Ravenspurn North gas compression deck decommissioning programmes

Approved February 2026 · Information accurate as of 4 November 2026 · Source: programme document on GOV.UK

The Ravenspurn North Central Complex Gas Compression Deck Topside and Bridges Decommissioning Programmes were approved in February 2026. The operator, Perenco UK Limited, plans to remove the 3,187 tonne gas compression deck and its three bridges from the Ravenspurn North complex in the UK Southern North Sea, between the second quarter of 2026 and the end of 2027. The rest of the complex keeps producing, with field cessation of production planned for 2038.

Key facts

ProgrammesRavenspurn North Central Complex Gas Compression Deck (RNCC GCD) Topside and Bridges Decommissioning Programmes
OperatorPerenco UK Limited (71.25%)
ApprovedFebruary 2026
LocationUK Southern North Sea, Block 43/26, approx. 76 km east of Flamborough Head
Water depth43 m
Deck installed1993
Gas compression stopped2017
Made hydrocarbon safe24 October 2020
What is removedGas compression deck, 3,187 tonnes including three bridges
What staysThe concrete gravity structure, the central production platform and the WT-1 wellhead tower, which keep producing
WellsNone on the deck
Planned removalQ2 2026 to Q4 2027
Field cessation of productionPlanned for 2038

What is being removed?

PLATFORMkeeps producingDECKremovedbridgesCONCRETE SHAFTSstay43 mNot to scale
Simple drawing, not to scale. The compression deck and bridges (blue) are removed. The concrete shafts and production platform (grey) stay.

The gas compression deck is an integrated deck on three levels: a cellar deck at +24.70 m, a mezzanine deck at +31.20 m and a weather deck at +37.7 m above Lowest Astronomical Tide. The deck weighs 3,187 tonnes, which includes three bridges to the central production platform of 2, 18 and 11.5 tonnes. Steel makes up 3,030 tonnes, approx. 95% of the weight.

What stays in place?

The deck sits on one of the three concrete shafts of a concrete gravity structure, through a steel deck transition structure. The concrete gravity structure, the central production platform and the WT-1 wellhead tower stay and keep producing. The shafts hold seawater and have never been used to store hydrocarbons.

The deck is removed early for safety, cost and vessel availability. After removal, shaft 3 will be painted white or covered in retroreflective material and lit by a spotlight on the central production platform.

How will the deck be removed?

The programmes considered a single lift, a modular lift, skidding onto a jack-up barge, and piece small. The environmental appraisal expects a six-legged heavy lift jack-up barge, the Obana. Contracts have been awarded.

When will the work happen?

  1. 1988: WT-1 wellhead tower installed
  2. 1989: concrete gravity structure and central production platform installed
  3. 1993: gas compression deck installed
  4. 2017: gas compression stopped
  5. 24 October 2020: deck made hydrocarbon safe
  6. Q2 2026 to Q4 2027: deck removal
  7. 2038: field cessation of production planned

What happens to the materials?

All 3,187 tonnes are planned to come ashore to a selected disposal yard, not named in the programmes. No recycling percentage is given.

Link to the official government decommissioning programme

Ravenspurn North Central Complex Gas Compression Deck Topside and Bridges Decommissioning Programmes (PDF, GOV.UK)

Perenco UK Limited, final version December 2025, approved February 2026. This page summarises pages 9 to 50.

Key terms

Concrete gravity structure (CGS)
A platform base made of concrete that stays in place on the seabed because of its own weight.
Topsides
The decks and equipment that sit above the sea on an offshore platform. See topside preparation and removal.
Lowest Astronomical Tide (LAT)
The lowest sea level that can be predicted. Heights and depths on offshore installations are often measured from LAT.
Cessation of production (CoP)
The date a field permanently stops producing.

Other programmes approved in 2026

Learn more about decommissioning

Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including topside preparation and removal.

Explore the training

Source. Ravenspurn North Central Complex Gas Compression Deck Topside and Bridges Decommissioning Programmes, Perenco UK Limited, final version December 2025, approved February 2026: programme document (PDF, GOV.UK), pages 9 to 50.

List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).

Contains public sector information licensed under the Open Government Licence v3.0.

Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.

Scroll to Top
Secret Link