Home/Offshore Decommissioning/Decommissioning Programme
Decommissioning knowledge

Decommissioning Programme (UK): OPRED Approval, Contents and Process

In the UK, a decommissioning programme is the formal document an operator must have approved before removing offshore oil and gas installations and pipelines.

Based on The Decommissioning Programme and Regulators and Regulations modulesTaught by Gareth Jones, Xodus, and Teresa Munro, OPRED
96%

target recycling figures are seen by OPRED in the waste management plans of UK decommissioning programmes.

Lean Decom training
2 to 5 years

before cessation of production: when most UK operators start dialogue with OPRED.

OPRED Guidance Notes, November 2018
Quarterly

progress meetings between OPRED and the operator once a programme is approved.

Lean Decom training
5 to 9 years

can be needed to decommission a complex Northern North Sea asset, from start to finish.

Lean Decom training
Quick answer

What is a decommissioning programme?

A decommissioning programme (DP) is the formal document a UK operator submits to the regulator before removing offshore oil and gas installations and pipelines. The programme lists the infrastructure, the removal and disposal methods, the environmental impacts, the cost, the schedule and the monitoring of anything left in place. OPRED reviews each programme, and the Secretary of State approves or rejects the programme under the Petroleum Act 1998. Carrying out an approved programme is a legal obligation.

Where this applies: The decommissioning programme, OPRED and the Petroleum Act 1998 are the UK system, used here as a worked example. Other countries have their own regulator, rules and terms. The planning questions a programme answers apply to a project in any region.

Key points

  • In the UK, no physical removal work can start without an approved decommissioning programme.
  • Most operators start dialogue with OPRED two to five years before cessation of production.
  • The materials inventory is the backbone of the programme: every item on the installation and the seabed.
  • Two documents support the programme: the environmental appraisal and the comparative assessment.
  • A comparative assessment is required for every pipeline and for any derogation candidate.
  • An approved programme is signed by the Secretary of State and the operator’s board, and becomes a legal obligation.
The basics

What is a decom programme, and why is one needed?

A decommissioning programme is a formal document that an operator submits to the regulator to decommission offshore oil and gas infrastructure. The programme sets out what will be decommissioned, where, which activities will take place and the potential impacts.

Decommissioning programme is the UK term. The Petroleum Act 1998 uses the name abandonment programme for the same document. Other countries use other names. Elsewhere the name decommissioning plan is sometimes used for a document of the same kind.

In the UK, the Offshore Petroleum Regulator for Environment and Decommissioning (OPRED), part of the Department for Energy Security and Net Zero, manages the decommissioning process and reviews every programme. Read more on the OPRED and UK decommissioning regulation page.

Diagram of the scope a decommissioning programme covers: a platform and subsea infrastructure with hydrocarbons removed, wells plugged, and steel and concrete on the seabed due for removal
What a programme must deal with. The installations and pipelines left in the field.From the training: bp, Introduction to Commercial Models
Key rule: no programme, no removal

In the UK, physical removal operations cannot take place without an approved decommissioning programme. Some activities, such as engineering down, flushing and cleaning, can be carried out earlier as operational activities.

How many programmes does a project need?

The number depends on the type and size of the project. TAQA’s Brae Bravo project in the training ran two programmes: one for the topsides and flare, and one for the upper jacket. In the UK, pipelines and installations need separate programmes, which can be presented in one document.

The legal basis in the UK

The Petroleum Act 1998 is the statutory framework for decommissioning offshore installations and pipelines on the UK Continental Shelf. Under Part IV of the Act, the Secretary of State may issue a section 29 notice requiring relevant parties to submit a decommissioning programme.

The parties who submit an approved programme must secure that the programme is carried out. The duty is joint and several, so one party may have to meet the full obligation if another party does not. Decommissioning without an approved programme is an offence under the Act.

Timing

At what stage of the platform life is a decommissioning programme written?

