OEUK Work Breakdown Structure (WBS) for Decommissioning
The OEUK Work Breakdown Structure (WBS) splits a decommissioning project into 11 cost elements.
elements in the OEUK WBS, numbered 1 to 11.
OEUK, Decommissioning Work Breakdown Structure Guidelines, 2019is the approx. share of UK Continental Shelf (UKCS) decommissioning cost that has historically gone on well decommissioning (WBS 3).
NSTA, UKCS Decommissioning Cost and Performance Update 2025was spent on UKCS decommissioning in 2025, a record. Approx. £1.3 billion went on well decommissioning.
NSTA, UKCS Decommissioning Cost and Performance Update 2026of forecast UKCS decommissioning spend from 2026 onwards is subsea infrastructure (WBS 9). The share of actual spend in 2023 to 2025 was 6%.
NSTA, UKCS Decommissioning Cost and Performance Update 2026What is the OEUK decommissioning Work Breakdown Structure?
The OEUK Work Breakdown Structure (WBS) is a framework that splits a decommissioning project into 11 standard elements, from project management to post-decommissioning monitoring. Offshore Energies UK (OEUK), a trade association for the UK offshore energy industry, publishes the WBS. UK operators and the supply chain use the 11 elements to estimate, report and benchmark decommissioning costs in the same way. OEUK describes the WBS as a guide, not a detailed project management tool.
Where this applies: The WBS is a UK framework, published by OEUK and used for cost reporting to the UK regulator. The cost figures are UK figures. Readers elsewhere can use the 11 elements as a checklist of scope. Other countries have their own reporting rules.
Key points
- The WBS has 11 elements, numbered 1 to 11.
- OEUK, a UK trade association, publishes the WBS. The North Sea Transition Authority (NSTA), the UK regulator for decommissioning costs, collects cost data under the same 11 elements.
- Well decommissioning (WBS 3) has historically been approx. 50% of UKCS decommissioning cost.
- Subsea infrastructure was 6% of actual UKCS spend in 2023 to 2025, and is 12% of forecast spend from 2026.
- The WBS began as a cost estimation and benchmarking tool. The Lean Decom training says operators outside the UK now use the WBS as well.
- Engineering down and clean (EDC) sits mainly in WBS 4, but EDC-linked work is funded across several elements.
Why does the decommissioning WBS matter?
The WBS is a framework that guides teams through each element of a decommissioning project. The WBS gives commonality: every project describes the scope under the same 11 headings.
With a common structure, teams can benchmark against themselves and against the initial cost estimate, and report costs under the right element.
OEUK first created the WBS as a cost estimation and benchmarking tool. The OEUK guideline that sets out the WBS (Guideline on Decommissioning Cost Estimation, Issue 3, September 2013) is written for offshore oil and gas facilities on the UKCS.
The Lean Decom training says operators and the supply chain in other regions now use the WBS as well, and that the WBS can be developed to suit any project in any region. For a reader outside the UK, the 11 elements are a checklist of the scope that a decommissioning estimate has to cover.

OEUK states that the WBS is intended to act as a guide only, and is not intended to be a detailed project management tool. Operators may deviate from the WBS to suit a project. The Lean Decom training describes the WBS as a funding breakdown structure, developed by OEUK so that operators fund and commercially develop projects in a similar way.
What are the 11 elements of the OEUK decommissioning WBS?
The WBS numbers the elements 1 to 11. OEUK notes that the elements are not sequential: some run at the same time, and not every project needs all 11.

