North Cormorant upper jacket decommissioning programmes
The North Cormorant Upper Jacket and Associated Riser Sections Decommissioning Programmes were approved in May 2026. The operator, TAQA Bratani Limited, plans to remove the upper section of the 172 m tall North Cormorant jacket in the UK Northern North Sea, approx. 12,500 tonnes including marine growth, with removal planned between 2025 and 2027. The topsides were covered by a 2020 programme, and the footings are left for a later programme.
Key facts
| Programmes | North Cormorant Upper Jacket and Associated Riser Sections Decommissioning Programmes (six programmes) |
|---|---|
| Operator | TAQA Bratani Limited |
| Approved | May 2026 |
| Location | UK Northern North Sea, Block 211/21a, 112 km from the nearest UK coast |
| Water depth | 161 m |
| Installed | 1981 |
| First production | February 1982 |
| Cessation of production | June 2024 |
| What is removed | Upper jacket, approx. 12,500 tonnes including approx. 700 tonnes of marine growth; upper sections of 4 rigid risers, 3 risers in J-tubes, 3 umbilicals and 9 cables |
| What stays for now | The footings below approx. 116 m below LAT, and the drill cuttings pile |
| Whole jacket | Eight legs, 172 m tall, 20,052 tonnes without marine growth, piles or grout |
| Planned removal | 2025 to 2027; disposal 2026 to 2028 |
| Recycling target | Around 95% recycled |
What is being removed?
The upper jacket runs from approx. 11 m above Lowest Astronomical Tide down to approx. 116 m below, which is approx. 45 m above the seabed. The section weighs approx. 12,500 tonnes: approx. 11,090 tonnes of steel, approx. 700 tonnes of marine growth and 15 tonnes of hazardous paint.
Two legs were used as diesel tanks, and four legs held drinking water, the larger tanks approx. 500 cubic metres each. Removed with the upper jacket:
- 4 rigid risers, from 10 inch to 20 inch
- 3 rigid risers in J-tubes, 8 inch
- 3 umbilicals
- 9 cables, including a 33 kV power cable
The whole jacket
North Cormorant stands on an eight-legged steel jacket with K-bracing, 172 m tall in 161 m of water. The jacket weighs 20,052 tonnes, not counting marine growth, piles or grout. 32 foundation piles, 8 at each corner leg, each approx. 2 m in diameter, hold the jacket in place. The corner legs are 6 m in diameter at the base, narrowing to 2 m at the top. The footprint at the seabed is 75 m by 77 m.
What stays in place?
The footings below approx. 116 m below Lowest Astronomical Tide and the drill cuttings pile stay for a later programme. The programmes describe the sub-structure as a candidate for derogation under OSPAR Decision 98/3.
How will the upper jacket be removed?
The programmes list three options. A contractor has been selected, but is not named.
- A single lift by Pioneering Spirit's jacket lift system
- A heavy lift vessel, in two sections
- Two heavy lift vessels working together in a quad lift
When will the work happen?
- May 1974: field discovered
- 1981: platform installed
- February 1982: first production
- November 2020: topsides programme approved
- June 2024: cessation of production
- 2025 to 2027: topsides and upper jacket removal
- 2026 to 2028: disposal
- 2027 to 2029: survey of what is left
What happens to the materials?
The aim is to recycle around 95%. The yard has not been chosen and may be outside the UK.
Link to the official government decommissioning programme
North Cormorant Upper Jacket and Associated Riser Sections Decommissioning Programmes (PDF, GOV.UK)
TAQA Bratani Limited, final version December 2025, approved May 2026. This page summarises pages 7 to 43.
Key terms
- Jacket
- The steel frame that holds a platform's topsides up from the seabed. See substructure removal.
- Footings
- The lowest part of a large steel jacket, at the seabed, where the jacket is fixed to its piles. See substructure removal.
- Marine growth
- Sea life, such as mussels and seaweed, that builds up on structures under water and adds to their weight.
- J-tube
- A J-shaped tube fixed to a jacket that guides a riser or cable from the seabed up to the platform.
- Derogation
- Permission under OSPAR Decision 98/3 to leave part of a large installation, such as the footings of a heavy steel jacket, in place.
- Lowest Astronomical Tide (LAT)
- The lowest sea level that can be predicted. Heights and depths on offshore installations are often measured from LAT.
Other programmes approved in 2026
Learn more about decommissioning
Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including substructure removal.
Explore the trainingSource. North Cormorant Upper Jacket and Associated Riser Sections Decommissioning Programmes, TAQA Bratani Limited, final version December 2025, approved May 2026: programme document (PDF, GOV.UK), pages 7 to 43.
List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).
Contains public sector information licensed under the Open Government Licence v3.0.
Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.