Leman Southwest well and pipeline sections decommissioning programmes
The Leman Southwest 53/02a-15Y WHPS and PL3731 & PLU3732 Pipeline Sections Decommissioning Programmes were approved in July 2026. The operator, Perenco UK Limited, plans to permanently abandon one subsea gas well in the UK Southern North Sea and remove the Xmas tree, wellhead, wellhead protection structure and short pipeline end sections, 232.68 tonnes in total. The work is planned over four years from the third quarter of 2026.
Key facts
| Programmes | Leman Southwest 53/02a-15Y WHPS and PL3731 & PLU3732 Pipeline Sections Decommissioning Programmes (two programmes) |
|---|---|
| Operators | Perenco UK Limited (78.26%) and RockRose UKCS 10 Limited (21.74%) |
| Approved | July 2026 |
| Location | UK Southern North Sea, Leman South field, Block 53/02a, approx. 60 km north-east of Bacton Gas Terminal |
| Water depth | 37.2 m |
| Production | February 2015 to August 2021 (gas) |
| Well | 1 subsea gas well, 53/02a-15Y |
| What is removed | Xmas tree 17.56 tonnes, wellhead 18.8 tonnes, wellhead protection structure 24.11 tonnes, mattresses, and up to 16 m of the 6 inch gas line PL3731 and 10 m of the 4 inch umbilical PLU3732: 232.68 tonnes in total |
| What stays | The rest of PL3731 and PLU3732, for a later programme. The neighbouring well 53/02a-14A stays in production |
| Protected area | Inside the Southern North Sea SAC |
| Planned schedule | Four years from Q3 2026 |
What is being removed?
- Xmas tree: 17.56 tonnes
- Wellhead: 18.8 tonnes, including 4.2 tonnes of conductor
- Wellhead protection structure: 24.11 tonnes
- Up to 5 fronded mattresses of approx. 10 tonnes each
- Up to 16 m of the 6 inch gas line PL3731 and up to 10 m of the 4 inch umbilical PLU3732
- Up to 10 more mattresses of approx. 12 tonnes each, and an umbilical ramp
All 232.68 tonnes are planned to come ashore.
Well
The well 53/02a-15Y produced gas from February 2015 and was shut in in August 2021. The well is permanently abandoned, and the conductor is cut 3 m below the seabed.
What stays in place?
The rest of the gas line PL3731 and the umbilical PLU3732 stay for a later programme. The neighbouring well 53/02a-14A stays in production.
How will the work be done?
Divers close the valves. The lines are cut to leave a gap, and the equipment is lifted to the vessel deck. A danger buoy marks the site for up to one year.
When will the work happen?
- 1968: Leman South discovered
- February 2015: well starts producing
- August 2021: well shut in
- Q3 2026: start of the four-year plan
What happens to the materials?
The material is landed in the UK. The subsea control module, instruments and interface plates will be reused.
Link to the official government decommissioning programme
Perenco UK Limited, final version June 2026, approved July 2026. This page summarises pages 8 to 36.
Key terms
- Xmas tree
- The assembly of valves on top of a wellhead that controls the flow from a well.
- Wellhead
- The equipment at the top of a well that supports the well casing and the Xmas tree.
- Conductor
- The first and widest pipe set into the seabed at the top of a well.
- Umbilical
- A bundle of hoses and cables that carries power, control signals and chemicals to subsea equipment.
- Plug and abandonment (P&A)
- Sealing a well permanently with barriers, usually cement, so that the well can no longer flow. See well plug and abandonment.
- Special Area of Conservation (SAC)
- A protected area for important habitats or species.
Other programmes approved in 2026
Learn more about decommissioning
Lean Decom is a specialist decommissioning training provider. The training covers the full decommissioning journey, including well plug and abandonment.
Explore the trainingSource. Leman Southwest 53/02a-15Y WHPS and PL3731 & PLU3732 Pipeline Sections Decommissioning Programmes, Perenco UK Limited, final version June 2026, approved July 2026: programme document (PDF, GOV.UK), pages 8 to 36.
List of approved programmes: Oil and gas: decommissioning of offshore installations and pipelines (GOV.UK).
Contains public sector information licensed under the Open Government Licence v3.0.
Information accurate as of 4 November 2026. These pages summarise public documents and are not endorsed by the operators named. Plans may change, so check the source for the latest position. Spotted an error? Email contact@leandecom.com.