| WBS | Element | What the element covers |
|---|---|---|
| 1 | Project management | The core project management team within the decommissioning team, usually within the operator. Can start up to 10 years before cessation of production (CoP). Prepares the decommissioning programmes, the studies, and the pre-FEED and FEED (front-end engineering design) work before execution. |
| 2 | Post-CoP running costs | Operating costs for the offshore asset after cessation of production, such as the support teams, fuel, inspection, maintenance and logistics. The costs under this element stop when the topsides are removed. |
| 3 | Well decommissioning | The plug and abandonment of the wells, and wellhead severance. Historically approx. 50% of UKCS decommissioning cost. See well plug and abandonment. |
| 4 | Facilities and pipelines permanent isolation and cleaning | The make-safe: removal of hydrocarbons, pigging, and engineering down of all the elements of the offshore asset. Engineering down and clean (EDC) sits mainly in this element. |
| 5 | Topsides preparation | Preparing the topsides ahead of removal. For UK cost reporting, the NSTA lists temporary utilities, the separation of module process and utility systems, and dropped object surveys under this element, and asks operators to report removal preparation under WBS 6. See topside preparation and removal. |
| 6 | Topsides removal | Removing the topsides from the substructure, with large heavy lift vessels, or with smaller construction vessels that remove smaller parts one at a time. |
| 7 | Substructure removal | Removing the jacket: the large substructure that connects the topsides to the seabed, mainly with heavy lift vessels and large construction vessels. See substructure removal. |
| 8 | Topsides and substructure onshore disposal | Bringing the topsides and substructure onshore, where an onshore facility safely dismantles and recycles them. |
| 9 | Subsea infrastructure | Removing the seabed infrastructure that connected the platform to the wellheads: manifolds, pipelines, risers, cables and similar items, recovered by offshore construction vessel and taken onshore for disposal. Covers anything subsea except the substructure. See subsea infrastructure removal. |
| 10 | Site remediation | Cleaning up the seabed after the large items are removed, so that no debris is left behind. |
| 11 | Post-decommissioning monitoring | Monitoring of any infrastructure left in place. In the UK, the monitoring programme is agreed with the regulator. See OPRED and UK regulation. |
Element names from the OEUK Decommissioning Work Breakdown Structure Guidelines (2019) and the NSTA survey guide. Descriptions from the OEUK guidelines and the Lean Decom training. UK reporting notes from the NSTA guide to the decommissioning section of the UK Stewardship Survey (2025), which names element 1 “Operator project management”.




How are decommissioning costs split across the WBS?
OEUK publishes a decommissioning report every year, with a breakdown of the cost of each WBS element for the year completed. The figures cover the UK Continental Shelf.

On the UKCS, well decommissioning has historically been approx. 50% of the cost. Subsea infrastructure was 6% of actual spend in 2023 to 2025, and is 12% of forecast spend from 2026 onwards.
The plugging and abandonment of wells, and the rigs that work needs, drive the high cost of WBS 3. The regulator reports the same pattern: in 2025, approx. £1.3 billion of the £2.6 billion spent on UKCS decommissioning went on well decommissioning (NSTA, August 2026).
| WBS element | Share on the slide |
|---|---|
| 1 Project management | 6% |
| 2 Post-CoP running costs | 10% |
| 3 Well decommissioning | 48% |
| 4 Facilities and pipelines permanent isolation and cleaning | 3% |
| 5 Topsides preparation | 3% |
| 6 Topsides removal | 9% |
| 7 Substructure removal | 6% |
| 8 Topsides and substructure onshore disposal | 2% |
| 9 Subsea infrastructure | 12% |
| 10 Site remediation | 1% |
| 11 Post-decommissioning monitoring | 0.5% |
Figures shown on the OEUK slide in the training. The slide does not state the year, and the shares add up to 100.5% because of rounding. The split changes from year to year as projects reach different stages, so use the latest NSTA Decommissioning Cost and Performance Update and the latest OEUK Decommissioning Report for current figures.
How does the WBS support cost estimating, benchmarking and NSTA cost reporting?
Decommissioning estimates are often built from the bottom up and organised using a WBS. Individual costs are built up into a complete top-level figure, with each cost allocated to a WBS element. The reporting steps below are the UK example.
Build the estimate bottom up
Detail the individual costs and allocate each cost to a WBS element, until the estimate reaches a complete top-level figure.
Classify the estimate
The estimate class shows how confident the team is in the information behind each part of the estimate.
Approve the spend
An authorisation for expenditure (AFE) is the formal mechanism to approve cost. On a jointly owned asset, the operator usually needs approval from the other partners before funds are committed.
