Trees (Birch, Larch and Sycamore) subsea decommissioning programmes

Approved April 2026 · Information accurate as of 4 November 2026 · Source: programme document on GOV.UK

The Trees Decommissioning Programmes (Birch, Larch and Sycamore) were approved in April 2026. The operator, Spirit Energy North Sea Oil Limited, plans to remove the subsea manifolds, a wellhead and pipeline structures from the Birch, Larch and Sycamore fields in the UK Central North Sea, together with 568 mattresses and 5,300 grout bags. Trenched pipelines stay buried in place.

Key facts

ProgrammesTrees Decommissioning Programmes (Birch, Larch and Sycamore), seven programmes in one document
OperatorSpirit Energy North Sea Oil Limited (100%)
ApprovedApril 2026
LocationUK Central North Sea, Block 16/12a, approx. 215 km north-east of Peterhead
Water depthApprox. 125 m
Host platformSubsea tie-backs to Brae Alpha
First productionBirch 1995, Larch 1998, Sycamore 2003
Cessation of productionBirch 15 November 2020; Larch 24 January 2023; Sycamore notified as 6 April 2025
What is removedBirch manifold 109 tonnes; Larch manifold 63 tonnes; Sycamore wellhead and flowbase 10 tonnes; 9 pipeline structures; 3,145 tonnes of pipeline ends and spools; 568 mattresses; 5,300 grout bags; 18 covers
What stays8,144 tonnes of trenched pipelines, 38,168 tonnes of rock, piles cut 3 m below the seabed, and 2 drill cuttings piles
Pipelines and umbilicals54
Planned removalQ3 2024 to Q1 2027, with a window to the end of 2029
Recycling targetMore than 95% recycled

What is being removed?

125 mPIPELINESburied, stayMANIFOLDSremovedNot to scale
Simple drawing, not to scale. The manifolds and structures on the seabed (blue) are removed. Buried pipelines (grey) stay.
  • Birch manifold: 109 tonnes, 20 m by 16 m by 3.5 m, gravity based
  • Larch manifold: 63 tonnes, 12 m by 11.5 m by 3 m, on four piles cut 3 m below the seabed
  • Sycamore well SW1 wellhead and flowbase: 10 tonnes
  • A crossover bundle at Brae Alpha: 95 tonnes, 37.5 m long
  • Larch wye pieces of 71, 24 and 12 tonnes
  • Pipeline ends, spools, jumpers and surface-laid lines: 3,145 tonnes

568 concrete mattresses, 5,300 grout bags of 25 kg each and 18 protection covers are also lifted from the seabed.

What stays in place?

Pipelines trenched at least 0.6 m to the top of the pipe stay in place, 8,144 tonnes in all. This was the preferred option in the comparative assessment. The trenches are mostly 1 m to 2 m deep, and no snagging has been reported. 38,168 tonnes of rock stays, along with 2 drill cuttings piles that are below the OSPAR thresholds.

The risers and umbilical at Brae Alpha wait until Brae Alpha is decommissioned.

Pipelines and umbilicals

There are 54 pipelines and umbilicals: 27 at Birch, 10 at Larch and 17 at Sycamore. The Birch main lines are approx. 14 km long: the 10 inch production line (14.26 km), the 12 inch water injection line (13.92 km) and the 4 inch gas lift line (13.91 km).

When will the work happen?

  1. 1995: Birch production starts
  2. 1998: Larch production starts
  3. 2003: Sycamore production starts
  4. 15 November 2020: Birch cessation of production
  5. 24 January 2023: Larch cessation of production
  6. Q3 2024 to Q1 2027: removals, with a window to the end of 2029

What happens to the materials?

The target is more than 95% recycled, less than 5% reused and less than 5% disposed of. No yard is named.

Link to the official government decommissioning programme

Trees Decommissioning Programmes (Birch, Larch and Sycamore) (PDF, GOV.UK)

Spirit Energy North Sea Oil Limited, final version 3 March 2026, approved April 2026. This page summarises pages 8 to 62.

Key terms

Manifold
A subsea structure that gathers the flow from several wells into shared pipelines. See subsea infrastructure removal.
Umbilical
A bundle of hoses and cables that carries power, control signals and chemicals to subsea equipment.
Concrete mattress
A flexible mat of concrete blocks laid over pipelines on the seabed to protect them and hold them in place.
Grout bag
A bag filled with grout, a cement mix, used to support or protect pipelines on the seabed.
Subsea tie-back
A subsea field connected by pipelines to a platform some distance away, which processes the oil or gas.
Comparative assessment
A study that compares the options for decommissioning a pipeline or structure, looking at safety, environmental, technical, societal and economic factors.

Other programmes approved in 2026

Learn more about decommissioning

Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including subsea infrastructure removal.

Explore the training

Source. Trees Decommissioning Programmes (Birch, Larch and Sycamore), Spirit Energy North Sea Oil Limited, final version 3 March 2026, approved April 2026: programme document (PDF, GOV.UK), pages 8 to 62.

List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).

Contains public sector information licensed under the Open Government Licence v3.0.

Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.