Kestrel and Falcon subsea facilities decommissioning programmes
The Tern Area Kestrel and Falcon Subsea Facilities Decommissioning Programmes were approved in July 2026. The operator, TAQA Bratani Limited, plans to plug and abandon four subsea wells and remove the subsea installations of the Kestrel and Falcon fields in the UK Northern North Sea, approx. 794 tonnes in total, along with 499 mattresses and 5,870 grout bags. Removal is planned between 2029 and 2032.
Key facts
| Programmes | Tern Area Kestrel and Falcon Subsea Facilities Decommissioning Programmes (six programmes) |
|---|---|
| Operator | TAQA Bratani Limited |
| Approved | July 2026 |
| Location | UK Northern North Sea, approx. 111 km north-east of Shetland |
| Water depth | 164 m (Kestrel) and 160 m (Falcon) |
| Discovered | 1997 (Kestrel) and 2000 (Falcon) |
| First production | November 2001 (Kestrel) and July 2011 (Falcon) |
| Cessation of production | Q1 2024, with the Tern platform |
| What is removed | Kestrel installations 734.6 tonnes, including 9 sentry bollards with piles (527.6 tonnes); Falcon Xmas tree and wellhead 59.1 tonnes; 499 mattresses; 5,870 grout bags |
| What stays | Buried main lines with the ends cut, 51,388 tonnes of rock, and 217.9 tonnes of bollard piles below 3 m |
| Wells | 4 subsea wells (3 Kestrel, 1 Falcon) |
| Pipelines and umbilicals | 15 |
| Planned schedule | Well plugging 2025 to 2029; Kestrel removal 2029 to 2031; Falcon removal 2030 to 2032 |
What is being removed?
- Kestrel: 3 Xmas trees with flowbases and wellheads, 185.2 tonnes in total (for example P1: 4.24 m by 3.86 m by 3.35 m, 61.24 tonnes)
- Kestrel: subsea isolation valve, 8 m by 4 m by 3 m, 20 tonnes; a subsea distribution unit; and 2 small skids
- Kestrel: 9 sentry bollards, 4 m by 2 m by 1.5 m, with piles 18 m long and 0.76 m across, 527.6 tonnes in total
- Falcon: Xmas tree and wellhead, 5.1 m by 5.1 m by 4.4 m, 59.05 tonnes
159 mattresses at Kestrel (764.3 tonnes) and 340 at Falcon (1,655 tonnes) are recovered, with 5,870 grout bags.
Wells
The 4 subsea wells, 3 at Kestrel and 1 at Falcon, are plugged and abandoned between 2025 and 2029.
What stays in place?
Buried pipelines stay with the ends cut: the Kestrel main lines are approx. 8 km long and the Falcon lines approx. 3.8 km. 51,388 tonnes of rock cover stays, which is 95.6% of the Falcon pipeline inventory of 53,772.2 tonnes. 217.9 tonnes of bollard piles below 3 m stay in the seabed.
The 3 Kestrel risers run up the Tern jacket. They are cut 132 m below Lowest Astronomical Tide and removed with the Tern upper jacket, nominally in 2026 to 2028.
When will the work happen?
- 1997: Kestrel discovered
- 2000: Falcon discovered
- November 2001: Kestrel first production
- July 2011: Falcon first production
- Q1 2024: cessation of production
- 2025 to 2029: well plugging
- 2029 to 2031: Kestrel subsea removal
- 2030 to 2032: Falcon subsea removal
What happens to the materials?
No recycling percentage is given, and no yard has been chosen yet.
Link to the official government decommissioning programme
Tern Area Kestrel and Falcon Subsea Facilities Decommissioning Programmes (PDF, GOV.UK)
TAQA Bratani Limited, final for approval 23 February 2026, approved July 2026. This page summarises pages 8 to 48.
Key terms
- Xmas tree
- The assembly of valves on top of a wellhead that controls the flow from a well.
- Subsea tie-back
- A subsea field connected by pipelines to a platform some distance away, which processes the oil or gas.
- Subsea isolation valve (SSIV)
- A valve on the seabed that can shut off a pipeline.
- Concrete mattress
- A flexible mat of concrete blocks laid over pipelines on the seabed to protect them and hold them in place.
- Grout bag
- A bag filled with grout, a cement mix, used to support or protect pipelines on the seabed.
- Rock cover
- Rock placed over pipelines or pipeline ends on the seabed to protect them.
Other programmes approved in 2026
Learn more about decommissioning
Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including subsea infrastructure removal.
Explore the trainingSource. Tern Area Kestrel and Falcon Subsea Facilities Decommissioning Programmes, TAQA Bratani Limited, final for approval 23 February 2026, approved July 2026: programme document (PDF, GOV.UK), pages 8 to 48.
List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).
Contains public sector information licensed under the Open Government Licence v3.0.
Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.