Topside Preparation and Removal in Offshore Decommissioning
Topside preparation and removal covers the work to clean and de-energise a platform topside, separate the topside from the jacket and lift the topside away for dismantling onshore.
Weight of the Brae Bravo topside in the approved decommissioning programme, in 28 modules. TAQA removed the topside in 2021.
Brae Bravo decommissioning programme, 2018, and TAQA close-out report, 2023UK example: approx. share of decommissioning cost spent on topside preparation and removal in a typical year.
Lean Decom trainingUK example: the revised safety case for dismantling a fixed installation must reach the regulator at least three months before dismantling starts, unless the regulator sets a shorter period.
Offshore Installations (Offshore Safety Directive) (Safety Case etc.) Regulations 2015, regulation 20of the Brae Bravo topside material was reused, recycled or sent for energy recovery.
TAQA close-out report, 2023What is topside preparation and removal?
Topside preparation and removal is the stage of offshore decommissioning in which the topside of a fixed platform is cleaned and de-energised, separated from the jacket and lifted away for dismantling onshore. Preparation covers de-energisation, engineering down and clean, facilitation projects and structural work. Removal uses one of three methods: single lift, reverse installation or piece small.
Where this applies: The preparation steps and removal methods on this page are used on fixed platforms in any region. The case studies, cost share and regulations are UK North Sea examples from the training. Other countries have their own regulator, rules and terms.
Key points
- There are three removal methods: single lift, reverse installation and piece small.
- A topside declared hydrocarbon free can still hold residual hydrocarbons.
- The Brae Bravo topside, approx. 35,000 tonnes in 28 modules, was removed by reverse installation in 2021.
- Anything missing from the materials inventory becomes a variation order.
- 95.4% of the Brae Bravo topside material was reused, recycled or sent for energy recovery.
- UK example: topside preparation and removal is approx. 10 to 12% of decommissioning cost, in elements 5 and 6 of the Offshore Energies UK (OEUK) Work Breakdown Structure.
What is topside removal in offshore decommissioning?
On a fixed offshore platform, the topside is the structure that sits on the jacket or other substructure: the process and utility modules, the drilling derrick, the accommodation, the helideck and the cranes. Topside structure removal takes that structure off the substructure and brings the structure ashore for dismantling, recycling and disposal.
Heavy lift vessels are high cost and booked for a set period, so work left until the vessel is alongside adds significant cost.
Floating units, including floating production, storage and offloading units (FPSOs), are instead disconnected and towed away, for example to a port, a mooring location or a disposal facility, for reuse on another project or for disposal. See FPSO decommissioning and substructure removal.
Rules on what must be removed differ by country. One example: OSPAR Decision 98/3 applies in the North-East Atlantic, including the North Sea, and UK regulator guidance on the Decision states that the topsides of all installations must be returned to shore.

Where topside work sits in the WBS
In the OEUK Work Breakdown Structure (WBS), a UK cost framework, cleaning falls under element 4. Element 5, topside preparation: removing infrastructure or adding rigging points so the topside can be removed safely. Element 6, topside removal: lifting the topside off the substructure with heavy lift vessels, or with smaller construction vessels that remove parts one at a time. See the OEUK Work Breakdown Structure.
The EPRD contract
On Brae Bravo, TAQA used a lump sum EPRD contract: engineering, preparation, removal and disposal. The contract gave cost certainty and removed the interface between the heavy lift vessel contractor and the disposal yard.
How is a topside prepared for decommissioning?
Topside preparation for decommissioning starts long before the heavy lift vessel arrives: the wells are plugged and abandoned, the topside is cleaned and de-energised, and every connection that would stop a lift is separated.
De-energisation
De-energisation identifies, then removes or neutralises, every significant source of energy: hydrocarbons, but also springs in actuated valves, radioactive sources in level instruments, batteries and the passenger lift counterweight. Any source left behind goes on a stored energy register for the removal contractor. See the disembarkation procedure.
Engineering down and clean (EDC)
Engineering down and clean removes bulk hydrocarbons, chemicals and hazardous energy so the topside is inert. EDC activities are key activities for de-energisation. The four phases follow a set order, because each phase enables the next.