In the UK, planning for the programme starts in late life, before cessation of production (CoP). Once the economics are assessed and a CoP date is chosen, a decommissioning project is set up, and the first regulatory submission is the decommissioning programme. OPRED guidance describes five stages.

Early discussion

Before CoP, the operator and OPRED discuss the process, so the operator can plan a realistic timescale.

Planning and producing the programme

Options are assessed in detail to find the preferred solution. Government and other interested parties consider a draft programme.

Submitting the programme

After consultation, the operator and OPRED agree a final version. The Secretary of State calls formally for submission under the 1998 Act and confirms approval by letter.

Execution

The operator carries out the approved programme, up to the completion of the post-decommissioning site surveys.

Post-completion activities

After reporting completion, the operator monitors, maintains and manages the site and any remains of installations or pipelines.

Stages from the OPRED Guidance Notes (November 2018), as taught in the training.

Timings in OPRED’s guidance

Most operators start dialogue with OPRED two to five years before CoP, depending on the complexity of the project. For a potential derogation case, discussions may start up to five years ahead. Statutory consultees normally have 30 days to comment on a draft programme. The close-out report is due within one year of completing the offshore work.

How long the work takes

EnQuest notes in the training that a complex Northern North Sea asset can take five to nine years to decommission, from start to finish. A floating production, storage and offloading vessel (FPSO) can be far quicker, perhaps one to three years, because the risers are disconnected and the vessel sails back to shore.

Inside a programme

What does a decommissioning programme contain?

In the UK, OPRED provides a template for the decommissioning programme. The template follows a set order: first what is being decommissioned, then how, then the impacts, cost, schedule and monitoring.

Part of the programmeWhat goes in
Description of itemsTables of all the infrastructure: materials, weights, design outline, number of wells, and the length and size of pipelines.
Materials inventoryAll current infrastructure, equipment and materials at the asset location. The backbone of the programme.
Removal and disposal methodsHow each item will be decommissioned. For a jacket, a single lift or smaller sections, driven by water depth, size and complexity.
Comparative assessmentRequired for all pipelines and for derogation candidates: the options assessed and the recommended option.
WellsA list of the wells linked to the installation, with brief details of the plug and abandonment.
Environmental appraisalEnvironmental sensitivities, potential impacts and how each impact is managed.
Waste management planHow material brought to shore will be handled and recycled, with a target figure.
Interested party consultationsWho was consulted, and how the responses were taken into account.
Costs and scheduleA cost estimate against industry benchmarks, and a schedule with key stages flagged.
Post-decommissioning monitoringHow anything left on the seabed will be monitored and managed.

Contents as taught in the training. The wells and consultation rows are from the list of usual sections in the OPRED Guidance Notes (November 2018).

Field layout drawing of a platform with a bridge-linked flare, pipelines, umbilicals and subsea isolation valves inside and outside the 500 m zone
Field layout drawings. Pipelines, umbilicals and subsea valves inside and beyond the 500 m zone must all appear in the inventory.From the training: TAQA, Brae Bravo Overview

Why the materials inventory matters

Many assets have operated for more than 50 years. Over that life, topsides equipment is added or replaced, sometimes to a different specification, and extra stabilisation material is placed on the seabed after pipelines move, storms hit or a pipeline is snagged.

The materials inventory identifies exactly what is on the installation and the seabed at the point of decommissioning. As-built and field layout drawings are the starting point, but items are easy to miss: mattresses and grout bags placed over pipeline spans, or anchor blocks left inside the 500 m zone during construction.

OPRED process map

How is a decommissioning programme approved? The OPRED roadmap

In the UK, the roadmap to an approved programme runs from late-life planning to a decision by the Secretary of State. The steps follow the OPRED Guidance Notes.

Early discussion and cessation of production

Dialogue with OPRED starts before cessation of production (CoP). The planned CoP date is agreed with the North Sea Transition Authority (NSTA). Once production has stopped for good, the licensee notifies the NSTA within 14 days.