Report to the regulator
In the UK, operators report decommissioning cost information to the NSTA mainly through the annual UKCS Stewardship Survey, submitted through the UK Energy Portal, including actual and forecast costs. The survey asks for the costs under each of the 11 WBS categories.
Benchmark
Compare performance against the initial estimate, through project execution, and against industry figures from OEUK and the NSTA.
AACE estimate classes
| Class | Certainty | Typical basis |
|---|---|---|
| Class 5 | Lower certainty and confidence | Industry benchmarks. Still a rough estimate. |
| Classes 4 to 2 | Certainty rises as the project is defined | More studies and more project detail. |
| Class 1 | High certainty and confidence | A well-defined project with detailed studies, assessed rates and contractor quotes. |
AACE is the Association for the Advancement of Cost Engineering. The classes count down from 5 to 1. In the UK, the NSTA asks operators to give the AACE class of each decommissioning cost estimate.
The ARO is a number, not a description of activities: the current estimate of what the decommissioning liability will cost, at today’s value and on present-day assumptions. A producing asset has an ARO, and the ARO is revised periodically as assumptions change.
Cost information may also be discussed in NSTA asset stewardship reviews and, where relevant, during NSTA consultation on decommissioning programmes.
What is included in WBS 4, the facilities make-safe?
WBS 4, facilities and pipelines permanent isolation and cleaning, is the make-safe of the offshore asset. The NSTA survey guide lists what UK operators report under WBS 4: draining, flushing, purging and venting; engineering down, including physical isolation and de-energising; all cleaning costs, including pipeline pigging; and waste management.

Engineering down and clean (EDC) sits mainly in WBS 4. The core EDC work is generally the same on every asset: some form of well bay clearance; drain, clean, purge and vent; system segregation; and plug and abandonment (P&A) fluid handling. The facilitation projects that support EDC, such as nitrogen or added power generation, differ from asset to asset.
Where EDC-linked work is funded
The funding for EDC-linked work is spread across several elements. The examples are from the Lean Decom training.
| WBS | Example of EDC-linked work |
|---|---|
| 1 | Late-life study work. |
| 2 | Post-CoP works and utilities, such as hazardous and non-hazardous drains and instrument air, to prepare for CoP. |
| 3 | Well bay clearance and air gapping. |
| 4 | The core EDC: removing hydrocarbons and making the facilities safe. |
| 5 | Separating the process and utility systems between modules, ahead of removal. |
| 6 | Designing and installing the lift points that the heavy lift contractor will use for a single lift. |
EDC-linked work is spread through the whole of the OEUK WBS. EDC does not sit in one element alone.
Why the split matters
The contractors supplying the technical elements of EDC and the operator must work under one common structure, and know which part of the EDC project is funded by which WBS element. For UK cost reporting, the NSTA survey guide sets where each cost is reported: structural separation and reinforcement for removal go under WBS 6. See topside preparation and removal for WBS 5 and 6 in practice.
What does the decommissioning cost model look like?
The asset lifecycle cost model shows where decommissioning planning and activity sit in the life of an offshore asset, and how costs change from the first investment to the final removal.
Field development
High upfront capital expenditure as the infrastructure is built, before or around first production. The first cost spike.
Operations
Costs flatten into ongoing operating expenditure while the asset produces revenue. Acquisitions, divestments or further field development can shift cost, value and future liabilities.
Falling production, rising cost
Production falls as the reserves deplete, while OPEX rises, for example through maintenance. Costs eventually overtake revenue: the economic tipping point.
Preparing for decommissioning
The focus shifts from maximising economic recovery to preparing for decommissioning and cessation of production.
Decommissioning
Production and revenue stop, and a final cost spike follows to retire the asset safely and compliantly. Many costs continue with no revenue coming in.
The point in late life where operating costs become higher than the revenue generated, and producing is no longer economically feasible. The tipping point sets the economic life of the field and makes decommissioning planning more immediate.
Where the WBS fits
The WBS splits the cost of decommissioning (ABEX) into 11 elements, so the estimate can be built in a structured way. Once costs are allocated to WBS elements, the estimate class shows how confident the team is in each part of the estimate.
From the training: Lean Decom, Cost Model, Estimations and Financial Security Arrangements.
