Alba Northern Platform topsides decommissioning programme
The Alba Northern Platform Topsides Decommissioning Programme was approved in January 2026. The operator, Ithaca Oil and Gas Limited, plans to remove the 17,543 tonne topsides of the Alba Northern Platform in the UK Central North Sea between mid-2028 and the end of 2032. The eight-leg steel jacket stays in place for a later programme.
Key facts
| Programme | Alba Northern Platform Topsides Decommissioning Programme |
|---|---|
| Operator | Ithaca Oil and Gas Limited (36.67% equity) |
| Approved | January 2026 |
| Location | UK Central North Sea, Block 16/26a, approx. 210 km north-east of Aberdeen |
| Water depth | Approx. 138 m |
| Platform installed | 1993 |
| First oil | January 1994 |
| Cessation of production | Q3 2026 (agreed) |
| What is removed | Topsides: 17,543 tonnes, one integrated deck |
| What stays for now | Eight-leg steel jacket, for a later programme |
| Wells | 31 platform wells: 25 oil production and 6 water injection |
| Planned removal | Mid-2028 to the end of 2032 |
| Recycling target | More than 95% recycled |
What is being removed?
The programme covers the topsides of the Alba Northern Platform: one integrated deck with deck extensions, weighing 17,543 tonnes. The topsides include:
- drilling modules, and a drilling derrick on skid rails over the well bay
- an accommodation module for up to 144 people, with the central control room, helideck and lifeboats
- a flare boom at the north end
- process plant for separation, gas compression, water injection, produced water treatment and power generation
By weight, the topsides are 92.5% steel, 4.75% non-ferrous metal, 2.5% plastic and rubber, and 0.25% hazardous material. The cut between the topsides and the jacket is planned between elevation +13 m and +22 m.
What stays in place?
The eight-leg steel jacket stays in place for a later programme, together with the caissons, risers and umbilicals fixed to the jacket. Diesel tanks inside the jacket legs will be drained. The top of the jacket stays above sea level, and the 500 m safety zone and navigation aids are kept. The pipelines, the floating storage unit and the subsea equipment are covered by other programmes.
How will the topsides be removed?
The programme lists four removal options. The final method will follow a front-end engineering design (FEED) study and a tender.
- Single lift by a single lift vessel or semi-submersible crane vessel
- Modular lift, in sections
- Piece small, cutting the topsides into small pieces offshore
- A combination of these methods
When will the work happen?
- 1984: field discovered
- 1993: platform installed
- January 1994: first oil
- Q3 2026: cessation of production
- Mid-2028 to end of 2032: topsides removal window
What happens to the materials?
All 17,543 tonnes are planned to come ashore. The target is more than 95% recycled, less than 5% reused and less than 5% disposed of. The disposal yard has not been named, and a yard outside the UK is possible.
Link to the official government decommissioning programme
Alba Northern Platform Topsides Decommissioning Programme (PDF, GOV.UK)
Ithaca Oil and Gas Limited, final version 14 November 2025, approved January 2026. This page summarises pages 7 to 30.
Key terms
- Topsides
- The decks and equipment that sit above the sea on an offshore platform. See topside preparation and removal.
- Jacket
- The steel frame that holds a platform's topsides up from the seabed. See substructure removal.
- Cessation of production (CoP)
- The date a field permanently stops producing.
- Decommissioning programme
- The document an operator submits to the regulator, setting out how offshore installations and pipelines will be decommissioned. See decommissioning programme.
Other programmes approved in 2026
Learn more about decommissioning
Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including topside preparation and removal.
Explore the trainingSource. Alba Northern Platform Topsides Decommissioning Programme, Ithaca Oil and Gas Limited, final version 14 November 2025, approved January 2026: programme document (PDF, GOV.UK), pages 7 to 30.
List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).
Contains public sector information licensed under the Open Government Licence v3.0.
Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.