Wellhead and Conductor Removal in Offshore Decommissioning
Wellhead removal is the last step of well plug and abandonment.
below the seabed is the least depth to which a well origin must be removed in the UK, unless OPRED agrees otherwise.
NSTA guidance, 2026(approx. 4.6 m) below the mudline is the least depth for removing wellheads and casings in US federal waters, unless an alternate depth is approved.
30 CFR 250.1716of UK decommissioning cost has historically been well decommissioning, the work that ends with wellhead removal.
NSTA, 2025is the weight range given in the training for subsea Christmas trees.
Lean Decom trainingWhat is wellhead removal in decommissioning?
Wellhead removal is the final step of well plug and abandonment. After the permanent barriers are set and verified, the casing strings are cut below the seabed and the wellhead is recovered to a rig or vessel. On a platform well, the conductor is also cut and lifted out. The cut depth is set by, or agreed with, the regulator: often 3 m below the mudline in the UK.
Where this applies: The cutting and recovery methods on this page are used on offshore wells in any region. The phase names and cost figures are UK North Sea examples, and the cut depths are UK and US examples. Other countries have their own regulator, rules and terms.
Key points
- Wellhead removal is the last step of well P&A: phase AB3 in the UK.
- The cut is below the mudline: often 3 m in the UK, at least 15 ft in US federal waters.
- Cutters are abrasive, mechanical or explosive.
- A newer cutting tool took one platform from approx. 5 days to 2 to 3 days per conductor.
- Subsea Christmas trees in the training weigh approx. 30 to 60 tonnes.
Where does wellhead removal fit in well abandonment?
A well is abandoned in steps: the live well is suspended, the reservoir is permanently isolated, and any other zones with flow potential are isolated. The last step is to cut and recover the wellhead, after which the well cannot generally be re-entered. In the UK, wellhead removal is phase AB3. See the well abandonment phases page for the earlier steps.
The wellhead is the equipment at the top of the well: on the platform for a platform well, and on the seabed for a subsea well. Below the wellhead, several casing strings run down into the well, one inside another, each cemented in place. The cut has to sever all of these strings.
UK example: the North Sea Transition Authority records a well as AB3 once the well origin (the point where the well enters the seabed) and the conductor have been removed. In the Offshore Energies UK (OEUK) work breakdown structure, wellhead severance sits inside well decommissioning, historically approx. 50% of UK decommissioning cost. See the OEUK work breakdown structure.


How far below the mudline is a wellhead cut?
The casing strings are cut below the seabed, not at the seabed, so that the remains are unlikely to become uncovered and are no risk to other users of the seabed. The cut depth is set by, or agreed with, the regulator, so the depth differs between countries.
| Where | Cut depth |
|---|---|
| UK | Often 3 m (10 ft) below the mudline. The regulator OPRED requires the well origin to be removed to at least 3 m below the seabed unless OPRED agrees otherwise. |
| US federal waters | Wellheads and casings are removed to at least 15 ft (approx. 4.6 m) below the mudline, unless an alternate depth is approved. |
Sources: the training (Well-Safe Solutions, Claxton); NSTA guidance, 2026; report published on GOV.UK, 2023; 30 CFR 250.1716.
UK guidance sets the same aim for jacket piles: a cut depth of 3 m below the natural seabed level, with consideration given to seabed conditions and currents. See substructure removal.
How is a wellhead cut? Abrasive, mechanical and explosive cutting
Three types of cutter are used for the wellhead cut: abrasive, explosive and mechanical.
Abrasive water jet
Abrasive material is carried in a high-pressure water jet that wears away the steel. A cutting system is landed on the wellhead and severs the casing strings below the mudline.
Mechanical cutting
A tool is lowered into the well and turned, and hydraulically actuated blades are forced outwards to mill through the casing. Diamond wire saws, fixed to the outside of the pipe, are used on conductors, caissons and jacket members.
Explosive cutting
An explosive charge severs the wellhead. Explosive severance is used only after the well has been plugged and abandoned downhole.
Descriptions are general. The choice of method depends on the well, the water depth and the regulator. This page does not recommend a supplier or method.
The abrasive water jet example from the training, step by step
Confirm the barriers
The permanent barriers are in place and verified before the wellhead is cut.
Land the cutting tool
The cutting tool is run from the vessel and lands on top of the wellhead.
Sever every casing string
All the casing strings are cut below the mudline in one trip, from the innermost to the outermost.
Pull the wellhead free
The vessel crane pulls the wellhead and the cut casing free of the seabed.
Recover to deck
The wellhead is recovered to deck, which completes the decommissioning work on that well.

