GPIII FPSO sailaway decommissioning programmes
The GPIII FPSO Sailaway and Disconnection of Risers and Pipelines Decommissioning Programmes were approved in March 2026. The programmes cover disconnecting the 30,870 tonne Global Producer III FPSO from the Donan, Balloch and Lochranza fields in the UK Central North Sea and towing the vessel away, with tow-away planned between the second quarter of 2026 and the third quarter of 2027. The subsea equipment, wells, anchors and lower mooring chains are left for a second programme.
Key facts
| Programmes | GPIII FPSO Sailaway and Disconnection of Risers and Pipelines Decommissioning Programmes (two programmes) |
|---|---|
| Operator | NEO NEXT+ Energy Production UK Limited (named in the programme document as NEO Energy Production UK Limited, 100%) |
| Approved | March 2026 |
| Location | UK Central North Sea, Blocks 15/20a and 15/20b, 222 km north-east of Aberdeen |
| Water depth | Approx. 145 m |
| Fields served | Donan (online 2007), Lochranza (2010) and Balloch (2013) |
| Cessation of production | No earlier than the end of Q1 2026; base case end of Q1 2027 |
| What is removed | FPSO 30,870 tonnes; 747 tonnes of mooring chain; 5 flexible risers and 1 umbilical riser with 161 buoyancy modules, 364 tonnes |
| What stays for now | Lower mooring chains, ground chains, drag anchors, subsea equipment and wells, for a second programme |
| Planned tow-away | Q2 2026 to Q3 2027 |
| Recycling target | More than 90% reused if the FPSO is resold; more than 90% recycled if dismantled |
What is being removed?
The Global Producer III FPSO weighs 30,870 tonnes. The vessel turns around a turret on a 10-point mooring and has three sections:
- forward: accommodation, helideck, bridge and control room, and machinery and equipment rooms
- central: crude storage, ballast, mooring, turret and production systems
- aft: main power generation, the flare and vent tower, and the offloading system
The 10 mooring lines are 108 mm studless chain, each approx. 1,100 m long, weighing 2,550 tonnes in air in total. Approx. 280 m to 320 m of each chain is recovered, 747 tonnes in all. 5 flexible risers and 1 umbilical riser, 1.76 km in total, are removed with 161 buoyancy modules.
What stays in place?
The lower chain sections are lowered to the seabed. The lower chains, ground chains, drag anchors, subsea equipment and wells stay for a second programme, with approval expected by 2027 and the work planned for 2028 to 2032. The anchors and ground chain were fully buried at the 2024 survey.
How will the work be done?
The FPSO is flushed and disconnected, then towed either to a new field for reuse or to a licensed yard for recycling.
When will the work happen?
- 2007: Donan online
- 2010: Lochranza online
- 2013: Balloch online
- End of Q1 2027: cessation of production (base case)
- Q2 2026 to Q3 2027: tow-away
- To approx. Q3 2028: recycling, if the FPSO is dismantled
- 2028 to 2032: second programme work (subsea equipment and wells)
What happens to the materials?
If the FPSO is resold, more than 90% is reused. If the FPSO is dismantled, more than 90% is recycled and less than 10% disposed of. No yard has been selected yet. Recycling the FPSO's materials is estimated at 27,383 tonnes of CO2, against 55,164 tonnes to make the same materials new.
Link to the official government decommissioning programme
NEO Energy, final version 4 February 2026, approved March 2026. This page summarises pages 7 to 48.
Key terms
- FPSO
- A floating production, storage and offloading vessel: a ship-shaped unit that processes and stores oil offshore.
- Turret mooring
- A mooring point on an FPSO that lets the vessel turn around the mooring lines with the wind and waves.
- Riser
- A pipe or cable that rises from the seabed to a platform or vessel.
- Cessation of production (CoP)
- The date a field permanently stops producing.
Other programmes approved in 2026
Learn more about decommissioning
Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including FPSO removal.
Explore the trainingSource. GPIII FPSO Sailaway and Disconnection of Risers and Pipelines Decommissioning Programmes, NEO Energy, final version 4 February 2026, approved March 2026: programme document (PDF, GOV.UK), pages 7 to 48.
List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).
Contains public sector information licensed under the Open Government Licence v3.0.
Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.