Well bay clearance
Clear the equipment and pipework around each well slot so the wells team can work.
Drain, clean, purge and vent
Flush with water, chemicals or steam, purge vapours with an inert gas such as nitrogen, and vent all pressure.
System segregation
Physically disconnect pipework and cables to leave an air gap between systems.
P&A fluid handling
Keep one last fluid route to push residual inventory down the wells or into export lines.
Hydrocarbon free does not mean that no hydrocarbons remain. Cleaning removes high levels of hydrocarbons, but residual hydrocarbons may still be present. At the time of filming, no industry-wide acceptance criteria existed for the gas test that follows flushing and purging, so each operator typically sets the criteria. EnQuest steam cleaned the Heather platform, pushing hydrocarbons through the system for capture and removal ashore. Export pipelines are cleaned and physically disconnected, so the platform is isolated from other assets.
Facilitation projects and weight control
Facilitation projects are enabling work that supports EDC and well plug and abandonment, and differ on every asset: nitrogen to blanket flare systems, temporary diesel generators, structural strengthening, new gratings and handrails, and crane upgrades for the high volume of lifts.
Weight control also drives facilitation work. Each heavy lift vessel has a weight limit, so access platforms or even a whole module may have to come off before a single lift.


Hazardous materials
Before cutting and hot work begin, the hazardous materials on the topside must be known and planned for.
- NORM (naturally occurring radioactive material) in any component that carried production fluids.
- Synthetic radioactive sources, such as cobalt or caesium, in measuring devices. Old exit signs may contain tritium.
- H2S from sour wells, monitored together with benzene.
- Mercury, at far higher concentrations in basins in Thailand, Malaysia and Australia than in the North Sea.
- Heavy metals in residues, plus asbestos, coatings and refractory ceramic fibres.
What are the methods of topside removal?
The training sets out three methods: single lift, reverse installation and piece small. The choice depends on the size and weight of the topside, the vessels able to make the lift and the preparation each method needs.
Single lift
A heavy lift vessel with enough capacity lifts the whole topside off the jacket in one lift.
- Caissons, risers, conductors, cables and discharge lines are separated, often with new supports so nothing falls into the sea.
- The legs are cut. On Heather, 10 legs were cut and bearing brackets were welded onto 8 legs.
- For leg cuts, Claxton commonly uses an abrasive water jet or a diamond wire saw. Claxton calls the short period after the vessel has taken the weight, when the final cut is made, the red zone.
- The topside may need strengthening, because the lift loads the structure differently from installation.
Reverse installation
Reverse installation, or reverse install, lifts the modules off one by one: the reverse of how a modular topside was installed.
- Modules are separated by cutting the cables, piping and walkways between them.
- No structural steel for a single lift is needed.
- The vessel stays on site longer, or makes several trips. Used on Thistle (EnQuest) and Brae Bravo (TAQA).
Piece small
The topside is cut up offshore into pieces small enough for the platform cranes to lift off.
- A long process, with a very large number of lifts, and every lift carries risk.
- The crew must be housed while the accommodation is removed, which may mean a flotel.
- TAQA judged piece small unsuitable for Brae Bravo.



How is the removal method chosen?
A topside of approx. 35,000 tonnes is far heavier than the two 10,000 tonne cranes of the heavy lift vessel used on Brae Bravo can lift, so a single lift would have needed a specialist single-lift vessel. A single lift also needs structural steel, usually installed low on the platform, with rope access work that carries safety risk and adds time.
For Brae Bravo, reverse installation proved the most efficient suitable method. Avoiding the structural steel was one factor, but the final decision was financial, reached during the tender.
Brae Bravo case study: how was a 35,000 tonne topside removed?
Brae Bravo was one of the largest topsides in the North Sea: approx. 35,000 tonnes in 28 modules, on an eight-legged steel jacket in approx. 100 m of water in the central North Sea. The flare sat on a separate jacket at the end of a 170 m bridge, and the flare, bridge and flare jacket all had to be removed.
Before removal, production had ceased, the wells were plugged and abandoned, and the platform was de-energised and disembarked. Planning began in 2011, and removal began in 2021. A live bypass gas line ran around the platform, so dropped objects were a significant consideration for every lift.

Planning and the contract
The removal method and the contractor were chosen through an invitation to tender (ITT). The UK regulator approved the decommissioning programme in August 2018. A lump sum EPRD contract went to a consortium of a heavy lift vessel owner and a yard in Norway.
The contract was signed in 2018, before disembarkation, so the contractor could advise how to leave the platform. The contractor spotted scaffold boards on top of gratings, which took two months to remove while the crew was on board. With the vessel alongside, the same work would have been a significant added expense. The zones where the modules were to be separated were also left clear of stored items.


