Substructure Removal: Cutting, Lifting and Recycling Offshore Jackets
Substructure removal is the stage of offshore decommissioning in which the structure that supports a platform topside, usually a steel jacket, is cut free and lifted away.
Weight of the Brae Bravo upper jacket in TAQA’s approved decommissioning programme, including 1,547 tonnes of marine growth. The approved method was removal in one piece.
TAQA, Brae Bravo Upper Jacket Decommissioning Programme, 2022below the natural seabed level: the pile cut depth UK regulator guidance tells operators to aim for when a jacket is removed in full.
UK regulator guidance notes (OPRED), 2018North-East Atlantic rule: only a steel jacket weighing more than 10,000 tonnes in air, placed before 9 February 1999, can be considered for a permit to leave the footings in place.
OSPAR Decision 98/3below lowest astronomical tide: the cut depth for the Brae Bravo upper jacket in TAQA’s approved decommissioning programme, approx. 38.5 m above the seabed.
TAQA, Brae Bravo Upper Jacket Decommissioning Programme, 2022What is substructure removal?
Substructure removal is the stage of offshore decommissioning in which the structure that supports a platform topside, usually a steel jacket, is cut free and lifted away. The jacket is cut at the piles below the seabed for full removal, or higher up where the rules allow the lower part to stay. A heavy lift vessel lifts the jacket in one or more lifts, and the jacket goes ashore for demolition, reuse and recycling.
Where this applies: The cutting and lifting methods on this page are used on steel jackets in any region. The removal rules described are OSPAR (North-East Atlantic) and UK examples, and the case study is from the North Sea. Other countries have their own regulator, rules and terms.
Key points
- Two common substructure types are the steel jacket and the concrete gravity based structure.
- For full removal, the piles are cut below the mudline. UK guidance tells operators to aim for 3 m.
- North-East Atlantic example: OSPAR Decision 98/3 provides for a permit to leave the footings of steel jackets of more than 10,000 tonnes in air placed before 9 February 1999.
- The Brae Bravo upper jacket, 11,600 tonnes in TAQA’s approved programme, was cut at minus 61 m and lifted in one piece.
- TAQA’s approved programme lists the Brae Bravo upper jacket as approx. 84% carbon steel by weight, with a plan to recycle 87%.
What is an offshore substructure?
The substructure is the support structure that the topside of a fixed installation rests on, connecting the topside to the seabed. Two common types are the steel jacket and the concrete gravity based structure.
A steel jacket is typically built from tubular steel members in a truss or lattice, typically held in place by piles driven into the seabed at the bottom of each leg. A concrete gravity based structure can weigh hundreds of thousands of tonnes and stays on the seabed under the weight of the concrete, which makes removal very challenging or impractical.
The Brae Bravo jacket supported 28 conductors, including caissons, J-tubes and risers. A number came out with the topside, but approx. six remained and had to come out with the jacket.
In the Offshore Energies UK (OEUK) Work Breakdown Structure, a UK cost framework, offshore substructure removal is element 7. Element 8, topsides and substructure onshore disposal, follows at the yard.

Full removal or derogation: can a jacket be left in place?
The answer depends on the region. In the North Sea, steel jackets are usually removed in full and concrete gravity based structures are usually left in place. The rules below are the OSPAR and UK example from the training.
| Structure, topside excluded | OSPAR Decision 98/3 (North-East Atlantic) |
|---|---|
| Steel jacket weighing less than 10,000 tonnes in air | Not in a derogation category. UK guidance: must be completely removed. |
| Steel jacket weighing more than 10,000 tonnes in air, placed before 9 February 1999 | A permit may be considered to leave all or part of the footings in place. |
| Steel jacket placed on or after 9 February 1999 | No footings derogation. UK guidance: must be completely removed. |
| Gravity based concrete installation | A permit may be considered to leave the installation wholly or partly in place. |
OSPAR Decision 98/3 prohibits leaving a disused offshore installation wholly or partly in place. A derogation is a permit from the national authority to leave part of a structure, issued only where an assessment shows significant reasons why leaving the structure is preferable to reuse, recycling or disposal on land, and after consulting the other OSPAR countries. The footings are the parts of a steel installation below the highest point of the piles.
How a derogation is requested in the UK
The operator carries out a comparative assessment that includes full removal. A derogation is considered only if the assessment shows significant reasons why leaving the footings in place is preferable to returning the footings to shore. The Offshore Petroleum Regulator for Environment and Decommissioning (OPRED) reviews the case, and the UK consults the other OSPAR countries before a permit is issued. The options are compared in a comparative assessment. See also OPRED and UK decommissioning regulation.
Outside the OSPAR area
Other countries have their own regulator, rules and terms. Worldwide, Resolution A.672(16) of the International Maritime Organization (IMO), adopted in 1989, sets guidelines and standards that governments are recommended to take into account: removal as the general requirement, exceptions decided case by case by the coastal state, and an unobstructed water column of not less than 55 m above a partly removed structure that does not project above the sea surface. A coastal state may set stricter requirements.
Why the Brae Bravo jacket was cut above the footings
Removing the jacket down to the seabed would have disturbed the drill cuttings pile, which contains oil-based mud. Each corner leg also had eight piles, 70 m long and driven 50 m into the seabed, and cutting the piles below the seabed would have needed substantial dredging. The upper jacket was cut at minus 61 m instead. TAQA’s approved programme gives the layout of the cross bracings and access for the cutting tools as the main reasons for that depth. Leaving the footings in place permanently needs a derogation, and TAQA’s approved programme for the upper jacket leaves the footings to a separate decommissioning programme.

