South Magnus and Magnus Swift wellheads and Xmas trees decommissioning programme
The South Magnus and Magnus Swift Wellheads and Xmas Trees Decommissioning Programme was approved in June 2026. The operator, EnQuest Heather Limited, plans to plug and abandon five subsea wells in the Magnus field in the UK Northern North Sea and remove their wellheads and Xmas trees, 280 tonnes in total. Offshore work could start as early as the second quarter of 2026 and run to the end of 2030.
Key facts
| Programme | South Magnus and Magnus Swift Wellheads and Xmas Trees Decommissioning Programme |
|---|---|
| Operator | EnQuest Heather Limited (100%) |
| Approved | June 2026 |
| Location | UK Northern North Sea, Block 211/12a, approx. 142 km north-east of Shetland |
| Water depth | Approx. 186 m |
| Field | Magnus, producing since 1983. South Magnus installed 1995/96; Magnus Swift installed 1995 |
| What is removed | 5 wellheads with Xmas trees, 280.26 tonnes in total |
| Wells | 5 subsea wells: South Magnus F9 and F10, and Magnus Swift F1, F2 and F3 |
| What stays for now | The Swift manifold, spools, jumpers, flowlines PL1227 and PL1271, and mattresses, for a later Magnus programme |
| Planned schedule | Offshore work from as early as Q2 2026 to the end of 2030 |
| Recycling target | More than 98% recycled |
What is being removed?
5 wellheads with Xmas trees, 280.26 tonnes in total. Each measures 5.95 m by 3.68 m by 3.68 m and weighs 55.24 or 57.27 tonnes. They are 98% steel and 2% plastic or rubber, with 18¾ inch wellheads and no piles.
Wells
The 5 wells are fully plugged and abandoned, and the conductors are cut 3 m below the seabed. The wells were checked for reuse for carbon storage and found not suitable. Well F9 was shut in in 2013 after defects in pipework and the riser, and rising hydrogen sulphide.
What stays in place?
The seven-slot Swift water injection manifold, the spools, jumpers, flowlines PL1227 and PL1271, and the mattresses stay for a later Magnus programme. The flowlines are disconnected and blanked. Approx. 2 mattresses at each of 4 wells and up to 24 grout bags are moved aside and left in place.
How will the work be done?
First a light well intervention vessel campaign, which also removes the F9 and F10 trees, then a drilling rig. The wellheads are designed to come out with a hydraulic retrieval tool, with cutting as the back-up.
When will the work happen?
- 1974: Magnus discovered
- 1983: Magnus production starts
- 1995: Magnus Swift installed
- 1995/96: South Magnus installed
- 2013: well F9 shut in
- December 2025 to January 2026: site survey attempted, then postponed after 7 weeks of bad weather
- Q2 2026 at the earliest to the end of 2030: offshore work
What happens to the materials?
The target is less than 2% reused, more than 98% recycled and less than 2% disposed of. No yard has been chosen yet, and shipping waste abroad may be needed.
Link to the official government decommissioning programme
South Magnus and Magnus Swift Wellheads and Xmas Trees Decommissioning Programme (PDF, GOV.UK)
EnQuest Heather Limited, final version A7 dated 19 May 2026, approved June 2026. This page summarises pages 6 to 38.
Key terms
- Wellhead
- The equipment at the top of a well that supports the well casing and the Xmas tree.
- Xmas tree
- The assembly of valves on top of a wellhead that controls the flow from a well.
- Plug and abandonment (P&A)
- Sealing a well permanently with barriers, usually cement, so that the well can no longer flow. See well plug and abandonment.
- Conductor
- The first and widest pipe set into the seabed at the top of a well.
- Manifold
- A subsea structure that gathers the flow from several wells into shared pipelines. See subsea infrastructure removal.
Other programmes approved in 2026
Learn more about decommissioning
Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including well plug and abandonment.
Explore the trainingSource. South Magnus and Magnus Swift Wellheads and Xmas Trees Decommissioning Programme, EnQuest Heather Limited, final version A7 dated 19 May 2026, approved June 2026: programme document (PDF, GOV.UK), pages 6 to 38.
List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).
Contains public sector information licensed under the Open Government Licence v3.0.
Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.