How are platform conductors removed?
Platform wells run inside very large diameter tubes called conductors, which are connected to the platform. Conductors are removed after the wells are abandoned. Subsea wells have no conductors of this kind to remove.
On a platform, conductor removal is heavy lifting work, and the conductors may be in poor condition after years of seawater corrosion. The work often runs alongside the last well operations and the start of topsides preparation. The conventional method named in the training is pinning and cutting the conductors.
Before a topsides single lift, everything that connects the topsides to the jacket must be separated, including caissons, risers and conductors. Separated items must be supported so that nothing falls into the sea.
On some projects, conductors or caissons come out with the jacket. On TAQA’s Brae Bravo platform, the jacket had supported 28 conductors, a figure that included caissons, J-tubes and risers. Most had been removed during topside removal; approx. half a dozen remained and came out with the upper jacket.


How did one project cut the time to remove conductors?
On the Heather platform in the northern North Sea, EnQuest had 41 conductors to remove. Two changes saved time.
From approx. 5 days to 2 to 3 days per conductor
The team used a newer conductor cutting tool, and benchmarked the tool against the conventional method of pinning and cutting conductors.
The usual time to remove a conductor on Heather fell from approx. five days to two to three days. Over 41 conductors, EnQuest describes the saving as considerable. Not every new technology tried during the well P&A campaign succeeded.
Removing the need for the crane
Moving caissons, tubulars and conductors from the V-door to the pipe deck needed the platform crane, and the crane had weather limits.
The team slid each item down onto a catwalk and rolled the item onto the pipe deck instead, which removed the need for the crane. EnQuest estimates a saving of several days, possibly tens of days, without a full analysis.
Grouping wells that need the same equipment means the equipment is brought on board, rigged up and demobilised once. See how wells are sequenced and bundled.
How are subsea wellheads removed?
Subsea wellheads sit on the seabed, often spread across a field and tied back to a manifold. The abandonment work, including the wellhead cut, is done from a drilling rig or a light well intervention vessel positioned above each well.
The amount of downhole work decides which. A rig gives the heavy capability to set plugs in several zones and to cut and recover casing. If the subsurface work shows that some zones do not need to be isolated, the scope may shrink to cutting and recovering the wellhead, which a light well intervention vessel can do. In the UK example in the training, that change can move an abandonment from many millions of pounds to one or two million.
In the vessel-based example in the training, the tools are run on the vessel crane through the water column, and a remotely operated vehicle (ROV) crew monitors the tool landing on the wellhead. After the cut, the vessel crane pulls the wellhead free and recovers the wellhead to deck.
Once the wells are abandoned, the rest of the seabed equipment, such as manifolds, pipework and umbilicals, is removed in a later phase. See subsea infrastructure removal.

| Platform wells | Subsea wells | |
|---|---|---|
| Wellhead location | On the platform | On the seabed |
| Conductors to remove | Yes, large conductors | None of this kind |
| Carried out from | Platform rig or hydraulic workover unit | Drilling rig or light well intervention vessel |
| Also removed | Caissons and risers, before the topsides lift | Christmas trees; later, manifolds, pipework and umbilicals |
Get your information pack
Course details and free sample lessons, emailed to you.
How are subsea Christmas trees recovered?
A Christmas tree is the assembly of valves and instruments on the wellhead that controls the flow of production fluids from the well. Platform wells have trees at the surface. This section covers subsea trees.


Subsea Christmas trees are generally released from the wellhead and recovered. A tree may be recovered to a rig as part of the P&A scope, or by a subsea contractor to a construction vessel.
Christmas tree recovery, step by step
Plan the lift
Check the rigging is rated and easy to attach, the crane has enough hook height to bring the tree inboard, and tugger winches are ready to control orientation.
Clean the interface
The lifting tool fits an interface on top of the tree: in the DOF example, an H4 profile with a jagged shape. After years subsea, the profile is cleaned, for example with a high-pressure water jet, so the tool fits well.
Land and clamp the tool
Dogs on the recovery tool lock into the profile, and the tool is hydraulically clamped.
Confirm the connection
An over-pull test confirms there is no movement, and indicators on the tool show whether the tool is clamped. A specialist from the tool provider generally verifies the connection.
Lift and bring inboard
Tugger winches control the orientation of the tree, which matters in marginal weather, and help land the tree at the sea-fastening location on deck.
Check for NORM before sea fastening
A radiation protection supervisor checks the tree before the deck crew approach. Marine growth and loose debris are checked too.


NORM is naturally occurring radioactive material, which can build up as scale in pipes and vessels. In the training, any equipment that carried production fluids is treated as a NORM risk, whether or not NORM has been found before. The rules on NORM depend on where the work takes place.
Wellhead and conductor removal in the Lean Decom training
The training covers the final cut from three sides: the tools, the platform campaign and the subsea recovery. The case studies are from the North Sea; the methods are used in any offshore region.

Specialised Tooling
Wellhead severance, rigless abandonment and below-mudline cutting tools.