How are jacket piles cut below the mudline?
For full removal, the piles that hold the jacket to the seabed are cut below the mudline, the surface of the seabed. UK regulator guidance tells operators to aim for 3 m below the natural seabed level, with allowance for seabed conditions and currents. Other countries set their own depth. Soil is first cleared so a cutting tool can reach the cut depth.


| External cutting | Internal cutting | |
|---|---|---|
| Typical tool | Diamond wire saw | Abrasive water jet cutting tool |
| Access | Excavation around the pile, down to the cut depth | Soil cleared inside the pile. The tool enters from the top of the pile or leg |
| The cut | A diamond-beaded wire runs at high speed through steel, grout and smaller conduits in one pass | A jet of water and abrasive cuts the wall from inside, with no mechanical parts passing through the leg |
| Dredging outside the pile | More | Less |
Two main systems are used to cut a jacket below the mudline: an internal abrasive water jet cutting tool and a diamond wire cutting tool. Internal cutting is preferred where possible, because internal cutting needs less dredging. External dredging adds time and cost, and a nearby drill cuttings pile could release hydrocarbons if disturbed.
UK example: the permit limits the dredging. The permit sets the area of seabed that may be disturbed. In one anchor pile removal, almost all of the permitted area was used on the first one or two of 12 piles, because the piles were not where the records said. A survey beforehand, or a contingency in the permit, would have helped.
How is a jacket prepared for removal?
Brae Bravo example: the team returned eleven months after the topside was removed, to make the unmanned jacket safe to work on and to weld on the lifting assemblies.
Remove the navigation aid
The navigation aid above the jacket came off first, so the aid would not interfere with the vessel’s navigation systems.
Install four work platforms
Temporary platforms designed to sit directly on the structure.
Access by basket, then gangway
Approx. six people arrived by basket to confirm the jacket was safe and to fit handrails, scaffolding and walkways. A gangway then allowed approx. 50 people on the jacket at any one time, a limit set under the UK safety case regulations and monitored electronically.
Lift over containers
Welding containers, safety containers for man-overboard or fire scenarios, and a break container.
Weld the lifting assemblies
Two large spreader beams welded to the top of the jacket: approx. two weeks of near-continuous welding and testing.
Secure everything still attached
Umbilicals, J-tubes and risers are secured before cutting, to prevent dropped objects.

On Brae Bravo, anything that fell into the sea had to be reported to the regulator, with best efforts made to recover the item. Know exactly what is on the jacket before going offshore.
Work stops when the ERRV is out of limits
An emergency response and rescue vessel (ERRV) stood by throughout the welding, ready to assist any rescue and monitoring the weather. When the weather was too poor to guarantee a rescue, the ERRV was out of limits for approx. 24 hours and operations were suspended.
How was the Brae Bravo upper jacket cut and lifted?
Brae Bravo was one of the largest platforms installed in the North Sea. The topside of approx. 35,000 tonnes was removed first. The upper jacket, 11,600 tonnes in TAQA’s approved programme, followed in one lift.
| Brae Bravo jacket | Figure |
|---|---|
| Water depth | 99.5 m |
| Full jacket | Approx. 22,000 tonnes on eight main legs |
| Cut elevation | Minus 61 m (38.5 m above the seabed). Approx. 70 m of structure removed |
| Upper jacket lifted | 11,600 tonnes in the approved programme, including 1,547 tonnes of marine growth |
| Subsea cuts | 31: 28 green and 3 red |
| Cranes | Two, each rated at 10,000 tonnes |
| Lift duration | Approx. 30 minutes |
Figures from TAQA’s approved Brae Bravo Upper Jacket Decommissioning Programme (2022) and the Lean Decom training.
Green cuts and red cuts are TAQA’s terms on Brae Bravo. A green cut does not affect the structural integrity of the jacket. After a red cut, the jacket could not survive poor weather, so the spreader beams, rigging and cranes must all be ready before the red cuts begin.
The subsea cuts
For every subsea cut, a remotely operated vehicle (ROV) first installed a cutting tool support frame. A separate diamond wire cutter was then installed by crane. Before the red cuts, the rigging was hooked up to the spreader beams and to both cranes.