Get your information pack
Course details and free sample lessons, emailed to you.
How are decommissioning costs secured between joint venture partners?
Offshore assets are commonly owned by joint venture partners, so the future cost of decommissioning often sits with more than one company. Financial security arrangements protect the partners if one partner cannot pay. The example and the terms below are from the UK.
Two partners, one liability
Two companies own an offshore asset in UK waters, with an estimated decommissioning cost of £400 million. Each company has a 50% share, so each company’s liability is £200 million, before tax relief.
The risk is whether each partner will still be able to pay when the work happens. If one partner becomes insolvent, the other partners may be exposed to the unpaid cost. This is counterparty risk.
An agreement between the partners that defines what security is required, when the security is required, and what types of security are acceptable, so that each partner’s share of the liability is covered.
Common financial security arrangements
| Arrangement | How the arrangement works | Benefit | Drawback |
|---|---|---|---|
| Decommissioning trust fund | Money is placed in a dedicated trust, and stays available if a partner becomes insolvent. | Strong security, with the money clearly set aside for the purpose. | Ties up a large amount of capital that cannot be used elsewhere in the business. |
| Letter of credit or bank guarantee | A bank stands behind the company’s obligation, and pays if the company cannot. | Moves counterparty risk away from the company and to the bank. | The company usually pays the bank a fee. |
| Surety bond | An insurer or surety provider pays if the company cannot meet the obligation. | Avoids tying up cash, and can preserve banking lines a letter of credit would use. | Comes at a cost, priced on how risky the provider judges the company. |
| Parent company guarantee | A stronger parent company stands behind a subsidiary or related company. | No direct cash cost like a letter of credit, surety bond or trust fund. | Depends heavily on the financial strength of the parent company. |
Where to find the WBS guideline and current UK cost figures
The OEUK guidelines define the WBS, and reports from OEUK and the NSTA give current UK cost and performance figures.
Decommissioning Work Breakdown Structure Guidelines
The OEUK guideline on the elements of a decommissioning project and the activities within each element. Supplementary to the Guideline on Decommissioning Cost Estimation, Issue 3 (September 2013). Free to OEUK members; other readers can buy a copy. oeuk.org.uk
OEUK Decommissioning Report 2025
The annual OEUK report on decommissioning activity across the UK Continental Shelf, with the latest data on spend, activity levels and regional trends. Free to download. oeuk.org.uk
UKCS Decommissioning Benchmarking Report 2026
The NSTA report on actual UKCS decommissioning performance. The benchmarks focus mainly on the highest-cost work elements. nstauthority.co.uk
OEUK also runs member forums on decommissioning, including the Decommissioning Forum and the Decommissioning Benchmarking Task Finish Group, which develops benchmarking approaches across the WBS areas.
The WBS and decommissioning cost in the Lean Decom training
The training covers the WBS from OEUK, the cost model and financial security behind the numbers, and the contractor’s view of how EDC work maps onto the WBS. Each module is online and video-based, so you can learn at your own pace.

OEUK Work Breakdown Structure
The 11 elements of the WBS, the typical cost split, and how the WBS supports planning, reporting and benchmarking.

Cost Model, Estimations and Financial Security Arrangements
The asset lifecycle cost model, estimate classes, ARO and AFE, and the financial security used between partners.

Engineering Down and Clean
The phases of EDC, the facilitation projects, and how EDC work is located within the WBS elements.
Explore the training options →
Job titles and organisations are as given in the training.
Decommissioning cost terms
- Work breakdown structure (WBS)
- A framework published by OEUK, a UK trade association, that splits decommissioning into 11 standard elements for cost estimating, reporting and benchmarking.
- Cessation of production (CoP)
- The permanent end of production from an asset. Post-CoP running costs (WBS 2) start here.
- Engineering down and clean (EDC)
- The removal of bulk hydrocarbons, chemicals and hazardous energy from an offshore installation, so that the installation is safe for removal. Mainly WBS 4.
- ABEX
- Abandonment expenditure: the cost of decommissioning, the final cost spike in the life of an asset.