Execution, step by step
These are the key steps highlighted in one of the case studies featured in the Lean Decom training, where the topside was removed by reverse installation, module by module, with a heavy lift vessel.
Make the platform safe
A small team checks gratings for holes and fallen items. Mobile cranes, workshops and power follow.
Separate the modules
Cables, piping and walkways between modules are cut, work known on the project as splicing. Every pipe gets a pilot hole first, even former air or seawater lines, to check for hydrocarbons before hot work.
Remove the flare
The flare tower, bridge and flare jacket come out in a first campaign, with the flare jacket lifted clear of the live bypass line.
Trip one
In the second campaign, modules are lifted one by one until the vessel deck is full. The drilling derrick module, with a higher centre of gravity, needed particular care. The last lift is the module support frame (MSF), with two process modules left on top to save lifts.
Trip two
A navigation aid on a 13 m column marks the jacket first. The second half then comes off the same way.
Use the vessel while the vessel is in the field. In June 2022, the heavy lift vessel that removed the Brae Bravo upper jacket also removed the West Drilling Rig from the nearby Brae Alpha platform, avoiding a dedicated trip.
Why does the materials inventory matter in topside removal?
The materials inventory tells the contractor what is to be removed, and how much time and effort the removal will take. The inventory is a key document for the invitation to tender, and should be complete and as accurate as possible before the tender goes out. Anything missing generates a variation order.
What a good materials inventory covers
What happens to a topside onshore? Demolition and disposal
Onshore demolition turns the modules back into materials for reuse, recycling or disposal.
The Brae Bravo topside went to a yard in a deepwater fjord in Norway, where the heavy lift vessel could set modules straight onto the quay, with no barge transfer. Self-propelled modular transporters (SPMTs) moved the modules through the yard. Dismantling ran from May 2021 to February 2023, and 95.4% of the material by weight was reused, recycled or sent for energy recovery (TAQA close-out report).
Front running
Copper cabling, loose pipework and other accessible items come out first. Radioactive smoke detectors and NORM-contaminated waste had to go back to the UK, the country of origin.
Downsizing
Shears and high-reach machines cut the steel into manageable pieces. Some sections were brought down with explosives.
Material management
Refractory ceramic fibres needed powerful water jetting to remove. A lifeboat went for reuse, and cut steel was baled for smelting.


SPMTs must be in place in advance, and heavy cranes need several days to set up and remove. A port chosen only for sail time can add onshore craneage. Extra notice lets the supply chain plan ahead and reduce avoidable costs.
Local rules at the disposal site can add challenges. For Brae Bravo, repatriating radioactive waste to the UK added high cost and time. The team returned for the upper jacket 11 months after the topside was removed. See substructure removal.
Get your information pack
Course details and free sample lessons, emailed to you.
What are the main risks during topside preparation and removal?
Hot work, heavy lifts, changing escape routes and schedule pressure overlap during topside preparation and removal.

Residual hydrocarbons and hot work
A declaration of hydrocarbon free does not mean that no hydrocarbons remain. Residual hydrocarbons can be present while a large amount of hot work takes place, so work parties must stay alert to fire and explosion. Well work may run in parallel, with heavy lifts of corroded risers and conductors.
Changing escape routes
Walkways are removed as work progresses and escape routes can change daily, so check the escape routes before every activity.
Schedule pressure
The vessel is booked for a specific time. Pressure to be ready, real or perceived, can lead to incidents.
High tempo on deck
Heavy backloading puts deck crews under pressure.
New crews and specialists
Many new people work on board at once, so communication of risks is vital.
Dropped objects
On Brae Bravo, anything that fell into the sea had to be reported to the regulator, with best efforts made to recover the item.
Nesting birds
UK example: a nesting bird can stop a removal. A licence needs at least two years of survey data, and a missed vessel slot can mean waiting another year.
What are the lessons learned from topside removal?
The Brae Bravo lessons concern early decisions on dates, contracts and vessels.
Lock in the CoP date
Permits and licences are time-bound. Each time the cessation of production (CoP) date moves, the permits must be applied for again.
Secure the ERRV early
The market for emergency response and rescue vessels (ERRVs) can be tight, and without an ERRV the work cannot go ahead.
Place the navigation aid with care
On Brae Bravo, the exhaust stack shaded the solar panels. In late winter the navigation aid ran out of power, and a guard vessel was needed.
Bring the contractor on board early
A contract signed before disembarkation helps avoid disputes over variation orders later.
Engage regulators early
On Brae Bravo, sharing plans early with the UK regulators and the Norwegian Environment Agency led to faster permitting.
Topside preparation and removal in the Lean Decom training
The training covers topside work from cleaning the plant to the demolition yard, taught by the specialists who delivered the work. Each module is online and video-based.