OPRED review

OPRED is the focal point for reviewing the decommissioning proposals.

Develop the programme

The operator identifies the infrastructure and drafts the programme on the OPRED template. The section 29 notice holders must also consult the NSTA before the programme is submitted.

Submission for consultation

When OPRED is content with the level of detail, the programme is submitted and put out for consultation. The OPRED Guidance Notes call this version the consultation draft.

Public consultation

OPRED publishes the draft and consults government departments and agencies. The operator places a public notice and consults the statutory consultees, such as fishing organisations. Non-governmental organisations and the public can comment.

Addressing feedback

The operator responds to every comment or request and reports the responses in the programme. OPRED reviews the responses.

Final submission and decision

OPRED formally directs the notice holders to submit the final programme. The Secretary of State approves the programme, with or without conditions, or rejects the programme.

Roadmap slide: public consultation, then addressing feedback
Consultation. Consultees review the programme, and the operator responds to every comment.From the training: Xodus, Roadmap to DP Approval
Roadmap slide: final submission, then government review by the Secretary of State
Decision. The Secretary of State evaluates the final programme.From the training: Xodus, Roadmap to DP Approval
Supporting documents

Which documents support a decommissioning programme?

Two main supporting documents sit alongside a UK programme: the environmental appraisal (EA) and the comparative assessment (CA).

Environmental appraisal (EA)

The impact on the marine environment

The environmental appraisal sets out the impact of the selected decommissioning option on the environment, from the seabed to the water column and the birds. Each impact is quantified as far as possible, and changes needed to protect marine life are built into the programme. For example, removing a drill cuttings pile disturbs the seabed and can release the material inside the pile into the sea.

Comparative assessment (CA)

Choosing the right option

In the UK, a comparative assessment is required for all pipelines and for any installation that may qualify for a derogation. The options, such as full removal, partial removal or leave in situ, are compared against five criteria: safety, environmental, technical, societal and economic. Read the full guide to comparative assessment and derogation.

Derogation: the exception to a clear seabed

UK policy aims for a clear seabed. Under OSPAR Decision 98/3, which applies to the North-East Atlantic, a disused installation may be left in place only under a derogation. Candidates include the footings of large steel jackets and concrete gravity base structures. In the UK, the operator must carry out a comparative assessment that includes full removal. A derogation is considered only if the assessment shows significant reasons why leaving the footings in place is preferable. OPRED then consults the other OSPAR countries. The Decision does not cover pipelines.

How pipelines are decided

Pipelines follow their own route. OSPAR Decision 98/3 covers offshore installations, not pipelines, and there is no international rule for pipelines. So the UK has its own test: every pipeline gets a comparative assessment, starting from the aim of a clear seabed. A pipeline may stay in place only where the assessment supports leaving the line, and OPRED approves the decommissioning programme. Any pipeline left in place is then monitored. Sources: OSPAR Decision 98/3 and the OPRED Guidance Notes, 2018.

Programme management

How are cost and schedule set out in a decommissioning programme?

In the UK, cost and schedule form part of the discussions between the operator, OPRED and the NSTA, which is responsible for the cost efficiency of decommissioning.

Cost

Each activity is described and given a cost, to build a robust estimate. At submission, costs should be well defined. The supply chain may not yet have been tested for rates, but the operator has framed the duration of each activity and the cost against industry benchmarks. In the UK, the detailed cost estimate can be submitted separately and is kept in confidence.

Schedule

Cost and schedule are closely linked, because the schedule reflects the number of days at sea. The schedule shows where the submission date sits in the whole project, and flags key stages: the topside lift, the jacket lift, and the subsea and wells activities. The last part shows the expected post-decommissioning monitoring programme.

Slide of the programme management section: describe activities, assign costs, estimate against industry benchmark, frame the steps, submission date and key stages
Programme management: costs and schedule. The cost and schedule part of a programme, as shown in the training.From the training: Xodus, Cost and Schedule
Why the NSTA takes an interest

In the UK, decommissioning costs involve a form of tax relief, so the economics are a national concern, not only a company concern. The NSTA gives input on each programme.