Decommissioning Overview: Heather and Thistle case study
Conductor removal and the time saved across 41 conductors.

Subsea Infrastructure Removal and Site Remediation
Christmas tree recovery, from the lift plan to the NORM check on deck.
Wellhead and conductor terms
- Wellhead
- The equipment at the top of a well, on the platform or on the seabed. The Christmas tree sits on the wellhead.
- Conductor
- On a platform, the very large diameter tube, connected to the platform, that a well runs inside.
- Mudline
- The level of the seabed. Wellheads and piles are cut a set depth below the mudline.
- Casing strings
- The steel pipes that line the well, one inside another, each cemented in place.
- AB3
- The UK status of a well once the permanent barriers are in place and the well origin and conductor have been removed.
- Christmas tree
- The assembly of valves and instruments on the wellhead that controls the flow from the well.
- Abrasive water jet cutting
- Cutting with a high-pressure water jet that carries abrasive material, able to cut through several casing strings.
- Over-pull test
- A pull on a recovery tool to confirm the tool is locked on before the lift.
- NORM
- Naturally occurring radioactive material, which can build up as scale in equipment that carried production fluids.
Sources and further reading
- Lean Decom training: Subsurface and Well P&A module, taught by Ruth Thomas, Well-Safe Solutions.
- Lean Decom training: Specialised Tooling module, taught by David Ledingham, Claxton.
- Lean Decom training: Decommissioning Overview: Heather and Thistle case study, taught by Will Black and Ean Paul, EnQuest.
- Lean Decom training: Subsea Infrastructure Removal and Site Remediation module, taught by Mike McHardy, DOF.
- Lean Decom training: Substructure Removal and Onshore Demolition module, taught by Malcolm McCombie, TAQA; Safety and Risk Management module, taught by Graham Skinner, OEUK; OEUK Work Breakdown Structure module, taught by Ricky Thomson, OEUK.
- UK: North Sea Transition Authority, UKCS Well Applications and Consents Guidance, January 2026 (definitions of AB1, AB2 and AB3; paragraph 137 on the 3 m requirement). nstauthority.co.uk
- UK: Offshore Petroleum Regulator for Environment and Decommissioning (OPRED), Guidance Notes: Decommissioning of Offshore Oil and Gas Installations and Pipelines, November 2018. gov.uk
- UK: The Use and Environmental Impact of Explosives in the Decommissioning of Offshore Wells and Facilities, a report published on GOV.UK, December 2023 (enquiries to OPRED) (cutting methods; the 10 ft good practice, citing the OEUK Well Decommissioning Guidelines). gov.uk
- US: Code of Federal Regulations, 30 CFR 250.1716, To what depth must I remove wellheads and casings? govinfo.gov
- UK: Health and Safety Executive, Naturally occurring radioactive material (NORM). hse.gov.uk
- UK: North Sea Transition Authority, UKCS Decommissioning Cost and Performance Update 2025 (well decommissioning as a share of decommissioning cost). nstauthority.co.uk
Wellhead and conductor removal: common questions
What does wellhead abandonment mean?
Wellhead abandonment means the final step of well plug and abandonment: cutting and recovering the wellhead once the permanent barriers are in place. The training calls this step wellhead severance. In the UK, the step is phase AB3.
How far below the seabed is a wellhead cut?
The regulator sets or agrees the cut depth. In the UK, the cut is often 3 m (10 ft) below the mudline. US federal rules require at least 15 ft below the mudline. Other countries set their own depth.
How are subsea wellheads removed?
From a drilling rig or a light well intervention vessel. A cutting tool, commonly an abrasive water jet tool, is landed on the wellhead and severs the casing strings below the mudline. The vessel crane then pulls the wellhead free and recovers the wellhead to deck.
What methods are used to cut a wellhead?
Abrasive, mechanical and explosive cutters. An abrasive water jet uses water and grit at high pressure, 14,500 psi in the example in the training. A mechanical cutter uses blades forced outwards inside the well. An explosive charge severs the wellhead, only after the well has been plugged and abandoned downhole.
What is a conductor on an offshore platform?
A conductor is the very large diameter tube, connected to the platform, that a platform well runs inside. After the well is abandoned, the conductor is cut and lifted out, or on some projects comes out with the jacket.
How heavy is a subsea Christmas tree?
In the training, lighter subsea Christmas trees weigh approx. 30 tonnes, and heavier trees 50 to 60 tonnes. The weight matters for the rigging and the vessel crane.
Related topics
Get your information pack
Course details and free sample lessons, emailed to you.
Learn wellhead and conductor removal from the people who do the work
Lean Decom is a specialist decommissioning training provider. The training shares lessons from North Sea projects, taught by 18 specialists, for you to apply to your own work.