- ARO
- Asset retirement obligation: the current estimate of what the decommissioning liability will cost, at today’s value, revised periodically as assumptions change.
- AACE estimate class
- A scale from class 5 (lower certainty) to class 1 (high certainty). In the UK, the NSTA asks operators to give the AACE class of each decommissioning cost estimate.
- Decommissioning security agreement
- In the UK, an agreement between joint venture partners on the security each partner must provide for a share of the decommissioning liability.
Sources and further reading
- Lean Decom training: OEUK Work Breakdown Structure module, taught by Ricky Thomson, OEUK.
- Lean Decom training: Cost Model, Estimations and Financial Security Arrangements module, by Lean Decom.
- Lean Decom training: Engineering Down and Clean module, taught by Nigel Melling, Nexos; Subsea Infrastructure Removal and Site Remediation module, taught by Mike McHardy, DOF.
- Offshore Energies UK (OEUK): Decommissioning Work Breakdown Structure Guidelines. oeuk.org.uk
- Offshore Energies UK (OEUK): Guideline on Decommissioning Cost Estimation, Issue 3, September 2013. oeuk.org.uk
- Offshore Energies UK (OEUK): Decommissioning Report 2025. oeuk.org.uk
- North Sea Transition Authority (NSTA): UKSS Section Guide: Decommissioning, published 3 November 2025. nstauthority.co.uk
- North Sea Transition Authority (NSTA): UKCS Decommissioning Benchmarking Report 2026. nstauthority.co.uk
- North Sea Transition Authority (NSTA): UKCS Decommissioning Cost and Performance Update, published 13 August 2026. nstauthority.co.uk
The OEUK decommissioning WBS: common questions
What is the OEUK decommissioning WBS?
The OEUK decommissioning work breakdown structure (WBS) is a framework that splits a decommissioning project into 11 standard elements. Offshore Energies UK (OEUK), a trade association for the UK offshore energy industry, publishes the WBS, and UK operators use the 11 elements to estimate, report and benchmark decommissioning costs. OEUK describes the WBS as a guide, not a detailed project management tool.
What are the 11 elements of the decommissioning WBS?
1 Project management, 2 Post-CoP running costs, 3 Well decommissioning, 4 Facilities and pipelines permanent isolation and cleaning, 5 Topsides preparation, 6 Topsides removal, 7 Substructure removal, 8 Topsides and substructure onshore disposal, 9 Subsea infrastructure, 10 Site remediation, 11 Post-decommissioning monitoring. CoP means cessation of production.
What is included in WBS 4, the facilities make-safe?
WBS 4, facilities and pipelines permanent isolation and cleaning, covers the make-safe of the offshore asset: removal of hydrocarbons, pigging and engineering down. Engineering down and clean (EDC) sits mainly in WBS 4, and some EDC-linked work is funded under other elements, such as well bay clearance under WBS 3.
What share of decommissioning cost goes on wells?
On the UK Continental Shelf, well decommissioning (WBS 3) has historically accounted for approx. 50% of decommissioning cost, because plugging and abandoning wells needs high-cost rigs. Subsea infrastructure was 6% of actual spend in 2023 to 2025, and is 12% of forecast spend from 2026 onwards, according to the NSTA.
How does the WBS support NSTA cost reporting?
In the UK, operators report decommissioning cost information to the North Sea Transition Authority (NSTA) mainly through the annual UKCS Stewardship Survey, submitted through the UK Energy Portal, including actual and forecast costs. The survey asks for the costs under each of the 11 WBS categories, and for the AACE class of each estimate.
Is the OEUK WBS used outside the UK?
The OEUK guideline that sets out the WBS is written for offshore oil and gas facilities on the UK Continental Shelf. The Lean Decom training says operators and the supply chain in other regions now use the WBS as well, and that the WBS can be developed to suit any project in any region. Other countries have their own cost reporting rules.
Related topics
Get your information pack
Course details and free sample lessons, emailed to you.
Learn the decommissioning WBS from OEUK and from practitioners
Lean Decom is a specialist decommissioning training provider. The training shares lessons from North Sea projects, taught by 18 specialists, for you to apply to your own work.