Flooded members and free drainage
The lifting assemblies were engineered for a weight that assumes flooded steel members. Holes were drilled in some members so the members filled with seawater and the real weight matched the engineered weight. Water must also drain freely from the jacket during the lift.
The weather window
This lift needed a forecast maximum wave height under 2 m for five continuous days. Other projects may set different limits. The lift could in practice be done safely in 6 m: the safety margin engineered into the operation.
Transit to shore
Once lifted, the jacket hung clear of the water at a height set to suit the crane booms for the transit to Norway. All but one work platform stayed on the jacket, because removal onshore was easier.
What happens to a jacket once the jacket reaches shore?
On Brae Bravo, the topside and the upper jacket both went to a demolition yard in a deepwater fjord in Norway. The topside arrived a year before the jacket.

Laydown and transport
Because the yard sits in a deepwater fjord, the heavy lift vessel could come directly alongside the quay, avoiding the barge transfer that many other yards need. Self-propelled modular transporters (SPMTs) then moved each load further into the yard. SPMTs move slowly, so every move is planned in advance.
Toppling the upper jacket
The yard surface was prepared so the jacket could be toppled onto the ground in three sections. Wire was installed so each section could be pulled over by winch, then the final cut was made. At ground level, mobile machinery could reach the steelwork.


Front running
In the topside modules, teams first remove accessible materials such as copper cabling, loose pipework, televisions and light bulbs, sorted for disposal. Batteries are needed until disembarkation, so batteries stay on board and are removed at the yard.
Downsizing
A mobile shear handles smaller cutting and a static shear reduces larger sections. High-reach machines with claws bring steel down to ground level.
Sweepings
Cleaning the yard surface leaves piles of sweepings: fragments of metalwork, paint and cabling. Sweepings are sorted so the fragments are accounted for as waste.


Get your information pack
Course details and free sample lessons, emailed to you.
How much of a jacket is recycled?
Jackets are mostly steel, so a very high share can be recycled. Every installation is unique, and the share recycled depends on many factors. Each decommissioning programme must show how the waste hierarchy will be applied, and the operator states the share planned for reuse, recycling and disposal. The usual aim given in the training, across a whole asset, is at least 97% reuse, repurposing or recycling, with as little as possible going to landfill.
The Brae Bravo topsides project had a target of at least 95% reuse, recycling or energy recovery by weight, and reached 95.4% (TAQA close-out report). TAQA’s approved programme for the upper jacket lists approx. 84% of the weight as carbon steel and approx. 13% as marine growth, with a plan to recycle 87%. Steel is easy to smelt and reuse. Cut steel was compacted into bales and shipped to the north of Norway for smelting.
Hazardous materials from the topside
- Refractory ceramic fibre (RCF) passive fire protection bonds tightly to steel, needs powerful water jetting to remove, and becomes hazardous waste.
- NORM (naturally occurring radioactive material) in process pipework is cleaned out and collected into barrels.
- Smoke detectors, hundreds of them, each contain a radioactive element.
Because the asset came from UK waters, the radioactive waste had to be returned to the UK. Repatriation added high cost and time, so plan for repatriation early.

| Term | Meaning |
|---|---|
| Reuse | The same item used again for the same purpose. Brae Bravo: a lifeboat reused elsewhere. |
| Repurpose | The item put to a different use. |
| Recycle | The material processed into a new product. Brae Bravo: jacket steel smelted. |
Definitions from the Lean Decom training. The topside preparation and removal page covers the topside work.
What are the lessons learned from jacket removal?
The Brae Bravo lessons centre on understanding the asset and engaging early.
Vessels and contracts
Contract the ERRV early. Work cannot proceed without the ERRV, and any gap brings high-cost variation orders against the heavy lift contract. Engage the supply chain and put clear contracts in place.
Engineering and welding
Extra fabrication checks onshore can save significant time and cost offshore. Agree up front what counts as a passing weld, because standards for welding and non-destructive testing (NDT) can differ between operator and contractor. The marine warranty surveyor must also be satisfied before signing off the lift.
Regulators, birds and navigation aids
On Brae Bravo, TAQA shared plans early with the UK regulators and, for the Norwegian yard, the Norwegian Environment Agency. Fit bird deterrents in advance: in the UK sector of the North Sea, removing nesting birds needs a licence applied for beforehand. Choose a navigation aid tall enough to clear the waves and reliable all year.
Substructure removal in the Lean Decom training
The training follows the Brae Bravo upper jacket from preparation offshore to recycling at the yard, taught by the project manager responsible for the work. Two further modules cover the cutting tools and the onshore work. Each module is online and video-based.