Free information pack

Get your information pack

Course details and free sample lessons, emailed to you.

Execution and close-out

What happens after a decommissioning programme is approved?

Once approved, a UK programme becomes the template for the work that follows. Completing the work in the timeframe set out is a legal obligation.

A legal obligation

The approved programme is signed by the Secretary of State and the operator’s board. If an approved programme is not carried out, the Secretary of State can serve a notice requiring remedial action. Failing to comply with that notice is a criminal offence under section 37 of the Petroleum Act 1998.

Progress and deviations

Each operator has an OPRED case manager. OPRED meets the operator quarterly and receives a progress report: infrastructure removed, costs to date and the plan ahead. OPRED must approve any deviation from the plan.

Close-out and monitoring

The operator submits a close-out report within one year of completing the offshore work. OPRED reviews the report, circulates the report to the stakeholders consulted on the programme, and publishes the accepted report. Post-decommissioning monitoring is agreed with OPRED, for example a seabed survey every three years.

Cut pipework and steel plate sorted at an onshore disposal yard for recycling
Recovered material, sorted for recycling. The waste management plan in a programme sets the target recycling figure.From the training: TAQA, Material Management

Waste management and recycling

The waste management plan explains what happens to material back on shore, how the material will be recycled, and the target recycling figure. OPRED sees target figures of 96%. On TAQA’s Brae Bravo project in the training, the jacket programme, mostly steel, achieved over 99% recycling or reuse.

Monitoring what is left behind

For a pipeline or jacket base left in place, the operator must show there is no risk to fishing, with regular surveys at a frequency agreed with the regulator, for example after two, five and ten years. OPRED also encourages operators to take part in the Fisheries Legacy Trust Company, which helps make sure legacy seabed items are recorded and communicated to fishermen and other sea users.

Lessons from practice

What are the common permitting pitfalls after approval?

After approval, execution needs many permits, and a permit problem can hold a high-cost vessel at the quayside.

Materials inventory errors

For example: a programme quotes 400 grout bags, and 700 are on the seabed. The permit then covers too small an area of impact. A new permit could mean two to four weeks of delay, or as much as six months.

Changing a supplier

A permit names the chemicals and volumes for a flushing scope. A new supplier with different chemicals or volumes needs a new permit. Even a rushed permit can take two weeks.

Nesting birds

Nesting birds must not be disturbed. On offshore platforms the breeding season is usually from March or April to the end of September. A licence to disturb covers a set number of birds and needs at least two years of survey data. A missed heavy lift slot can mean waiting another year.

Track every permit: the PLANC register

A PLANC register tracks every permit, licence, approval, notification and consent, with an owner and a date for each. Build the register early and engage the regulators before permits become the critical path.

Learn this in the training

Decommissioning programmes in the Lean Decom training

The training covers the decommissioning programme from both sides: the consultant who builds programmes, and the regulator who reviews them. Each module is online and video-based, so you can learn at your own pace.

The Decommissioning Programme module
Planning and regulation

The Decommissioning Programme

How a decommissioning programme supports compliant decommissioning, including consultation and comparative assessment.

Taught by Gareth Jones, Xodus
Regulators and Regulations module
Planning and regulation

Regulators and Regulations

The regulator’s role in offshore decommissioning, from the decommissioning programme to close-out.

Taught by Teresa Munro, OPRED
Permitting Lessons Learned and Efficiency Strategies module
Safety, tools and lessons learned

Permitting Lessons Learned and Efficiency Strategies

How permitting decisions affect cost, schedule and risk, with practical efficiency opportunities.

