and 2030.

Key facts

ProgrammesTern Area Hudson Subsea Facilities Decommissioning Programmes (four programmes)
OperatorsTAQA Bratani Limited (26.73%) and TAQA Bratani LNS Limited (73.27%)
ApprovedJuly 2026
LocationUK Northern North Sea, Blocks 210/24a and 210/24b, approx. 10 km west of the Tern platform
Water depth158 m
First productionJuly 1993, through the Petrojarl-1 FPSO; subsea tie-back to Tern from early 1995
Cessation of productionQ1 2024
What is removedManifold 333.9 tonnes; crossover skid 37.5 tonnes; protection structure 5 tonnes; 9 Xmas trees 367.2 tonnes; 354 mattresses; 24,039 grout bags; 6 grouted supports; 3,625.7 tonnes of pipeline to shore
What staysBuried pipelines, 53,228 tonnes of rock, and 2 drill cuttings piles
Wells9 subsea wells: 7 oil producers and 2 water injectors
Pipelines52 pipelines, approx. 48.6 km in total
Planned scheduleWell plugging 2025 to 2030; subsea removal 2025 to 2030; survey 2029 to 2030

What is being removed?

158 mPIPELINESburied, stayMANIFOLDremovedwells pluggedNot to scale
Simple drawing, not to scale. The manifold, Xmas trees and mattresses (blue) are removed and the wells plugged. Buried pipelines (grey) stay.
  • Manifold: 25 m by 13.5 m by 7.8 m, 333.9 tonnes, on 4 piles cut 3 m below the seabed
  • Crossover skid: 4 m by 3.4 m by 4.6 m, 37.5 tonnes, on 1 pile
  • Protection structure: 8 m by 3.8 m by 0.3 m, 5 tonnes
  • 9 Xmas trees with flowbases and wellheads: 367.2 tonnes in total

The installations total 743.7 tonnes, 98.7% steel, of which 707.5 tonnes comes ashore. 354 mattresses (approx. 1,231 tonnes), 24,039 grout bags (601 tonnes) and 6 grouted supports are also recovered.

Wells

The 9 subsea wells, 7 oil producers and 2 water injectors, are plugged and abandoned between 2025 and 2030.

Pipelines

The field has 52 pipelines, approx. 48.6 km in total. The main lines run approx. 10 km to 11 km to the Tern platform, for example the 10 inch production line PL1018 (10.141 km). 3,625.7 tonnes of pipeline comes ashore. Buried lines stay, and two lines, PL1022 and PL1021A, are re-trenched along their whole length.

12 lines at Tern, 5 pipelines and 7 umbilicals, are cut 132 m below Lowest Astronomical Tide and removed with the Tern upper jacket.

What stays in place?

Buried pipelines, 53,228 tonnes of rock and two drill cuttings piles, of 6,819 and 1,156 cubic metres, stay in place.

When will the work happen?

  1. July 1993: first production, through the Petrojarl-1 FPSO
  2. Early 1995: subsea tie-back to Tern
  3. Q1 2024: cessation of production
  4. 2025 to 2030: well plugging and subsea removal
  5. 2029 to 2030: survey after removal

What happens to the materials?

No recycling percentage is given, and no yard has been chosen yet.

Link to the official government decommissioning programme

Tern Area Hudson Subsea Facilities Decommissioning Programmes (PDF, GOV.UK)

TAQA Bratani Limited, final for approval 23 February 2026, approved July 2026. This page summarises pages 8 to 57.

Key terms

Manifold
A subsea structure that gathers the flow from several wells into shared pipelines. See subsea infrastructure removal.
Xmas tree
The assembly of valves on top of a wellhead that controls the flow from a well.
Subsea tie-back
A subsea field connected by pipelines to a platform some distance away, which processes the oil or gas.
FPSO
A floating production, storage and offloading vessel: a ship-shaped unit that processes and stores oil offshore.
Grout bag
A bag filled with grout, a cement mix, used to support or protect pipelines on the seabed.
Drill cuttings pile
A pile of crushed rock and drilling fluid on the seabed, left from drilling the wells.

Other programmes approved in 2026

Learn more about decommissioning

Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including subsea infrastructure removal.

Explore the training

Source. Tern Area Hudson Subsea Facilities Decommissioning Programmes, TAQA Bratani Limited, final for approval 23 February 2026, approved July 2026: programme document (PDF, GOV.UK), pages 8 to 57.

List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).

Contains public sector information licensed under the Open Government Licence v3.0.

Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.

Scroll to Top
Secret Link