Substructure Removal and Onshore Demolition
The Brae Bravo upper jacket: preparation, subsea cuts, the single lift, onshore demolition and material management.

Specialised Tooling
The tools used to cut and remove substructures, topsides and subsea infrastructure, and how the right tool reduces risk and cost.

Onshore Disposal, Reuse, Repurpose and Recycle
How recovered material is received, cleaned, classified and routed, and how the waste hierarchy recovers value.
Substructure removal terms
- Substructure
- The support structure that holds the topside and connects the topside to the seabed, such as a steel jacket or a concrete gravity based structure.
- Steel jacket
- A substructure of tubular steel members in a truss or lattice, typically held to the seabed by piles.
- Footings
- In OSPAR Decision 98/3, the parts of a steel installation below the highest point of the piles that connect the installation to the seabed.
- Mudline
- The surface of the seabed. Pile cut depths are measured below the mudline.
- Derogation
- Under OSPAR Decision 98/3, a permit to leave part or all of certain disused installations in place, as an exception to the general prohibition.
- Drill cuttings pile
- The mound of rock cuttings and drilling fluid residues left on the seabed from drilling the wells. Disturbing the pile may release hydrocarbons.
- Green and red cuts
- TAQA’s terms on Brae Bravo. A green cut does not affect the structural integrity of the jacket. After the red cuts, the jacket must be lifted.
- Front running
- Removing accessible materials such as cabling and loose pipework at the yard before heavy demolition starts.
Sources and further reading
- Lean Decom training: Substructure Removal and Onshore Demolition (Malcolm McCombie, TAQA).
- Lean Decom training: Specialised Tooling (David Ledingham, Claxton) and Onshore Disposal, Reuse, Repurpose and Recycle (Lee Vettese, ASCO).
- Lean Decom training: Decommissioning Overview: Heather and Thistle case study (Will Black and Ean Paul, EnQuest), Regulators and Regulations (Teresa Munro, OPRED), Permitting Lessons Learned and Efficiency Strategies (Gareth Jones, Xodus) and Offshore Oil and Gas Infrastructure and Locations (Lean Decom).
- OSPAR Decision 98/3 on the Disposal of Disused Offshore Installations. ospar.org
- OPRED: Guidance Notes, Decommissioning of Offshore Oil and Gas Installations and Pipelines, November 2018. gov.uk
- IMO Resolution A.672(16): Guidelines and Standards for the Removal of Offshore Installations and Structures on the Continental Shelf and in the Exclusive Economic Zone, 1989. imo.org
- TAQA: Brae Bravo Upper Jacket Decommissioning Programme, April 2022. gov.uk
- TAQA: Brae Bravo Topsides, Flare Bridge, Flare Tower and Flare Jacket Decommissioning Close Out Report, August 2023. gov.uk
Substructure removal: common questions
What does the decommissioning of substructures involve?
Decommissioning a substructure means preparing the jacket offshore, cutting the piles or the legs and members, lifting the jacket with a heavy lift vessel, and taking the jacket ashore for demolition and recycling. In the North Sea, concrete gravity based structures are usually left in place under a derogation.
How is an offshore jacket removed?
The jacket is cut free and lifted by a heavy lift vessel in one or several lifts. On Brae Bravo, lifting assemblies were welded to the jacket, the legs and members were cut subsea with diamond wire cutters, and the upper jacket was lifted in one piece and carried to a disposal yard.
Why are jacket piles cut 3 m below the mudline?
The 3 m figure is UK regulator guidance: operators should aim to cut piles 3 m below the natural seabed level, with allowance for seabed conditions and currents, so that the remains are unlikely to become uncovered. Other countries set their own depth.
Can a steel jacket be left in place?
The answer depends on the region. In the North-East Atlantic, OSPAR Decision 98/3 provides for a permit to leave the footings of a steel jacket weighing more than 10,000 tonnes in air and placed before 9 February 1999. Smaller and newer steel jackets have no such category. Other countries have their own regulator, rules and terms.
What are green cuts and red cuts?
Green cuts and red cuts are TAQA’s terms on Brae Bravo. A green cut does not affect the structural integrity of the jacket. After a red cut, the jacket could not survive poor weather, so the lift must be ready before the red cuts begin. Brae Bravo needed 28 green cuts and 3 red cuts.
How much of a jacket is recycled?
Jackets are mostly steel, so a very high share can be recycled. TAQA’s approved programme lists the Brae Bravo upper jacket as approx. 84% carbon steel by weight, with a plan to recycle 87%.
Related topics
Get your information pack
Course details and free sample lessons, emailed to you.
Learn substructure removal from the people who plan and deliver the work
Lean Decom is a specialist decommissioning training provider. The training shares lessons from North Sea projects, taught by 18 specialists, for you to apply to your own work.