Taught by Gareth Jones, Xodus

Explore the training options →

Glossary

Decommissioning programme terms

Decommissioning programme (DP)
The formal document setting out what will be decommissioned, how, and with what impacts. The UK term. The Petroleum Act 1998 uses the name abandonment programme. Other countries use other names.
OPRED
The Offshore Petroleum Regulator for Environment and Decommissioning, the UK regulator that reviews decommissioning programmes.
Cessation of production (CoP)
The point at which production stops permanently. In the UK, CoP sits with the North Sea Transition Authority (NSTA).
Materials inventory
A list of all current infrastructure, equipment and materials at the asset location.
Environmental appraisal (EA)
The supporting document that assesses the impact of the selected decommissioning option on the environment. The training also uses the name environmental statement.
Comparative assessment (CA)
A structured comparison of decommissioning options against safety, environmental, technical, societal and economic criteria. Required in the UK for all pipelines and for derogation candidates.
Derogation
Under OSPAR Decision 98/3, a permit to leave a disused offshore installation, or part of one, in place: for example the footings of a large steel jacket.
Close-out report
The report an operator submits when the decommissioning work is complete. In the UK, the report is due within one year of completing the offshore work.
Sources

Sources and further reading

  1. Lean Decom training: The Decommissioning Programme module, taught by Gareth Jones, Xodus.
  2. Lean Decom training: Regulators and Regulations module, taught by Teresa Munro, OPRED.
  3. Lean Decom training: Permitting Lessons Learned and Efficiency Strategies module, taught by Gareth Jones, Xodus.
  4. Lean Decom training: Decommissioning Overview: Heather and Thistle case study (EnQuest) and Substructure Removal and Onshore Demolition (TAQA) modules.
  5. OPRED: Guidance Notes, Decommissioning of Offshore Oil and Gas Installations and Pipelines, November 2018. gov.uk (PDF)
  6. OPRED: Oil and gas: decommissioning of offshore installations and pipelines (draft and approved decommissioning programmes, close-out reports). gov.uk
  7. The Petroleum Act 1998, Part IV. legislation.gov.uk
  8. OSPAR Commission: OSPAR Decision 98/3 on the Disposal of Disused Offshore Installations. ospar.org
  9. North Sea Transition Authority: Cessation of Production. nstauthority.co.uk
FAQ

Decommissioning programmes: common questions

What is a decom programme?

A decom programme, or decommissioning programme, is the formal document a UK operator submits to the regulator before removing offshore oil and gas installations and pipelines. Decommissioning programme is the UK term. Other countries use other names for the equivalent document.

What is OPRED?

OPRED is the Offshore Petroleum Regulator for Environment and Decommissioning, part of the UK Department for Energy Security and Net Zero. OPRED regulates the environmental side of offshore oil and gas and manages the decommissioning programme process. See the OPRED and UK decommissioning regulation page.

At what stage of the platform life is a decom programme written?

In the UK, planning for the programme starts in late life, before cessation of production. The OPRED Guidance Notes say most operators start dialogue with the regulator two to five years before cessation of production. Physical removal cannot start until the programme is approved.

Where can I find approved decommissioning programmes?

In the UK, OPRED publishes draft programmes under consideration, approved programmes and accepted close-out reports on the GOV.UK page for the decommissioning of offshore oil and gas installations and pipelines. Lean Decom also summarises the UK decommissioning programmes approved in 2026.

Can offshore infrastructure be left in place?

In the UK, the policy aim is a clear seabed. Some pipelines may be left in situ after a comparative assessment. Under OSPAR Decision 98/3, the footings of large steel jackets and concrete gravity base structures may qualify for a derogation, but only after a comparative assessment that includes full removal. See comparative assessment and derogation.

Free information pack

Get your information pack

Course details and free sample lessons, emailed to you.

Take the training

Learn how decommissioning programmes are built and approved

Lean Decom is a specialist decommissioning training provider. The training shares lessons from North Sea projects, taught by 18 specialists, for you to apply to your own work.

Online and video-basedECITB-approved course availableFree Preview available
Scroll to Top
Secret Link