Topside Removal: Brae Bravo case study
Removal methods, the EPRD contract and a 35,000 tonne reverse installation.

Engineering Down and Clean
The four phases of EDC, and the facilitation projects that support them.

Onshore Disposal, Reuse, Repurpose and Recycle
Hazardous materials, waste management and onshore handling costs.
Topside removal terms
- Topside
- The part of a fixed installation that sits on the substructure: the decks and modules for processing, drilling, utilities and accommodation.
- EPRD contract
- Engineering, preparation, removal and disposal in one contract.
- Single lift
- Removal of the whole topside in one lift by a heavy lift vessel with enough capacity, after the legs are cut.
- Reverse installation
- Removal of a modular topside one module at a time, the reverse of the original installation.
- Piece small
- Cutting the topside up offshore into pieces small enough for the platform cranes to lift.
- Module support frame (MSF)
- The frame on which the other topside modules sit.
- Materials inventory
- The list of what is to be removed, issued with the invitation to tender.
- Engineering down and clean (EDC)
- Removing bulk hydrocarbons, chemicals and hazardous energy so the asset is inert.
Sources and further reading
- Lean Decom training: Topside Removal: Brae Bravo case study (Kevin McSweeney, TAQA) and Substructure Removal and Onshore Demolition (Malcolm McCombie, TAQA).
- Lean Decom training: Engineering Down and Clean (Nigel Melling, Nexos), De-energisation of Offshore Installations (Mark Wilson, TAQA), Decommissioning Overview: Heather and Thistle case study (Will Black and Ean Paul, EnQuest), OEUK Work Breakdown Structure (Ricky Thomson, OEUK), Onshore Disposal, Reuse, Repurpose and Recycle (Lee Vettese, ASCO), Specialised Tooling (David Ledingham, Claxton), Safety and Risk Management (Graham Skinner, OEUK) and Permitting Lessons Learned and Efficiency Strategies (Gareth Jones, Xodus).
- TAQA: Brae Bravo Topsides, Flare Bridge, Flare Tower and Flare Jacket Decommissioning Close Out Report, August 2023. gov.uk
- OPRED: Guidance Notes, Decommissioning of Offshore Oil and Gas Installations and Pipelines, November 2018. gov.uk
- OSPAR Decision 98/3 on the Disposal of Disused Offshore Installations. ospar.org
Topside preparation and removal: common questions
What is topside removal in decommissioning?
Topside removal is the removal of the topside of a fixed platform from the substructure, using heavy lift vessels, smaller construction vessels or the platform cranes. The topside goes ashore for dismantling, reuse, recycling and disposal.
What are the methods of topside removal?
The training describes three methods. Single lift removes the whole topside in one lift with a heavy lift vessel that has enough capacity. Reverse installation removes the modules one by one. Piece small cuts the topside into pieces small enough for the platform cranes to lift, a long process with a very large number of lifts.
What is reverse installation (reverse install) of a platform topside?
Reverse installation removes a modular topside one module at a time, the reverse of the original installation. The modules are separated by cutting cables, piping and walkways, then lifted onto a heavy lift vessel or a barge. The Brae Bravo topside was removed this way in 2021.
How is a topside prepared for decommissioning?
Topside preparation for decommissioning includes de-energisation, engineering down and clean, facilitation projects such as temporary power and structural strengthening, and separating the topside from the jacket or the modules from each other.
What happens to a topside after removal?
The topside goes to an onshore yard. Accessible materials are removed first, then the steel is cut down and sorted for reuse, recycling or disposal. For Brae Bravo, 95.4% of the material was reused, recycled or sent for energy recovery.
Related topics
Get your information pack
Course details and free sample lessons, emailed to you.
Learn topside removal from the people who planned and delivered the work
Lean Decom is a specialist decommissioning training provider. The training shares lessons from North Sea projects, taught by 18 specialists, for you to apply to your own work.





